Schnabel Foundation Company v. National Union Fire Insurance

Court of Appeals for the Fourth Circuit·Decided July 10, 2019·No. 18-1782·Unpublished

Opinion

UNPUBLISHED

UNITED STATES COURT OF APPEALS FOR THE FOURTH CIRCUIT

No. 18-1782

SCHNABEL FOUNDATION COMPANY, Plaintiff – Appellant,

v.

NATIONAL UNION FIRE INSURANCE COMPANY OF PITTSBURGH, PENNSYLVANIA,

Defendant – Appellee.

Appeal from the United States District Court for the District of Maryland, at Greenbelt. Paula Xinis, U.S. District Court Judge. (8:16-cv-00895-PX)

Argued: May 7, 2019 Decided: July 10, 2019

Before GREGORY, Chief Judge, and AGEE and DIAZ, Circuit Judges.

Affirmed by unpublished opinion. Judge Agee wrote the opinion, in which Chief Judge Gregory and Judge Diaz joined.

ARGUED: C. Thomas Brown, SILVER & BROWN, Fairfax, Virginia, for Appellant. Agelo L. Reppas, BATESCAREY LLP, Chicago, Illinois, for Appellee. ON BRIEF: Paul D. Smolinsky, JACKSON & CAMPBELL, Washington, D.C.; Justin K. Seigler, BATESCAREY LLP, Chicago, Illinois, for Appellee.

Unpublished opinions are not binding precedent in this circuit.

AGEE, Circuit Judge:

In this insurance coverage case, Schnabel Foundation Company (“Schnabel”)

appeals from the district court’s order granting summary judgment to National Union Fire Insurance Company (“NU”). Schnabel Found. Co. v. Nat’l Union Fire Ins. Co. of Pittsburgh, Pa., No. PX-16-0895, 2018 WL 2967384 (D. Md. June 12, 2018). For the reasons below, we affirm.

I.

This case arises from the delay of a building construction project in Bethesda, Maryland. Bainbridge St. Elmo Bethesda Apartments, LLC (“Bainbridge”) owned the land at issue (“the Site”) and built a 17-story mixed-use building on it called “the Monty.” Bainbridge hired Turner Construction Company (“Turner”) as the general contractor for the project and Turner subcontracted with Schnabel, a building foundation company, to provide the “support of excavation” system (“SOE”).

An SOE retains the earth immediately surrounding a building site and provides lateral support to neighboring properties during construction. The SOE at issue consisted of steel beams called “soldier piles” and wooden slats called “lagging.” To create the SOE, Schnabel drilled large holes several feet apart, installed the soldier piles vertically in the holes, and attached the lagging horizontally to the soldier piles. This SOE framework holds back earth on adjoining properties as excavation and construction occur on the Site. An SOE is crucial “until the foundation slab and walls are installed[,] at

which time the construction provides support.” J.A. 249 ¶ 27. When the built structure is complete, the SOE is “abandoned in place.” J.A. 249 ¶ 27.

In September 2011, Schnabel began constructing the Monty’s SOE by boring holes and installing soldier piles along the Site’s property line. Several buildings abutted the property line, including one that White Flint Express Realty Group Limited Partnership (“White Flint”) owned and leased to business tenants. Schnabel, in an attempt to construct the SOE as close to the property line as possible, drilled larger holes for the soldier piles than it had planned. Because the holes were oversized, the earth around them shifted and sloughed into the holes. Schnabel then had to use a vibrating air hammer to install the remaining soldier piles, which exacerbated the soil movement. Schnabel admits it “altered the means and methods of installation by . . . drilling larger holes” than planned and “hammer[ing] down [soldier piles] for the final feet of the installation.” J.A. 244 ¶ 17.

Schnabel had contracted with Turner to complete the SOE in March 2012, but during SOE construction in December 2011, Turner informed Schnabel that the floor of a restaurant in the adjoining White Flint building had buckled. Indeed, because of the SOE excavation at the Site, the earth under the White Flint building and other neighboring properties shifted, causing damage to those buildings. It is undisputed that Schnabel’s deficient SOE installation caused the soil to shift.

In March 2012, citing the damages to the neighboring properties, Montgomery County issued a Stop Work Order for the Monty project. From March to July, only safety measures could be implemented at the Site, and Schnabel had to remediate its SOE work

by installing reinforcements and implementing other County-approved design changes. Regular construction resumed in July, and Schnabel eventually completed a proper SOE in late October 2012, about seven months late. The Monty project continued to completion, but Schnabel’s faulty work on the SOE delayed the contracted completion date for approximately one year.

II.

Turner purchased two insurance policies for the Monty project, which together comprised a Contractor Controlled Insurance Plan (“CCIP”). 1 The policy at issue here is only the umbrella Commercial General Liability (“CGL”) policy Turner obtained from NU (“the Policy”). Under the Policy, NU agreed to “pay on behalf of the Insured those sums in excess of the Retained Limit that the Insured becomes legally obligated to pay as damages by reason of liability imposed by law because of . . . Property Damage . . . caused by an Occurrence” during the Policy period. J.A. 132.

After Schnabel’s faulty SOE construction damaged the neighboring properties, White Flint and other adjoining parties sued Bainbridge, Turner, and Schnabel for property damages and business disruption losses. Bainbridge, Turner, and Schnabel then sued each other, seeking to saddle the other with those liabilities. See Schnabel, 2018 WL 2967384, at *2 (discussing the multiple lawsuits among the parties). Bainbridge sued

1 Turner purchased the primary CCIP policy from Liberty Mutual Insurance Company. That policy had a $2 million limit, which Liberty Mutual paid out in full through its defense and indemnification of Bainbridge, Turner, and Schnabel. No one makes any remaining claims under the Liberty Mutual policy, so it is not at issue here.

Turner for construction delay costs, lost profits, and loss of use damages (“delay damages”), and Turner sought insurance coverage under the Policy. When NU denied coverage, Bainbridge accepted $3 million in settlement from Turner and assigned its remaining rights to Turner. Turner then sued Schnabel for the costs of Schnabel’s SOE remediation work (“repair damages”) and for indemnification for the Bainbridge settlement. Schnabel sought coverage from NU, which again denied coverage. Turner accepted $5 million in settlement from Schnabel and assigned its remaining rights to Schnabel.

Schnabel then sued NU in Maryland state court seeking $8 million in coverage, consisting of $3 million for Bainbridge’s delay damages and $5 million for Turner’s repair damages, all of which NU maintains the Policy does not cover. 2 NU removed the case to federal court, and the District of Maryland properly exercised diversity jurisdiction under 28 U.S.C. § 1332. 3 We have jurisdiction under 28 U.S.C. § 1291.

III.

NU denied coverage based on its interpretation of several Policy terms, which are central to our decision. First, NU argued Schnabel’s claimed damages were not caused by an “Occurrence” as defined in the Policy. Under the Policy, “Occurrence,” with respect to

2 Schnabel brought its claim directly against NU because Turner assigned its rights against NU to Schnabel in the parties’ settlement.

3 For purposes of diversity jurisdiction, Schnabel is a citizen of Washington, D.C.

and Virginia; NU is a citizen of Pennsylvania and New York; and the amount in controversy exceeds $75,000. See 28 U.S.C. § 1332.

“Property Damage, [means] an accident, including continuous or repeated exposure to substantially the same general harmful conditions. All such exposure to substantially the same general harmful conditions will be deemed to arise out of one Occurrence.” J.A. 152. NU contends Schnabel’s faulty SOE work is an uncovered business risk, not an “Occurrence.” Schnabel counters that it is a covered “accident” and therefore an “Occurrence.” The Parties also dispute whether Schnabel’s claims arise from “Property Damage.” Defined in the disjunctive, “Property Damage” means

Free access — add to your briefcase to read the full text and ask questions with AI

Schnabel Foundation Company v. National Union Fire Insurance, (4th Cir. 2019).

Schnabel Foundation Company v. National Union Fire Insurance (Schnabel Foundation Company v. National Union Fire Insurance) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related