Scholpp v. Forrest

40 P. 133, 11 Wash. 640, 1895 Wash. LEXIS 354
CourtWashington Supreme Court
DecidedApril 19, 1895
DocketNo. 1734
StatusPublished
Cited by4 cases

This text of 40 P. 133 (Scholpp v. Forrest) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scholpp v. Forrest, 40 P. 133, 11 Wash. 640, 1895 Wash. LEXIS 354 (Wash. 1895).

Opinion

[641]*641The opinion of the court was delivered by

Anders, J.

On October 27, 1894, the state, by its duly authorized agent, the commissioner of public lands, with the approval of the governor, entered into a contract with Eugene Semple, under and in pursuance of an act of the legislature of the state of Washington, approved March 9, 1893, entitled, “An act prescribing the ways in which waterways for the uses of navigation may be excavated by private contract, providing for liens upon tide and shore lands belonging to the state, granting rights-of-way across lands belonging to the state,” (Laws 1893, p. 241), for the excavation of a waterway from the deep waters of Elliott Bay to Lake Washington, and with the material taken therefrom to fill in and raise above extreme high tide, the tide lands lying in front of the city of Seattle; which contract was on the same day duly assigned to the defendant waterway company and is now owned and held by it.

On February 23, 1895, the state entered into an additional contract with the defendant company, which provides for the excavation of the material from the waterways mentioned and described in the first contract, and for filling in and raising above high tide, with the material so excavated, certain tide lands therein described, but not embraced in the first contract. All of the requirements of the law necessary to authorize the execution of the contracts were fully complied with prior to the execution thereof; and the bond required by the contract was duly executed, approved and filed.

These contracts were duly recorded in the office of the county auditor of King county, and by virtue thereof the waterway company claims a lien upon the [642]*642tide lands therein described. Pursuant to § 4 of said act the commissioner of public lands has adopted a form of certificate which he proposes to deliver to the defendant company upon completion of the whole, or any portion of the work provided for by said contract, capable of separate use for the purposes of navigation; which form of certificate has been approved by the attorney general. These certificates, when delivered and filed in the office of the county auditor of the county in which the lands are situated, will constitute a lien on the lands described theréin in favor of the holder thereof, for the amount therein specified, and fifteen per cent, additional thereon, with interest on said amount and additional percentage at eight per cent, per annum from date until paid.

This action was brought to enjoin and restrain the defendant company from performing the work commenced and contemplated by it upon the tide lands described in the complaint, and from trespassing thereon; and to restrain the commissioner of public lands from issuing any certificates under the contracts above mentioned, and for a decree discharging and freeing said lands from the alleged cloud caused by the execution and recording of said contracts. The superior court denied the relief prayed for in whole and in part, and gave judgment in favor of the defendants, from which the plaintiff appeals.

None of the facts alleged in the complaint were denied in the answer, and it is conceded that if the conclusions of law deduced therefrom by the trial court are correct the judgment and decree must be affirmed. In addition to the facts already stated, it appears from the complaint, as well as from the findings of fact, that the plaintiff is entitled, under the law, to a preference right of purchase, and that he has duly and legally ap[643]*643plied to purchase, from the state, the tide lands described in his complaint, and has filed such application with the commissioner of public lands. It also appears that the defendant corporation has entered upon these lands and has commenced work, under and by virtue of the said contract, with the intention and for the purpose of filling in said lands and raising them above high tide, and will, unless restrained by the court, fill and raise said lands above high tide and claim a lien thereon for the cost of filling the same, as provided for in said contracts. And it further appears that the commissioner of public lands will, unless restrained by the court, upon application therefor by the defendant corporation, issue his certificate for the cost of.filling said lands and raising them above high tide under and by virtue of said contract; and that the said defendant will file such certificate in the office of the auditor of King county, Washington, and claim a lien upon the lands so filled in and raised; and that the said defendant will issue said certificate in the form and at the times set forth in the complaint.

The only question to be determined on this appeal is whether the contracts and the certificate proposed to be issued thereunder are in accordance with the provisions of the statute. The learned counsel for appellant claim that the contracts in question are ineffectual and void because — (1) they contain a provision which is contrary to the rule laid down by the law with reference to the manner of apportioning liens among the several owners of land covered by a certificate issued under the contracts and the law; (2) because the first contract entered into contains a provision for the excavation of a waterway through the high lands between the head of Elliott Bay and Lake Washington; and (3) because the last contract provides for the excavation of [644]*644material from the same waterways described in the first.

The provision of the contracts which it is claimed invalidates them is as follows:

“ In apportioning the cost of such work to any lot or parcel of land to which any person or corporation has. a pre-emption right of purchase, the cost of the bulkhead shall be apportioned to the several lots inclosed within and protected by such bulkhead, in such proportion as the area of such lot or parcel bears to the entire area inclosed within such bulkhead. But the” charge against any lot or parcel for-filling in shall be in' such proportion to the entire cost of the work of filling in as the number of cubic yards required to fill in such lot bears to the entire number of yards required for the filling in of the entire area included within any bulkhead.”

The rule of apportionment prescribed by the aforesaid act (Laws 1893, p. 243, § 4) reads as follows:

“Such lien shall not be in solido, and upon the sale by the state to any person, or by any owner claiming under the state to any other person, of any of the tide and shore lands specified in such certificate, the lien herein granted may be discharged as hereinbelow provided, as to any such part of said lands, separately granted or owned, upon the payment of such part of the amount for which the lien upon the lands was given in the first instance as shall bear the same proportion to said whole amount which the area of such separate part of such lands bears to the area of the whole thereof.”

It will be seen that this provision of the contracts is at variance with the law; and this being so, the question is, what is the effect upon the contracts, if any, of such provision.

An examination of the law and the contracts discloses that all of the conditions and provisions which the statute requires are contained in the contracts, ex-[645]*645elusive of the provisions objected to, and the trial court held that such provision is without any force or effect whatever, and that it should be treated as mere surplusage.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Richards v. Bussell
127 P. 198 (Washington Supreme Court, 1912)
Bussell v. Ross
111 P. 165 (Washington Supreme Court, 1910)
Seattle & Lake Washington Waterway Co. v. Seattle Dock Co.
77 P. 845 (Washington Supreme Court, 1904)
Mississippi Valley Trust Co. v. Hofius
55 P. 54 (Washington Supreme Court, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
40 P. 133, 11 Wash. 640, 1895 Wash. LEXIS 354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scholpp-v-forrest-wash-1895.