School District No. 39 v. Sullivan

48 Kan. 624
CourtSupreme Court of Kansas
DecidedJanuary 15, 1892
StatusPublished
Cited by8 cases

This text of 48 Kan. 624 (School District No. 39 v. Sullivan) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
School District No. 39 v. Sullivan, 48 Kan. 624 (kan 1892).

Opinion

Opinion by

Simpson, C.:

The material facts in this case can be found stated in the opinion of Mr. Justice Valentine, [625]*625in 39 Kas. 347, delivered when the case was first brought to this court. When the case went back to the district court of Brown county it was tried by a jury, and a general verdict for the defendants in error was returned for $634.52. The jury also returned the following answers to special questions of fact submitted to them:

“1. Did the defendant school district, or any of its officers, enter into a contract for the erection of a school-house on the land described in the petition with Hiram Eley? Ans. Yes.
“2. Was that contract expressed or implied? A. Implied.
“3. What was Hiram Eley to receive for the building of that school-house, furnishing all the material? A. $838.
“4. Was the fact known to each member of the board that the defendant Hiram Eley was constructing this schoolhouse? A. Yes.”
“6. Was the fact that Hiram Eley was building a schoolhouse for the defendant school district, under a contract and agreement with C. A. Sawyer, treasurer of the defendant school district, generally known in that school district? A. Yes.
“7. When did he commence the work of erecting the school-house? A. On or about November 1, 1883.
8. When did he cease work, and did he abscond ? A. He ceased work November 22,1883; absconded between 22d and 24th of November, 1883.
“ 9. How far was the school-house completed when he absconded? A. It was ready for plastering.
“ 10. At the time of the arrangement between Eley and any member of the school board, did the board act in concert? A. No.
“11. If Eley absconded, how long did the school-house remain unoccupied and unfurnished? A. Finished January 10, 1884; occupied June 24, 1884.
“12. When did the defendant school district complete and finish the school-house? A. January, 1884.
“13. What other contract was made with defendant Eley for the erecting of the school-house than the arrangement and contract made between him and C. A. Sawyer, treasurer of the defendant school district? A. No other.
“14. What did the defendant school district expend, and what did they do to the completing of the school-house? A. Expended $600; plastered and completed the house.
“15. What knowledge had they, if any, that the defendant [626]*626Hiram Eley contracted for the building the school-house, and that he had done so under a contract of agreement with O. A. Sawyer, treasurer of the defendant school district? A. General knowledge, and by erection of building.
“ 16. What action did defendant school district take in the meeting of school district to accept this school-house which the defendant Eley had partially constructed ? A. By completing arrangements to pay indebtedness accrued by reason of finishing said house.
- “17. What use did the defendant school district make of it since? A. Used it for school purposes.
“18. What other school-house had the defendant school district at the time of accepting the school-house commenced by defendant Eley? A. The old school building.
“19. What did the defendant school district do in the way of finishing the school-house commenced by the defendant Eley? A. Plastered it and hung doors.
“20. What did defendant school district do in insuring the school-house erected for the defendant school district? A. Insured it in the Burlington company.
“21. What moneys of the defendant school district, with its consent, were paid to the defendant Eley as part payment to build the school-house? A. None by consent of the district.
“ 22. Did defendant school district, at the time of its acceptance of house, have a full knowledge of all the facts in regard to the arrangements between Eley and its treasurer, C. A. Sawyer, and abandonment of the contract by the defendant Eley, and that the school-house had only been partially completed? A. Yes.”
“25. Did the board of the defendant school district have full knowledge of the contract and arrangements between Eley and Sawyer to build said school-house? A. No.
“26. If ihe board did not have full knowledge, could it have ascertained it by exercising reasonable diligence? A. Yes.
“27. Did the majority of the board have full knowledge of the fact? A. Yes.
“28. Did Hiram Eley contract with the plaintiff for thep plaintiff to furnish the lumber and lime to be used in the construction of the school-house? A. Yes. .
“29. If so, what amount did the plaintiff furnish defendant Eley to be used in the construction of this school-house? A. $469.35.
[627]*627“30. Was this lumber and building material actually used in the construction of this school-house; if not, how much was used? A. It was.
“31. What was it reasonably worth, the amount that was used? A. $469.35.
“32. From what time have you allowed interest thereon? A. From November 12, 1883, to November 23, 1888.
“33. What amount is due plaintiff from the said Eley for the said material so used? A. $634.52.
“34. Did plaintiff file a mechanic’s lien for the material so furnished the said Eley, in the construction of said schoolhouse, with said district clerk of Brown county, Kansas, and if so, when? A. He did, on the 14th day of January, 1884.
“ 35. Did plaintiff serve a copy of said lien on the defendant school district, or its officers, and if so, when and on whom? A. He did, on or about January 15, 1884, on each member of the board.”

Questions and answers of fact submitted by defendant:

“1. At the meeting of June 24,1884, was there any statement made about the alleged contract between Sawyer and Eley, that Eley should build the school-house? Ans. There was not.
“ 2. At said meeting, was the ratification of any contract betweeh said Sawyer and said Eley discussed or voted upon? A. There was not.
“ 3. Was there any contract entered into between said Eley and Sawyer that was ever submitted to the district board or the district? A. There was not.
“4. If any contract was entered into between said Eley and said Sawyer, what were its terms? A. Implied contract, requiring the payment of $838.
“5. Was there any contract entered into between the board and said Eley? A. No.
“ 6. If question No, 5 is answered in the affirmative, what was it, and when, and who of said board was present? A.
“7.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Farmers State Bank v. School District No. 100
4 P.2d 404 (Supreme Court of Kansas, 1931)
Getty v. City of Syracuse
281 P. 883 (Supreme Court of Kansas, 1929)
Citizens State Bank v. School District No. 115
259 P. 796 (Supreme Court of Kansas, 1927)
Consolidated School Dist. No. 73 v. Ellison
1926 OK 381 (Supreme Court of Oklahoma, 1926)
Badger Oil & Gas Co. v. Preston
1915 OK 796 (Supreme Court of Oklahoma, 1915)
Watkins v. School District No. 104
118 P. 1069 (Supreme Court of Kansas, 1911)
Doyle v. School Dist. No. 38, Noble County
1911 OK 333 (Supreme Court of Oklahoma, 1911)
Union School Furniture Co. v. School District No. 60
50 Kan. 727 (Supreme Court of Kansas, 1893)

Cite This Page — Counsel Stack

Bluebook (online)
48 Kan. 624, Counsel Stack Legal Research, https://law.counselstack.com/opinion/school-district-no-39-v-sullivan-kan-1892.