Schubart v. N.C. D.O.T.

CourtNorth Carolina Industrial Commission
DecidedJanuary 4, 2005
DocketI.C. NO. TA-17719
StatusPublished

This text of Schubart v. N.C. D.O.T. (Schubart v. N.C. D.O.T.) is published on Counsel Stack Legal Research, covering North Carolina Industrial Commission primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schubart v. N.C. D.O.T., (N.C. Super. Ct. 2005).

Opinion

***********
The undersigned reviewed the prior Decision and Order, based upon the record of the proceedings before Deputy Commissioner Glenn. The appealing party has not shown good ground to reconsider the evidence, receive further evidence, rehear the parties or their representatives or amend the Decision and Order.

***********
Based upon all of the competent evidence of record and reasonable inferences flowing therefrom, the Full Commission makes the following:

FINDINGS OF FACT
1. All parties are properly before the Industrial Commission, and the Industrial Commission has jurisdiction over the parties and this claim. The parties are subject to and bound by the provisions of the North Carolina Tort Claim Act.

2. The injury and losses claimed by plaintiff occurred on Monday, January 22, 2001 over U.S. Highway I-85, on the Brentwood Bridge construction site in High Point, North Carolina (hereinafter referred to as the "job site").

3. North Carolina Department of Transportation (hereinafter referred to as "NCDOT") contracted Blythe Construction Company (hereinafter "Blythe") to be the general contractor on the job site, including the removal of the Brentwood Bridge.

4. The contract with Blythe provided that Blythe would be responsible for complying "with all applicable Federal, State, and local laws, ordinances, and regulations governing safety, health, and sanitation, and shall provide all safeguards, safety devices, and protective equipment, and shall take any other needed actions, on his own responsibility that are reasonably necessary to protect the life and health of employees on the job. . . ."

5. NCDOT contracted with Kissinger, Campo Associates Corporation (hereinafter "KCA"), for engineering services consistent with the contract entered into evidence as plaintiff's Exhibit 5. The KCA engineer (hereinafter "inspector") on this job site was Benny Horton.

6. The inspector's job duties included quality control and setting up traffic control. Mr. Horton maintained daily reports which included a list of the workers on site, the equipment on site, weather conditions, the time work began and was completed and issues regarding traffic control. The inspector was responsible for his own safety and the safety of the traveling public. He was not responsible for ensuring the safety of the other workers on the job site; however, he would generally encourage them to "be safe."

7. If Mr. Horton, the inspector, saw something unsafe, he would talk to the foreman and ask him to correct it. However, he had no power to control the manner of the work or to force the general contractor to stop working. If the foreman refused to correct something that the inspector knew was unsafe, the inspector could then report it to NCDOT. Mr. Horton never reported any safety violations on this job site to NCDOT.

8. Mr. Horton testified that he checked traffic control every hour and that it took him approximately thirty minutes to complete each inspection.

9. Blythe, the general contractor, had its own safety director who was responsible for ensuring that the workers on the job site complied with the applicable safety rules and regulations.

10. At all times relevant hereto, plaintiff worked for Blythe as the foreman on the job site. Plaintiff was responsible for supervising the laborers who worked under him on the job site. He was also responsible for ensuring their safety and his own.

11. Plaintiff testified that prior to starting work on this job site he told his supervisor at Blythe that he had no experience disassembling a bridge deck, but never told anyone at NCDOT or the KCA inspector on site that he had no experience disassembling a bridge deck. However, plaintiff did have previous experience building bridges, and had been the lead man on several projects and had lifted flat slabs of concrete before.

12. As part of the plans submitted to Blythe, there were instructions that the bridge deck should be removed by sawing sections between the beams and not allow any part of the structure to fall to the highway below. The plans further directed the general contractor to submit to NCDOT for approval its detailed method of structure removal prior to beginning work.

13. In response, Blythe submitted a letter to Brian Smith, NCDOT's Resident Engineer on this project, detailing Blythe's method of structure removal. It provided that "[t]he deck spans over Bus. I-85 will be removed by full depth saw cutting the deck slab at locations shown on the attached sketch. Before sawing a panel four (4) lift holes will be drilled in each panel and a crane with four way cable spreaders attached to hold and lift the panel out of the deck." (Hereinafter referred to as the "four pin method.")

14. Work began on the job site on Monday night, January 15, 2001. Plaintiff testified that on that night he took three safety harnesses onto the bridge deck for use by him and his workers. He was instructed by his supervisor with Blythe not to wear the safety harnesses because it would be more dangerous to wear them while doing this type of work.

15. Plaintiff never discussed the issue of safety harnesses with the KCA inspector or anyone at NCDOT.

16. Plaintiff attended safety meetings while at Blythe which included fall protection training and the use of safety harnesses. Plaintiff testified that he had not received any specific training for this project. However, on January 8, 2001, plaintiff signed a Fall Protection Training Certificate, wherein he certified that he had been trained in fall hazards associated with this project (defendant's Exh. 1).

17. Dennis Mise, the crane operator on the job site, testified that Blythe held safety meetings every Monday concerning issues that might arise on a job site.

18. Plaintiff's expert Albert Weaver testified that the best method of fall protection for this job site in his opinion was utilization of a safety harness and static line. However, he stated that if the contractor determined that such measures would not be feasible on this job site, then it could adopt alternative measures under OSHA such as a controlled access zone.

19. Mr. Weaver had no personal experience inspecting a bridge disassembly project, particularly with regard to fall protection.

20. There was no evidence presented as to whether or not an alternative fall protection plan was in place on the job site as allowed under OSHA and explained by Mr. Weaver. There was no evidence regarding whether or not a fall protection plan was in place on the job site and if so, whether it met the requirements of OSHA.

21. Although unclear, it appears that on the first night of this project, January 15, 2001, one panel may have been removed from the bridge deck using the four pin method as the saw operator was having trouble with his saw.

22. The second and third nights on the job site, January 16-17, 2001, a few additional panels were removed using the four pin method. However, the saw operator continued to experience difficulty with his saw and plaintiff testified that the cables connected to the concrete slab were in the way of the saw operator.

23. In an effort to progress at a faster rate, plaintiff contrived a new method of removing the panels drilling only two holes in the concrete panel. According to plaintiff's design, the concrete cutter was to cut six feet of the ten foot lengthwise panel and leave the last four feet uncut. Thereafter, plaintiff would then hook two pins up to the detached end of the panel and tension it up with a crane.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hall v. Kmart Corp.
525 S.E.2d 837 (Court of Appeals of North Carolina, 2000)
Kinsey v. Spann
533 S.E.2d 487 (Court of Appeals of North Carolina, 2000)
Woodson v. Rowland
407 S.E.2d 222 (Supreme Court of North Carolina, 1991)
Simmons v. North Carolina Department of Transportation
496 S.E.2d 790 (Court of Appeals of North Carolina, 1998)
Rhoades v. Rhoades
433 S.E.2d 487 (Court of Appeals of Virginia, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Schubart v. N.C. D.O.T., Counsel Stack Legal Research, https://law.counselstack.com/opinion/schubart-v-nc-dot-ncworkcompcom-2005.