Schillinger v. McGarry

25 Misc. 745, 55 N.Y.S. 673
CourtAppellate Terms of the Supreme Court of New York
DecidedJanuary 15, 1899
StatusPublished
Cited by2 cases

This text of 25 Misc. 745 (Schillinger v. McGarry) is published on Counsel Stack Legal Research, covering Appellate Terms of the Supreme Court of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schillinger v. McGarry, 25 Misc. 745, 55 N.Y.S. 673 (N.Y. Ct. App. 1899).

Opinion

Giegerich, J.

This action was brought to recover damages claimed to have been sustained in consequence of the defendant’s refusal to allow the plaintiff’s assignors to complete and carry out their part of an agreement in writing, bearing date the 1st day of October, 1897, made under their firm name of George Schillinger & Company, of which firm the plaintiff was a member, on the one part, and the defendant, on the other, by the terms of which they agreed to well and sufficiently finish all the cement and concrete work, viz.: and furnish all the cement and necessary ma[746]*746terial. Cellars, vaults, areas and sidewalks, and all coal cinder filling, and also, the asphalt work, viz.: The laying of asphalt on first floors and in water-closets, halls and wardrobes, at the new annex to Grammar School No. 2, situate at No. 116 Henry street, in the city of New York.

And that all work mentioned herein shall be done by the said parties of the second part, according to the plans and specifications of * * * , architect, for the sum of $2,290.”

The principal questions contested upon the trial were whether the plaintifi’s assignors were required to lay the coal cinder filling above the first story, and whether the defendant had prevented the former from performing the conditions of the contract on their part. With respect to the first stated proposition the trial justice, in denying the motion to dismiss the complaint made when the plaintiff rested, held, that the plaintiff’s assignors were not obliged to do any coal cinder filling above said last-mentioned part of the building, and, to my mind, such construction is fairly warranted by the contract.

The testimony regarding the other question was conflicting. The plaintiff testified that his assignors began work under the contract on October 23, 1897, and worked at intervals until March 3, 1898; that in'response to defendant’s letter of March 1, 1898, requiring said firm to perform the conditions of the contract on their part, the witness had an interview on March 2, 1898, with the defendant, in the course of which the latter insisted that by the terms of the contract, the said firm was required to lay the coal cinder filling on all the floors of the building. This was disputed by the plaintiff, who maintained that said filling was only to be laid in the cellar, sidewalks, yards and water-closets, whereupon the defendant offered to pay $3,600 if the firm would stipulate to do the work in dispute in addition to that called for by the contract. The plaintiff promised to consult his partners that evening, or on the following morning and advise the defendant through the telephone of the result of the consultation. The next morning he telephoned the defendant that his firm was willing to do the work for $3,800, which offer was rejected, the defendant saying he would do the work himself.

The plaintiff further testified, “ I was ready every time tb finish, only Mr. Me Garry was not ready, so I could finish, because he didn’t have the filling the right height, and in one place he [747]*747didn’t have the coping there. Q. Did you ever have any conversation with Mr. McGarry after the one in which he said he would do the work himself? A. About fourteen days afterwards I went there again and saw him in Madison street, and I asked him if he was ready for me to start in. He said, 1 I am not ready for you at all; you broke the contract, and ain’t got any right, to do something more.’ I asked him about money, and he said, ‘ You will have to wait for your money until I finish, and if it costs more, I will charge you for that.’ I said, 1 You ain’t a right to do my contract work; we did the work last October and ain’t got a cent; I must pay my men.’ He said, Go to court or somewhere else where you will get it.’ ”

On cross-examination the witness testified that -on March 3, 1898, his firm had three men upon the job doing “ patching work,” and carting the coal cinders from the “ street side ” to the “ Madison street side.” Upon being interrogated by the court, he testified: Q. When did you stop work? A. I didn’t stop; I couldn’t go further; he was not ready. Q. If you couldn’t go further, you stopped? A. I was. there; I couldn’t go further, as he was not ready for me; the cellar on Madison street side ■—that was brick and marble mixed, and I couldn’t get in and the coping was not set in the yard. Q. How long did that continue? A. I was there a couple of days afterwards, and he was not ready; I spoke to him and he said I broke the contract, and wouldn’t let me do anything more and said he would do it himself. Q. When was that? A. That was about March 6th or 7th.”

The defendant in his own behalf testified that the plaintiff’s assignors did not, as testified, do any work under the contract in the month of March, but that, on the contrary, the last work performed by them was in the latter part of February, when, according to the witness, there was “ plenty of work ready for him to do; ” that the plaintiff’s firm did not render any services after the defendant wrote the letter of March 1st; nor did he at any time prevent it from going on with the work; that in the latter part of February, the defendant asked the plaintiff to proceed and do all the concreting cinder work, and that one Gibbs was present at “ one conversation ” which in detail is as follows: Q. State the conversation with Mr. Schillinger and Mr. Gibbs. A. I saw Mr. Schillinger nearly every morning and I met him at the school with Mr. Gibbs, and we went into the office and talked the matter over; the inspector was there and I said the specifica[748]*748tions call for it, and I said 1 Go ahead/ and he said, I can’t afford to do it; it costs so much money.’ I wanted the work done, and ■said, ‘ How much will it cost? ’ He said $1,400/ or ‘ $1,500.’ We talked about $1,000, and I said to Gibbs, ‘ Will you pay one-half and I will pay one-half? ’ and he said I won’t pay five cents.’ And L said I couldn’t afford to pay it. He said, * I will see my partner to-night and let you know.’ I didn’t hear anything from him. Mr. Gibbs told me to go ahead. Q. Did you have any other ■conversation with Mr. Schillinger? A. No, sir.”

The defendant further testified that in March, 1898, he started ■to complete the work; that it was subsequently completed, and that the work was done by third parties. •

On cross-examination, the defendant further testified: “ Q. Do you remember a conversation with him on the telephone where he told you how much it would cost to do the entire concrete work ■and the arches? A. Not on the telephone; the only conversation I had was in Mr. Gibbs’ presence, and I wanted him to complete his work, as I had a great deal of money standing, and Mr. Gibbs told me if I didn’t do it, he would get somebody else to do it. <5. When Schillinger told you he could not do the arch work and •all the cinder concrete work in the other building, what did you say; did you tell him to go ahead? A. I said, ‘ Your contract calls for it; go ahead and finish; ’ there was talk about the asphalt then; he was to complete the work any way — the whole •of it.”

The said David H.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rosenkranz v. Saberski
40 Misc. 650 (Appellate Terms of the Supreme Court of New York, 1903)
Chambers v. Goldklang
31 Misc. 247 (Appellate Terms of the Supreme Court of New York, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
25 Misc. 745, 55 N.Y.S. 673, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schillinger-v-mcgarry-nyappterm-1899.