Schuepfer Plumbing Inc. v. State

52 Ill. Ct. Cl. 151
CourtCourt of Claims of Illinois
DecidedAugust 31, 1999
DocketNo. 91-CC-3407
StatusPublished

This text of 52 Ill. Ct. Cl. 151 (Schuepfer Plumbing Inc. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schuepfer Plumbing Inc. v. State, 52 Ill. Ct. Cl. 151 (Ill. Super. Ct. 1999).

Opinion

ORDER

Frederick, J.

This cause comes before the Court on Claimant’s motion for summary judgment and Respondent’s cross-motion for summary judgment, and the Court having reviewed all of the pleadings and exhibits, heard the arguments of counsel, and the Court being fully advised in the premises, wherefore, the Court finds:

Claimant filed its verified complaint in the Court of Claims on May 21, 1991. After a motion to dismiss was denied, the parties engaged in considerable discovery. The parties then filed cross-motions for summary judgment which are now before the Court. The parties both argue that there are no genuine issues as to any material issue of fact and that each is entitled to a judgment as a matter of law.

The undisputed facts are that on April 23,1987, W. G. James, Inc. and the Capitol Development Board entered into CDB Contract No. 87-0929-81 for CDB Project No. 810-032-009 for the William Rainey Harper College Corrective Rehabilitation, phases I and II. Thereafter, W. G. James, Inc. and Claimant, Scheupfer Plumbing, Inc., entered into an oral subcontract whereby Claimant agreed to furnish W. G. James, Inc. with labor, materials, tools, and equipment required to perform a portion of the work on this project. Claimant did furnish labor, materials, tools, and equipment pursuant to its oral contract. Claimant had no contract with the Respondent, State of Illinois. Claimant did not receive payment for a part of the labor, materials, tools, and equipment which it provided in the sum of $46,902.50. There is no dispute that Claimant provided such services, nor any dispute as to the amount owed Claimant.

On May 31, 1989, Claimant filed a public hen notice and bond claim with the State of Illinois. Thereafter, Claimant filed a complaint to foreclose its mechanics lien against W. G. James, Inc. in circuit court. W. G. James, Inc. prevailed in state court on the grounds that Claimant failed to file suit on its public lien within 90 days of the filing of notice and failed to file suit on the bond claim notice within 180 days from the date the bond claim notice was filed, as provided by statute.

Claimant argues that it is a third party beneficiary of the States contract with W. G. James, Inc. It is Claimants position that the prime contract required W. G. James to provide a labor and material payment bond to guarantee that subcontractors would be paid for the services and materials supplied for the project. This bond was required by 30 ILCS 550 — 1, et seq. Claimant believes this bond requirement was for the direct benefit of subcontractors and makes Claimant a third party beneficiary under the contract.

Claimant filed this action against the State of Illinois as a contract claim, a third party beneficiary claim, and a lien claim. We find there was no contract between Claimant and Respondent and Claimant cannot prevail on a direct contract claim.

A subcontractor cannot generally proceed against the State outside the Mechanics Lien Act in the absence of an allegation that the subcontractor is a third-party beneficiary under the proposed contract. If a contract is entered into for the direct benefit of a third party, not a party thereto, such person may sue for breach of the contract if the benefit to him is direct, but if the benefit to him arising from the contract is only incidental, he has no right to recovery. (First National Bank of Springfield v. State (1990), 43 Ill. Ct. Cl. 1.) One issue before the Court is, therefore, whether Claimant is a third party beneficiary of the prime contract. The Court must also consider whether Claimant has failed to comply with the filing provisions of the Mechanics Lien Act. This Court will strictly construe the provisions of the Mechanics Lien Act. KSM Sheet Metal Co. v. State (1986), 39 Ill. Ct. Cl. 41.

Respondents cross-motion for summary judgment contends that Claimant has no standing to sue because there is no contractual relationship between Claimant and the State of Illinois. (McNeil Asphalt Co. v. State (1984), 37 Ill. Ct. Cl. 68); that Claimant is not a third party beneficiary; that Claimants claim is barred by the doctrine of res judicata; that Claimant has failed to exhaust its remedies against W. G. James, Inc. by failing to file its mechanics lien in a timely fashion; and that the claim is barred by the Illinois Purchasing Act, 30 ILCS 505/ef seq., because the subcontract was oral and not in writing.

As previously stated, we find that Claimant cannot prevail on a direct contract claim. (County Sales & Supply Co. v. State (1986), 38 Ill. Ct. Cl. 73.) Claimants mechanics lien and bond claim must also fail. Claimant failed to notify the director of CDB of the filing of its verified complaint within 90 days of giving notice of its public hen. Claimant did not serve the CDB with its verified complaint until June 16,1989. Claimant failed to file verified notice of its bond claim with the CDB within 180 days after the date of the last item of work or the furnishing of the last materials. The last day Claimant provided any labor, material or supplies and services in connection with this claim was January 21, 1988. Claimant, therefore, had until July 20, 1988, to file its verified notice of bond claim with the CDB. In violation of the statutory provisions, Claimant did not serve its verified bond claim notice with CDB until April 23,1989.

Claimant’s mechanics hen claim against W. G. James, Inc. was the subject of a summary judgment motion in state court. W. G. James prevailed on the basis that Claimant failed to timely file its statutory notice and to timely file its complaint. This is a failure to exhaust remedies and this claim must be denied in the Court of Claims, (section 790.60 of the Court of Claims Regulations, 705 ILCS 505/25.) Failure to comply with the provisions of section 790.60 shall be grounds for dismissal. See section 790.90 of the Court of Claims Regulations (740 Adm. Code 790.90). Welsh v. State (1994), 46 Ill. Ct. Cl. 420.

Therefore, Claimants only possible source for recovery is pursuant to a third party beneficiary claim in the event we were to find that Claimants failure to timely perfect its mechanics hen remedy against W. G. James, Inc. does not bar this claim for failure to exhaust remedies. We will address that issue later in this order.

The Claimant has no privity of contract with the Respondent and the Claimant has failed to properly sue W. G. James, Inc. with whom they have privity of contract. Because there is no privity of contract with the State and because this Court will only imply a contract in very limited emergency situations, the Claimant seeks to recover against the State of Illinois as a third party beneficiary. This is not an emergency situation where this Court would consider finding an implied contract. There is no other basis upon which Claimant could recover on its claim before this Court.

Therefore, the only way the Claimant could possibly recover is if Claimant is found to be a third party beneficiary of the agreement between the State of Illinois and W. G. James, Inc., which was a public contract. Under Illinois law, there is a strong presumption against creating rights in a third party beneficiary. (Midwest Concrete Products Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

155 Harbor Drive Condominium Ass'n v. Harbor Point Inc.
568 N.E.2d 365 (Appellate Court of Illinois, 1991)
Midwest Concrete Products Co. v. La Salle National Bank
418 N.E.2d 988 (Appellate Court of Illinois, 1981)
Bates & Rogers Construction Corp. v. Greeley & Hansen
486 N.E.2d 902 (Illinois Supreme Court, 1985)
Altevogt v. Brinkoetter
421 N.E.2d 182 (Illinois Supreme Court, 1981)
Richardson v. United States
2 Ct. Cl. 483 (Court of Claims, 1866)
Brighton Building Maintenance Co. v. State
36 Ill. Ct. Cl. 36 (Court of Claims of Illinois, 1982)
McNeill Asphalt Co. v. State
37 Ill. Ct. Cl. 68 (Court of Claims of Illinois, 1984)
Homes v. State
37 Ill. Ct. Cl. 190 (Court of Claims of Illinois, 1984)
County Sales & Supply Co. v. State
38 Ill. Ct. Cl. 73 (Court of Claims of Illinois, 1986)
K.S.M. Sheet Metal Co. v. State
39 Ill. Ct. Cl. 41 (Court of Claims of Illinois, 1986)
First National Bank v. State
43 Ill. Ct. Cl. 1 (Court of Claims of Illinois, 1990)
Welsh v. State
46 Ill. Ct. Cl. 420 (Court of Claims of Illinois, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
52 Ill. Ct. Cl. 151, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schuepfer-plumbing-inc-v-state-ilclaimsct-1999.