School District No. 5 v. Ferrier

251 P. 425, 122 Kan. 15, 1926 Kan. LEXIS 120
CourtSupreme Court of Kansas
DecidedDecember 11, 1926
DocketNo. 26,541
StatusPublished
Cited by1 cases

This text of 251 P. 425 (School District No. 5 v. Ferrier) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
School District No. 5 v. Ferrier, 251 P. 425, 122 Kan. 15, 1926 Kan. LEXIS 120 (kan 1926).

Opinion

The opinion of the court was delivered by

Mason, J.:

A school district employed an architect to draw plans for a new schoolhouse, and to supervise its construction. The plans were drawn and a contract for its construction was entered into between the district and a film of contractors. The building was erected, accepted and paid for, the last payment being made in November, 1921. This action was brought by the district against [16]*16the contractors and the architect, the petition alleging that they had entered into a conspiracy, which was not discovered until June 1, 1923,-to defraud the district, in pursuance of which a new set of blue prints was made, involving the- skimping of material in quantity and quality, and by this device an inferior building was constructed at a saving of cost to the contractors. A jury trial resulted in a verdict and judgment for the defendants, from which the plaintiff appeals, contending that the uncontroverted facts entitled it to a judgment, and that the instructions to the jury were materially erroneous.

1. The working drawings, which were made after the contract had been signed, called for the use of reenforced concrete instead of certain structural steel provided for in the original plans. The plaintiff’s theory is that this was in pursuance of a conspiracy to defraud entered into by the architect and contractors. The defendants’ explanation, which there was evidence to support, may be thus summarized:

There is a general custom for concerns interested, with the permission of the architect of a proposed building, to submit an alternate design with respect to some detail, stating the price, for the use of any bidder who may see fit to include in his bid an alternate proposition based upon such change, the proposer later making working drawings in case a bid is accepted which includes his alternative. The Concrete Engineering Company, of Kansas City, made an estimate on a part of the construction, on the basis of the elimination of a part of the structural steel work already noted, which it furnished to the bidders on the schoolhouse, including the defendant contractors. The proposal as submitted to contractors for bids included eleven alternates. One of them, numbered 7, was for a system of reenforced concrete floor construction instead of steel form construction specified in the plans. This was submitted by the Concrete Products Company, a different concern from the Concrete Engineering Company. The defendant contractors made the lowest bid. They did not bid on the seventh alternative. After the bids were opened on July 14,1920, the architect and the school board discussed them for several hours in executive session. The proposal for the alternate design of the Concrete Engineering Company was specifically discussed at- this meeting. . The defendant contractors were called in on the suggestion of the architect, who asked them particularly, and [17]*17in the presence of all three members of the board, why they had not filled out the blank opposite alternative number 7. They answered that the reason was that their bid was based on the alternative design of the Concrete Engineering Company. The next day the bid of the defendant contractors was accepted (this being at the option of the district, for the call for bids reserved the right to reject all) and the contract was executed. Later the working plans corresponding to the estimate of the Concrete Engineering Company were prepared by that company, approved by the architect, and turned over to the contractors. On the morning of July 14 the contractors asked the architect if the Concrete Engineering Company’s design would be acceptable and he told them it would.

The jury, in response to special questions, made findings to this effect: The design of the Concrete Engineering Company, used in constructing the building, was approved by the architect. Neither defendant attempted to conceal from the members of the school board the fact that this design was used. The Concrete Engineering Company’s plans were around the building during its construction, where they could have been examined by the members of the school board if they desired. The architect acted in good faith in approving these plans, so far as the jury knew. The contractors acted in good faith in bidding and in constructing the building, and did not intend to defraud the plaintiff in any manner in connection with its construction. The architect and the contractors did not conspire together to defraud the plaintiff. To the question whether the architect intended to defraud the plaintiff in any manner in connection with the construction, the jury answered: “We do not know his intentions.”

Obviously the issue whether the defendants were guilty of the charge upon which the action was based — conspiracy to defraud— was one to be submitted to the jury, upon which the verdict, approved by the trial judge, is final unless shown to be affected by some error committed at the trial. In behalf of the plaintiff, however, it is argued that upon the conceded facts the defendants were guilty of legal fraud and breach of contract resulting in recoverable damages. Assuming that evidence given of defects in the building was conclusive, and that as a legal proposition, by virtue of the parol evidence rule, the obligation of the contractors was the same as though no change of design had been made or attempted, the question [18]*18whether the defendants could be held liable in the present action is substantially the same as that raised by the objection to the instructions, which will now be considered.

2. After the jurors had deliberated a part of two days they asked for further instructions. In response to this application the court gave an additional instruction which, after defining a “contract” and “fraud,” proceeded:

“A ‘tort’ is a legal wrong committed upon a person or property, independent of contract. In modern practice, tort is constantly used as an English word to denote a wrong, or wrongful act, for which an action will lie, as distinguished from a contract.
“In connection with the above definitions, which are given to help make plainer this, and other, instructions heretofore given you, you are instructed that you cannot allow damages to plaintiff in this case simply because you may believe from the evidence, if you do so believe, that the defendants, or any of them, failed to perform their contracts with the plaintiff, and that by reason of such breach of contract the plaintiff suffered some damage. In this connection you are further instructed that, although you may believe from the evidence that plaintiff sustained some damage, yet, unless you shall further find and believe from a preponderance of the evidence that such damage was the direct and proximate result or consequence of the fraud of defendants, or some of them, intentionally practiced upon the plaintiff, and was not merely from breach of contract, then your verdict should be for the defendant, or such of the defendants as you find from the evidence were not guilty of such fraudulent conduct.”

While some verbal criticism is made of this instruction, it affords no ground of reversal unless the court erred in holding that no recovery could be had for mere breach of contract, as the jury had been told in the original charge by fair implication.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barry v. Legler
39 F.2d 297 (Eighth Circuit, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
251 P. 425, 122 Kan. 15, 1926 Kan. LEXIS 120, Counsel Stack Legal Research, https://law.counselstack.com/opinion/school-district-no-5-v-ferrier-kan-1926.