Schalmo Builders, Inc. v. Malz

629 N.E.2d 52, 90 Ohio App. 3d 321, 1993 Ohio App. LEXIS 4620
CourtOhio Court of Appeals
DecidedSeptember 22, 1993
DocketNo. 2211-M.
StatusPublished

This text of 629 N.E.2d 52 (Schalmo Builders, Inc. v. Malz) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schalmo Builders, Inc. v. Malz, 629 N.E.2d 52, 90 Ohio App. 3d 321, 1993 Ohio App. LEXIS 4620 (Ohio Ct. App. 1993).

Opinion

Quillin, Judge.

In this case we must determine whether the trial court correctly granted summary judgment in favor of appellee, Bank One, as holder of a secured interest *323 senior to the mechanic’s lien held by appellant, Schalmo Builders, Inc. We affirm.

Sam and Grace Malz applied for a loan from appellee, Bank One, to fund the construction of ten six-unit buddings in Medina, Ohio. A construction loan for $2,400,000 was approved, for which the Maizes executed a construction loan agreement and an open-end mortgage deed. On May 31, 1989 the open-end mortgage deed was properly recorded.

The Maizes engaged appellant, Schalmo Builders, as general contractor for construction of the apartment buildings. Appellant performed its obligations under the construction contract, but was unable to recover payment from the Maizes. Appellant sued the Maizes and was awarded judgment under the contract. Appellant recorded an affidavit of mechanic’s lien pursuant to R.C. Chapter 1311 on January 23, 1991.

The Maizes defaulted on their loan payments, causing Bank One to bring an action for mortgage foreclosure. The Medina County Court of Common Pleas entered summary judgment, establishing Bank One’s right to foreclose and awarding Bank One’s mortgage priority over Schalmo Builders’ mechanic’s hen.

Schalmo Builders appeals the summary judgment and asserts two assignments of error.

Assignment of Error II

“The trial court erred in granting Bank’s motion for summary judgment to establish the priority of Bank’s mortgage over the hen of Plaintiff-Appellant because there exists a genuine issue of material fact as to whether or not Plaintiff-Appellant commenced ‘reasonably apparent’ and ‘readily visible’ construction at the property prior to Bank’s May 31, 1989 recordation of the mortgage.”

Appellant argues that its hen attached prior in time to Bank One’s filing of the open-end mortgage and, accordingly, that its hen should be given priority. We do not agree.

R.C. 1311.13(A)(1) provides:

“Liens * * * for labor or work performed or materials furnished prior to the recording of the notice of commencement pursuant to section 1311.04 of the Revised Code are effective from the date the first visible work or labor is performed or the first materials are furnished by the original contractor, subcontractor, materialman, or laborer at the site of the improvement.” (Emphasis added).

*324 “The mechanics’ liens thus attach at the time of such commencement of construction, the same as mortgage liens ‘take effect’ from the date of filing * * *." Wayne Bldg. & Loan Co. v. Yarborough, (1967), 11 Ohio St.2d 195, 217, 40 O.O.2d 182, 196, 228 N.E.2d 841, 856. R.C. 1311.13(B) gives such mechanic’s liens priority over “all other titles, liens or encumbrances” which may attach to the subject of the mechanics’ labor and are recorded after “construction, excavation or improvement” is commenced.

Bank One properly filed its open-end mortgage on May 31, 1989. Therefore, the appellant’s mechanic’s lien will take priority over appellee’s mortgage only if visible work or labor was performed or materials were delivered prior to May 31, 1989.

In Rider v. Crobaugh (1919), 100 Ohio St. 88, 125 N.E. 130, paragraph four of the syllabus, the Supreme Court of Ohio held:

“If it is reasonably apparent to the mortgagee that the construction, excavation or improvement had not actually and obviously commenced when the mortgage was filed for record, then such mortgage would retain priority.” (Emphasis added).

Although the Rider court never articulated what constitutes “commencement of construction,” as that concept appears in R.C. 1311.13, intermediate courts have developed a component-part test. See, e.g., Huntington Natl. Bank of Columbus v. Treasurer (1983), 13 Ohio App.3d 408, 13 OBR 493, 469 N.E.2d 535. The component-part test has been structured to require “the work * * * deemed the commencement of construction * * * [to] form a part of the work necessary for the construction and [to] be of a nature that can afterward be considered a component part of the structure.” (Emphasis added.) Id. at 409, 13 OBR at 495, 469 N.E.2d at 537, citing North Shaker Blvd. Co. v. Harriman Natl. Bank (1924), 22 Ohio App. 487, 153 N.E. 909. The purpose of the component-part test is to ensure adequate notice of potentially conflicting hens to those considering business dealings with the landowner. See id. We believe that the component-part test is consistent with the standard announced in Rider, and significantly furthers the legislature’s goals in drafting R.C. 1311.13.

In the case sub judice, appellants argue that readily apparent and visible labor had commenced prior to Bank One’s filing of the open-end mortgage in that:

“(a) Appellant caused the contemplated building improvements to be located and staked upon the Property; and,

“(b) Appellant performed certain soil testings/soil work where the building improvements were to be located.”

Neither the act of staking out the improvements, nor the soil testing constituted an act that could be considered a component-part of the structure. As a *325 consequence, neither act is sufficient to have established the effectiveness of appellant’s mechanic’s lien under R.C. 1311.13. Accordingly, we hold that Bank One’s mortgage lien is senior to the mechanic’s lien held by appellant.

Appellant’s second assignment of error is overruled.

Assignment of Error I

“The trial court erred in not concluding as a matter of law that the mechanic’s lien of Plaintiff-Appellant has priority over the mortgage of Defendant-Appellee, Bank One, Akron, N.A., (‘Bank’), and in otherwise determining that the mortgage maintained priority over the lien, because:

“(i) Bank failed to include within the mortgage the statutorily required covenant authorizing Bank to do all things provided to be done under Section 1311.14 of the Ohio Revised Code.

“(ii) Bank did not comply with Section 1311.14 of the Ohio Revised Code in making disbursements from the construction loan account because Bank did not retain sufficient funds to complete the improvements in accordance with the contract price and Bank improperly disbursed from the account to satisfy Bank’s accrued interest, Bank’s closing/settlement charges and the insurance obligations of Defendants-Appellees, Sam D. Malz and Grace C. Malz (Bank’s borrowers).

“(in) A portion of Bank’s $2,400,000.00 construction loan account equal to $223,463.52 was not disbursed as prescribed in Section 1311.14 of the Ohio Revised Code and was not ‘actually used’ to pay for construction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

North Shaker Boulevard Co. v. Harriman Natl. Bank
153 N.E. 909 (Ohio Court of Appeals, 1924)
Wayne Building & Loan Co. v. Yarborough
228 N.E.2d 841 (Ohio Supreme Court, 1967)
Akron Savings & Loan Co. v. Ronson Homes, Inc.
238 N.E.2d 760 (Ohio Supreme Court, 1968)
Colonial Mortgage Service Co. v. Southard
384 N.E.2d 250 (Ohio Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
629 N.E.2d 52, 90 Ohio App. 3d 321, 1993 Ohio App. LEXIS 4620, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schalmo-builders-inc-v-malz-ohioctapp-1993.