Scherer v. Schuler Custom Homes Construction, Inc.

2004 WY 109, 98 P.3d 159, 2004 Wyo. LEXIS 138
CourtWyoming Supreme Court
DecidedSeptember 22, 2004
Docket03-147
StatusPublished
Cited by12 cases

This text of 2004 WY 109 (Scherer v. Schuler Custom Homes Construction, Inc.) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scherer v. Schuler Custom Homes Construction, Inc., 2004 WY 109, 98 P.3d 159, 2004 Wyo. LEXIS 138 (Wyo. 2004).

Opinion

KITE, Justice.

[T1] Appellant Tim Scherer ("Mr. Scherer") appeals from the district court's order granting a summary judgment in favor of Schuler Custom Homes Construction, Inc. ("Schuler Custom Homes"). The district court dismissed Mr. Scherer's complaint ruling that a clause in the parties' construction contract, which provided for resolution of disputes over the contract by mediation and/or arbitration, was "applicable and should be enforced." We conclude that Schuler Custom Homes waived alternative dispute resolution, and, therefore, reverse and remand for further court proceedings.

ISSUES

[¶2] Mr. Scherer presents the following issues on appeal:

1 Whether a mediation/arbitration provision in a construction contract is enforceable where the general contractor abandons the construction project, thereby repudiating the contract.
2. If the mediation/arbitration provision is enforceable, whether the general contractor waived the mediation/arbitration provision when it refused to participate in arbitration.
3. Whether the district court abused its discretion in denying Appellant's motion for leave to file an amended complaint to add claims for fraud in the inducement and negligent misrepresentation.

[¶8] Schuler Custom Homes phrases the appellate issues as follows:

1. Whether the lower court erred in enforcing the parties' agreement to submit their disputes to alternative dispute resolution. -
2. After determining that there was no jurisdiction because of the parties' agreement to submit their disputes to alternative dispute resolution, did the lower court abuse its discretion in denying Appellant's motion to amend his Complaint[?]

FACTS

[¶4] On October 14, 2002, Mr. Scherer and Schuler Custom Homes entered into a contract for construction of a home at the base of Casper Mountain. The contract contained the following provision:

A. Mediation and Arbitration: The parties agree that if a dispute arises between them relating to this agreement, they will not file litigation, but will informally resolve the dispute between themselves or submit the dispute to mediation or arbitration. When a dispute arises which the parties are unable to resolve between themselves, the parties shall proceed in good faith to jointly appoint an acceptable mediator and will share equally in the cost of such mediator. The mediation shall be privileged and confidential as provided by Wyoming law. In the event the mediation fails to resolve the matter within forty-five (45) calendar days from the date the dispute arises, the parties *161 agree that the matter shall be submitted to binding arbitration. The arbitration shall be governed by the Wyoming Uniform Arbitration Act as now in effect or later amended, and, absent agreement of the parties to the contrary, each party shall select an arbitrator within fifteen (15) days of the failure of mediation and the two arbitrators shall name a third arbitrator. Unless otherwise decided by the arbitration panel, the parties shall share equally in the cost of such arbitrators.

[T5] Shortly after construction commenced, Mr. Scherer notified Schuler Custom Homes of defects in its workmanship and requested that the parties execute certain change orders to the project. Schuler Custom Homes did not address these issues to Mr. Scherer's satisfaction, and the business relationship between the parties deteriorated. On February 4, 2008, the parties had a meeting regarding the project, which culminated in an argument. At that meeting Mr. Scherer told Schuler Custom Homes that, unless the defects were corrected, he was going to terminate the contract. Mr. Scherer also told Schuler, Custom Homes that he would expect a refund of some of the nearly $150,000 he had already paid for construction of the home.

[T6] On February 6, 2008, Mr. Scherer delivered a letter to Schuler Custom Homes, outlining the outstanding problems and demanding that Schuler Custom Homes proceed with the construction according to the contract. In response to Mr. Scherer's letter, Schuler Custom Homes verbally communicated that it was terminating the contract and would not refund any of the money that Mr. Scherer had paid, Although Schuler Custom Homes did attempt some repair work the next day, it did not perform any additional work on the project after February 7, 2008. Mr. Scherer personally secured the site to prevent damage to the structure and hired other contractors to complete construction of the home.

[¶7] On February 10, 2008, Mr. Scherer filed a complaint against Schuler Custom Homes alleging breach of contract. Schuler Custom Homes filed a motion to dismiss the lawsuit claiming that the parties were required to submit their disagreement to alternative dispute resolution. On March 17, 2003, Mr. Scherer sent a letter to Schuler Custom Homes demanding arbitration and proposing an arbitrator. That letter referenced a February 26, 2008, letter in which Mr. Scherer stated that he was willing to stipulate to a stay of the pending litigation to arbitrate the dispute. On March 24, 2008, Schuler Custom Homes responded to Mr. Scherer's arbitration proposal by stating that it was unwilling to stipulate to a stay of the pending litigation and suggesting the parties should try to mediate their disagreement. The letter did not, however, contain any specifics on the mediation proposal, such as the suggestion of a mediator or a schedule for conducting the mediation. __

[T8] Without making any further effort towards alternative dispute resolution, Schu-ler Custom Homes simply filed an amended motion to dismiss the complaint. On May 15, 2003, Mr. Scherer withdrew his offer to arbitrate because Schuler Custom Homes had failed to nominate an arbitrator. Mr. Scherer filed a response to Schuler Custom Homes' motion to dismiss and a motion for leave to amend its complaint to add claims for fraud in the inducement, intentional and/or negligent misrepresentation, and piercing of the corporate veil.

[¶9] The district court held a hearing on the parties' pending motions. Because the parties submitted materials apart from the pleadings, the district court properly converted Schuler Custom Homes' motion to dismiss to a motion for summary judgment. At the conclusion of the hearing, the district court granted summary judgment in favor of Schu-ler Custom Homes, ruling that the alternative dispute provision of the agreement was applicable and should be enforced. The district court further ordered that Mr. Scherer's motion for leave to file an amended complaint was rendered moot by its summary judgment ruling. Mr. Scherer appealed.

DISCUSSION

1. Jurisdiction

[T10]) After reviewing the record and the parties' briefs, we became concerned *162 that this Court might not have jurisdiction over this appeal because the district court's ruling did not finally decide the parties' dispute. We, therefore, raise the jurisdiction issue sua sponte. See e.g., Terex Corp. v. Hough, 2002 WY 112, ¶ 6, 50 P.3d 317, 16 (Wyo.2002); Ahearn v. Anderson-Bishop Partnership, 946 P.2d 417, 422 (Wyo.1997).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Leslie Chapman v. The State of Wyoming
2013 WY 57 (Wyoming Supreme Court, 2013)
In Re Gulf Exploration, LLC
289 S.W.3d 836 (Texas Supreme Court, 2009)
Vogt v. MBNA America Bank
2008 WY 26 (Wyoming Supreme Court, 2008)
Wein v. Morris
909 A.2d 1186 (New Jersey Superior Court App Division, 2006)
Thunder Basin Coal Co. v. Campbell County
2006 WY 44 (Wyoming Supreme Court, 2006)
MULLINNIX LLC v. HKB Royalty Trust
2006 WY 14 (Wyoming Supreme Court, 2006)
Welty v. Brady
2005 WY 157 (Wyoming Supreme Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
2004 WY 109, 98 P.3d 159, 2004 Wyo. LEXIS 138, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scherer-v-schuler-custom-homes-construction-inc-wyo-2004.