This text of 135 N.Y.S. 1141 (Schlesinger v. O'Connor Construction Co.) is published on Counsel Stack Legal Research, covering Appellate Terms of the Supreme Court of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schlesinger v. O'Connor Construction Co., 135 N.Y.S. 1141 (N.Y. Ct. App. 1912).

Opinion

LEHMAN, J.

The plaintiffs brought this action to recover a balance unpaid upon a contract to make and set the metal work and roofings on buildings owned by the defendant. The defendant denies that the contract was fully performed, and counterclaims for the damages occasioned by the plaintiffs’ failure to comply with the terms of the contract. At the trial the defendant introduced evidence of very substantial defects, which the plaintiffs denied, and, though the testimony produced by the defendant seems persuasive, I do not think that it is sufficient to enable us to say that the trial justice, who saw the witnesses, was bound to hold that these defects existed to the extent claimed by the defendant. The defendant showed that it cost it $230 to remedy the defects, but the trial justice decided that it was entitled to an offset of only $80, apparently holding that the reasonable cost of repairing the actual defects was only; this sum. The trial justice, however, erred in giving judgment for $240, thus holding that, but for these defects, the plaintiffs would have been entitled to recover $320, when both pleadings and proof show a claim of only $300.

The judgment must therefore be reduced to $220, and affirmed, as modified, without costs to either party. All concur.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
135 N.Y.S. 1141, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schlesinger-v-oconnor-construction-co-nyappterm-1912.