Schultz v. Mueller

159 N.W.2d 63, 159 N.W.2d 68, 39 Wis. 2d 216, 1968 Wisc. LEXIS 981
CourtWisconsin Supreme Court
DecidedJune 4, 1968
Docket272
StatusPublished
Cited by1 cases

This text of 159 N.W.2d 63 (Schultz v. Mueller) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schultz v. Mueller, 159 N.W.2d 63, 159 N.W.2d 68, 39 Wis. 2d 216, 1968 Wisc. LEXIS 981 (Wis. 1968).

Opinion

Hanley, J.

Defendant contends that she should be granted a new trial: (1) Because the jury verdict was perverse as being contrary to the law and to the evidence; and (2) in the interest of justice.

The defendant put in evidence tending to show that the driveway was graded in a defective manner so that the driveway gate on the fence surrounding her property would no longer open inward and that the driveway was already cracked. (The trial occurred roughly two years after Mr. Schultz ceased working on the defendant’s premises.) There was also testimony tending to show that the agreement called for a two-level patio although the patio as built contained only one level. In addition, *219 sand was washing away from under the patio blocks; and the blocks had become uneven.

An expert witness for the defendant, Paul Yuker, a contractor, gave testimony concerning both the driveway and the patio. He stated that the driveway could have been constructed so that the gate would open inward by establishing a steeper grade for the first 40 feet and a lesser grade for the last 20 and that the cracks were the result of the improper placement of expansion joints. In his opinion the driveway was constructed “sloppily” and without a grade having been established. He estimated that it would cost the defendant $900 to correct the situation, for the present driveway would have to be removed and a new one constructed. With respect to the patio, Yuker testified that very few of the blocks were even with each other, and the sand has washed out from under the blocks, the result being that the blocks themselves have almost washed away. He stated that he could not see that any provision had been made for drainage. In his opinion the patio would have to be done over in order to achieve the proper result, which would require the reestablishment of a grade and the construction of a retaining wall. He estimated the cost of rebuilding the patio at from $600 to $700.

The plaintiff’s testimony tended to show that in installing the driveway he had to work with the existing grade of the gravel driveway that had been previously installed unless the south half of the front yard was to be resodded. Further, he testified that the fence gate was an adjustable type, but that defendant objected to the adjustment because it would allow her pet dog to escape from her yard. He also maintained that while the parties at one time considered a two-level patio, defendant concurred in his suggestion to construct the patio with one level only. He also testified that he installed a drainage pit seven or eight feet from the west end of the rear of the garage and put in pipes from the downspout to the pit. Concerning defendant’s complaint that sand and *220 gravel were washing away, plaintiff testified that he had originally corrected the situation but that it could recur until the ground settles. According to him the way to correct it is to put in additional drainage stone and to restore the patio blocks to the level of the established grade. He indicated that no retaining wall was constructed for the patio because it was not figured in the price for which he agreed to do the work.

Three expert witnesses, Nick Chenenoff, William Hingiss, and George Campfield, all of them contractors, testified on behalf of the plaintiff. Chenenoff observed both the driveway and the patio and testified that both were constructed in workmanlike fashion. In his opinion the sand and gravel washed away from underneath the patio blocks because of the settling process. Hingiss and Campfield both testified that the driveway was constructed in a workmanlike manner.

Against this backdrop of conflicting evidence, defendant contends that plaintiff should not be allowed to recover the entire unpaid balance of the contract price because expert witnesses for both sides conceded that more work was needed to be done to complete the contract. In addition to the previously recounted testimony of Yuker, she calls the court’s attention to Campfield’s testimony that the patio could be repaired at a cost of $35 and to Chenenoff’s testimony that the cracks in the driveway could be repaired for $10. Further, she contends that a letter from Mr. D’Amato, one of plaintiff’s attorneys, to Mr. Hajduch, defendant’s attorney, constitutes an admission that plaintiff never completed the contract.

The circumstances under which such testimony was elicited indicate that the plaintiff’s experts made no concession of any kind in testifying to such dollar amounts. The testimony was given on rebuttal — after Mr. Yuker testified that remedying the defects in workmanship would cost from $1,500 to $1,600. The questions eliciting *221 the dollar amounts were qualified in such a manner to show that no concession was intended. 1 The testimony of the plaintiff’s experts was not only important to the issue of the amount of damages provable under defendant’s counterclaim but also to his own recovery; for, if the trier of fact were to believe that defects existed and believed plaintiff’s rather than defendant’s estimates as to the cost of repair, recovery might have been had by the plaintiff under a theory of substantial performance for the balance of the contract price, minus any damages caused by any defects in performance. In that event, defendant’s counterclaim insofar as it sought recovery for the failure to perform the contract would have had to be dismissed.

The letter in question suggested that plaintiff would do what is necessary to complete the work provided that the defendant would place the money due him in escrow. The letter was placed in evidence by the plaintiff along with a letter from Mr. Hajduch to Mr. D’Amato apparently to show that the defendant continuously denied the plaintiff access to the property. It is doubtful that this attempt to settle the dispute was intended to admit any facts; and conceding for the purposes of a discussion only that it was an admission, it would be for the trier of fact to weigh along with the other evidence.

*222 It appears that the main dispute between the parties with respect to the work done pursuant to the contract was not so much over the existing condition of the improvements (although the testimony varies as to the condition of the driveway), but rather over whether their condition indicated that Mr. Schultz performed his work in a workmanlike manner. In this the evidence was in sharp dispute. The trier of fact chose to believe the plaintiff's rather than the defendant’s evidence. It could have concluded that the driveway gate being adjustable, its failure to open inward did not constitute a defect; it could have concluded that plaintiff was justified under the contract in using the existing grade in the construction of his driveway. It may have found that the driveway cracks were not substantial or that they were not caused by faulty construction on the part of the plaintiff. Concerning the patio, it could have considered that a retaining wall was not contracted for and that the washing away of the sand and gravel was due to normal settling and therefore not the responsibility of the plaintiff. In sum, there was ample credible evidence to sustain a finding of fact favoring either the plaintiff or the defendant on the question of workmanlike performance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Cardenas-Hernandez
571 N.W.2d 406 (Court of Appeals of Wisconsin, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
159 N.W.2d 63, 159 N.W.2d 68, 39 Wis. 2d 216, 1968 Wisc. LEXIS 981, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schultz-v-mueller-wis-1968.