Schreppel v. Campbell Sixty-Six Express, Inc.

441 P.2d 881, 201 Kan. 448, 1968 Kan. LEXIS 387
CourtSupreme Court of Kansas
DecidedJune 8, 1968
Docket45,045
StatusPublished
Cited by10 cases

This text of 441 P.2d 881 (Schreppel v. Campbell Sixty-Six Express, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schreppel v. Campbell Sixty-Six Express, Inc., 441 P.2d 881, 201 Kan. 448, 1968 Kan. LEXIS 387 (kan 1968).

Opinion

*449 The opinion of the court was delivered by

Fontron, J.:

This action was commenced against a truck line to recover damages occasioned by delay in transporting a shipment of freight. The plaintiffs, Tom and Rudy Schreppel, prevailed in the court below and the defendant, Campbell Sixty-six Express, Inc., has appealed.

Evidence introduced on behalf of the plaintiffs showed that the two Schreppel brothers, in addition to operating a business in Oswego, Kansas, engaged in custom combining during harvest time; that in July, 1965, Rudy was in charge of the combining operations; that approximately July 23, Rudy, who was then in Nebraska, phoned Tom at Oswego and told him either to ship or bring two combine pickup attachments to Gettysburg, South Dakota, where he planned to move, and to have them there not later than Friday, July 30; that Tom contacted both the driver of defendant’s truck and the manager of the defendant’s terminal at Parsons and was told by both men it would take three days to ship the attachments to Gettysburg; that Tom told both of them that if delivery could not be made within that time he would take the attachments to Gettysburg himself.

It is undisputed that the attachments were picked up in Oswego by the defendant’s truck on Tuesday, July 27, and were delivered to Buckingham Freight, an interlining carrier, at Kansas City on July 29; that when received by Buckingham the shipment was misaddressed to Gallysburg, South Dakota, (which is nonexistent) and it remained on Buckingham’s docks until Monday afternoon, August 2, at which time Rudy located the shipment by phone from Gettysburg; that the combine attachments were then transported by Buckingham to Sioux City, Iowa, approximately 450 miles from Gettysburg, where they were picked up by Rudy’s employees and taken to Gettysburg, reaching there Tuesday evening, August 3. By this time, however, it was too late, the plaintiff’s regular customers having had to make other arrangements for harvest, and the plaintiffs lost the combining jobs they had been offered.

In their petition the plaintiffs alleged an oral agreement on the part of the defendant to deliver the combine pickup attachments at Gettysburg in three days; that the defendant negligently failed to deliver the attachments to their destination in three days as per the contract; and that due to defendant’s negligence in not fulfilling *450 their contract, plaintiffs were damaged in the amount of $6,010.05.

For answer, the defendant company denied making any express contract to deliver the pickup attachments in three days and alleged that being a common carrier it does not guarantee any time of delivery but that plaintiff’s property was transported and delivered with reasonable dispatch. The defendant also counterclaimed for the unpaid freight bill which plaintiffs declined to pay.

The case was tried to the court, which found generally in favor of the plaintiffs and against the defendant, finding specifically that defendant negligently misaddressed the shipment to Gallysburg, South Dakota, when it should have been addressed to Gettysburg, South Dakota, which negligence prevented delivery of the attachments within a reasonable time and that the plaintiffs were damaged by such negligence in the amount of $4,650. The present appeal followed.

On appeal, the defendant first argues that under the provisions of the Interstate Commerce Act, and regulations adopted pursuant thereto, it, as a common carrier, is prohibited from entering into a special contract for the delivery of freight at a specified time; and that any such an agreement would be void and unenforceable. Accordingly, the defendant maintains that the only obligation it had in transporting the plaintiffs’ combine attachments was to deliver them with reasonable dispatch, as provided by the terms of the bill of lading which was executed in this case.

We are inclined to agree with the defendant in this contention. In Store & Mfg. Co. v. Am. Rys. Exp. Co., 227 Mo. App. 175, 51 S. W. 2d 572, the applicable rule is commendably expressed:

“. . . It is well established that a shipper cannot recover on a special contract to move a shipment within a specified time, for such would work an unjust discrimination among shippers. The only duty that the carrier is under is to carry the shipment safely and to deliver it at its destination within a reasonable time. [United States v. Am. Ry. Exp. Co., 265 U. S. 425, 44 Sup. Ct. Rep. 560; C. & A. R. R. Co. v. Kirby, 225 U. S. 155, 164; A. T. & S. F. Ry. v. Robinson, 233 U. S. 173, 34 Sup. Ct. 556; Fruit & Produce Co. v. Pa. Co., 201 Mo. App. 609.]” (p. 179.)

See, also, Fallgren v. Railway Express, 98 N. H. 333, 100 A. 2d 835; Eliasberg Bros., Inc. v. Railway Exp. Agency, Inc., 302 I. C. C. 305, Nov. 18, 1957; Tribby v. Chicago & N. W. Ry. Co., 62 S. D. 154, 252 N. W. 20.

But the trial court did not predicate its judgment on the violation of a contract to deliver the attachments to Gettysburg in three days, *451 but rather on negligence in misaddressing the same, thereby preventing delivery within a reasonable time. We view the court’s finding in this regard as a finding that the defendant negligently breached its obligation, as set out in the bill of lading, to transport the property “with reasonable dispatch.”

The defendant points to the plaintiffs’ petition which alleges the execution of a contract to deliver the combine parts in three days and alleges a breach thereof, contending that under this pleading the trial court was without authority to render judgment based on a different theory, i. e., negligence in failing to deliver the attachments within a reasonable time.

We believe this contention cannot be sustained. The issue of negligence on the part of defendant was clearly raised in the plaintiffs’ petition, and considerable evidence was introduced in that connection.

The defendant stoutly argues, however, that the cause of action set out in the petition relates solely to negligence in performing a special contract which was unenforceable. Strictly construed, the petition might, perhaps, be subject to such a limited interpretation. Even so, no benefit would accrue to the defendant from such a narrow construction.

K. S. A. 60-215 (b) provides in pertinent part:

“When issues not raised by the pleadings are tried by express or implied ■consent of the parties, they shall be treated in all respects as if they had been raised in the pleadings. . . .”

Judge Spencer A. Gard, in his work, Kansas Code of Civil Procedure, Annotated, in discussing this provision says on page 82:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Speer v. City of Dodge City
636 P.2d 178 (Court of Appeals of Kansas, 1981)
Kiser v. Gilmore
587 P.2d 911 (Court of Appeals of Kansas, 1978)
Starkovich v. Noye
529 P.2d 698 (Arizona Supreme Court, 1974)
Dear v. Vedros
516 P.2d 965 (Supreme Court of Kansas, 1973)
Tripp v. the Reliable Life Insurance Co.
499 P.2d 1155 (Supreme Court of Kansas, 1972)
Greenwood v. Blackjack Cattle Co.
464 P.2d 281 (Supreme Court of Kansas, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
441 P.2d 881, 201 Kan. 448, 1968 Kan. LEXIS 387, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schreppel-v-campbell-sixty-six-express-inc-kan-1968.