Schultz v. County of Chippewa

57 N.W.2d 158, 238 Minn. 392, 1953 Minn. LEXIS 571
CourtSupreme Court of Minnesota
DecidedFebruary 13, 1953
DocketNo. 35,854
StatusPublished
Cited by10 cases

This text of 57 N.W.2d 158 (Schultz v. County of Chippewa) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schultz v. County of Chippewa, 57 N.W.2d 158, 238 Minn. 392, 1953 Minn. LEXIS 571 (Mich. 1953).

Opinion

Knutson, Justice.

This is an appeal from a judgment entered pursuant to findings of fact, conclusions of law, and order for judgment after trial by the district court of an appeal from an order of the county board dismissing a petition for the improvement of a county ditch.

County ditch No. 9 of Chippewa county was established in 1907 and constructed shortly thereafter. It was a rather shallow “bull ditch” constructed by pulling a large plow with a capstan, which resulted in a ditch of uniform depth over its course, the plow cutting the same depth without regard to grade as it was pulled over the contour of the land. It was intended to drain an area of about eight square miles. It emptied into a natural watercourse known as Dry Weather Creek, which in turn emptied into the Chippewa River.

In 1916, county ditch No. 22 was established by the county board of Chippewa county and was constructed about 1920. That ditch commenced some two or more miles from the confluence of Dry Weather Creek and the Chippewa River and followed the bed of the creek some distance beyond the point where ditch No. 9 emptied into the creek. It was constructed so as to drain some 80 square [394]*394miles of land. It was a fairly large open ditch, having a ten-foot bottom below the point where ditch No. 9 emptied into it and an eight-foot bottom above that point.

On July 26, 1946, a petition was filed for the establishment of county ditch No. 53. The main course of this proposed ditch was to follow the course of old ditch No. 9, but it included several additional laterals and was intended to drain a number of potholes and sloughs which had not been drained by ditch No. 9. It is fair to say that it was intended to drain the same area as ditch No. 9 but more effectively. While old ditch No. 9 had a. bottom width of about 18 inches, ditch No. 53 was to have a bottom width of about four feet. It was also to be much deeper and constructed to grade. On May 1, 1947,. after proper notice, the county board met to consider the petition at a preliminary hearing. The board then found that the ditch was necessary and practical, that it would be a public benefit and promote the public health, and that it had a sufficient outlet. The board ordered a detailed survey made by an engineer. After receiving the engineer’s report of his survey, the county board met again on November 3, 1949, after proper notice to interested parties. Thereafter the board made and filed its order rejecting the petition on the ground that the proposed system “is not practicable and will not be of public benefit and utility.” An appeal was taken to the district court. After a trial, the court affirmed the order of the county board dismissing the petition. Judgment was entered, and this appeal followed.

In its findings, the court determined that Dry Weather Creek, ditch No. 22, and ditch No. 9 are all partly obstructed by natural growths and silt and that ditch No. 22 does not now have sufficient capacity to carry the water that is presently being drained into it which results in frequent flooding of land adjacent to it. The court also found that the benefits which would result from the construction of ditch No. 53 exceed the damages, “but that this does not take into consideration the lands lying below the outlet of said ditch and that said lower lands would be damaged to a considerable extent by the construction of County Ditch No. 53.” The court also found [395]*395that proposed ditch No. 58 is necessary, “but that it would not be of public benefit or utility, nor would it have a sufficient outlet.”

Subsequent to the filing of the petition and prior to the determination of the county board, one Isaac U. Eichelberger acquired a tract of land which would be within the drainage area of the proposed ditch. He was one of the county commissioners of Chippewa county and was present when the county board acted upon the petition. The trial court found that he had taken no part in the proceedings.

Appellants state as the only question involved in the appeal that “The Court erred in upholding the action of the County Board,” without specifying in what respect the court erred. This is not in compliance with our rules. We apprehend that the questions presented are these:

(1) Does M. S. A. 106.531, requiring consent to use an established ditch as an outlet for a proposed lateral, have any application to the facts of this case?

(2) Once the right to use ditch No. 22 as an outlet for ditch No. 9 has been acquired, may the court interfere with that right when ditch No. 9 is enlarged by the construction of a new ditch intended to drain the same area but having greater capacity than the old ditch?

(3) May the trial court, on appeal from an order of the county board, try the case de now ?

It is the contention of appellants that inasmuch as the petition here involved was filed on July 26, 1946, L. 1947, c. 143, § 53 (M. S. A. 106.531),2 has no application because of the saving clause [396]*396contained in § 67 of tbe 1947 act.3

We think that it is immaterial whether the 1947 act or the former law is applicable. Irrespective of statute, we have held on numerous occasions that once a ditch system is established owners of land who have recovered damages or have been assessed benefits for its construction have a property right in the maintenance of the ditch in the same condition as it was when originally established which right cannot be divested without due process of law. In re Petition of Jacobson re County Ditch No. 24, 234 Minn. 296, 48 N. W. (2d) 441; In re Petition for County Ditch No. 15, 238 Minn. 15, 55 N. W. (2d) 305.

And the fact that the landowners whose lands are drained by ditch No. 9 had acquired the right to an outlet for that ditch into [397]*397ditch No. 22 does not confer upon them the right to use ditch No. 22 as an outlet for the proposed ditch No. 53. Whether we consider ditch No. 53 an entirely new ditch or drainage system or we consider it an enlargement or improvement of ditch No. 9, it is clear from the evidence that it will carry the spring runoff as well as surface water in times of excessive rainfall into ditch No. 22 much faster and in greater volume than ditch No. 9 is capable of doing. The court’s finding that ditch No. 22 and its outlet in Dry Weather Creek are now inadequate to carry the water drained into them is amply sustained by the evidence. The inevitable conclusion is that the construction of the proposed ditch will cause water from the spring runoff and the runoff of surface water in times of excessive rainfall to drain into ditch No. 22 much faster than it now does from ditch No. 9. As far as the rights of landowners adjacent to ditch No. 22 are concerned, the same rule should apply whether the likely damage is to result from the use of the established ditch as an outlet for an enlarged old ditch or from its use as an outlet for a new ditch. It matters little to the landowners adjacent to ditch No. 22 whether their lands are flooded on account of water coming from an entirely new source or from the acceleration of drainage from an old source. The invasion of their property rights is the same in either event. See, In re Petition for County Ditch No. 15, 238 Minn. 15, 55 N. W. (2d) 305.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Madison v. Commissioner of Public Safety
585 N.W.2d 77 (Court of Appeals of Minnesota, 1998)
Titrud v. Achterkirch
213 N.W.2d 408 (Supreme Court of Minnesota, 1973)
In Re Petition of Schwermann v. Reinhart
210 N.W.2d 33 (Supreme Court of Minnesota, 1973)
In Re Establishment of Judicial Ditch No. 17
263 Minn. 547 (Supreme Court of Minnesota, 1962)
Johnson v. Hedtke
117 N.W.2d 392 (Supreme Court of Minnesota, 1962)
Rekedall v. County of Redwood
102 N.W.2d 682 (Supreme Court of Minnesota, 1960)
In Re Petition of Lippmann
81 N.W.2d 100 (Supreme Court of Minnesota, 1957)
State Ex Rel. Mosloski v. County of Martin
80 N.W.2d 637 (Supreme Court of Minnesota, 1957)
Oelke v. County of Faribault
70 N.W.2d 853 (Supreme Court of Minnesota, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
57 N.W.2d 158, 238 Minn. 392, 1953 Minn. LEXIS 571, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schultz-v-county-of-chippewa-minn-1953.