Scartelli Construction Services, Inc. v. Chesapeake Building Components, Inc.

CourtDistrict Court, M.D. Pennsylvania
DecidedAugust 9, 2021
Docket3:18-cv-01164
StatusUnknown

This text of Scartelli Construction Services, Inc. v. Chesapeake Building Components, Inc. (Scartelli Construction Services, Inc. v. Chesapeake Building Components, Inc.) is published on Counsel Stack Legal Research, covering District Court, M.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scartelli Construction Services, Inc. v. Chesapeake Building Components, Inc., (M.D. Pa. 2021).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE MIDDLE DISTRICT OF PENNSYLVANIA SCARTELLI CONSTRUCTION : Civil No. 3:18-CV-01164 SERVICES, INC, : : Plaintiff, : : v. : : CHESAPEAKE BUILDING : COMPONENTS, INC., : : Defendant. : Judge Jennifer P. Wilson MEMORANDUM This is a breach of contract action between two construction companies arising out of the construction of the North Pocono Public Library (“the library”) in Moscow, Pennsylvania. Plaintiff Scartelli Construction Services, Inc. (“Scartelli”), which served as the general contractor for the library project, has brought suit against one of its subcontractors, Defendant Chesapeake Building Components, Inc. (“Chesapeake”), regarding the furnishing of a prefabricated wood roof truss system that was to be installed as part of the library project. The case is presently before the court on Chesapeake’s motion for partial summary judgment. For the reasons that follow, the motion is granted in part and denied in part.

1 FACTUAL BACKGROUND AND PROCEDURAL HISTORY1 On May 8, 2012, Scartelli signed an agreement to serve as the general

contractor for the construction of the library. (See Defendant’s Exhibit G, Doc. 77- 2, p. 27.) The contract stated that Scartelli was to achieve substantial completion of the project within 300 days of the date of the contract. (Id., p. 28.) Scartelli

subsequently agreed to a subcontract with Chesapeake by which Chesapeake would supply a prefabricated wood roof truss system for the library. (See Doc. 15, ¶ 18; Doc. 43, ¶ 18.)2 Chesapeake delivered the truss system on November 13, 2012. (Doc. 15, ¶ 27; Doc. 43, ¶ 27.)

Scartelli alleges that the truss system that Chesapeake delivered “was defective, unfit and unsuitable for its purpose and not merchantable in that it did not conform, and was contrary to the Defendant’s shop drawings.” (Doc. 15, ¶ 29.)

This defective truss system, Scartelli alleges, caused disruption and delay in the

1 The parties’ statements of material facts at the summary judgment stage are silent as to several background facts regarding the library project. In order to aid the reader’s understanding of the factual background of this case, the court will cite to portions of Scartelli’s amended complaint (Doc. 14) and Chesapeake’s answer to the amended complaint (Doc. 43) where applicable.

2 Although the parties agree that they had a contract for the truss system, they disagree as to what document or documents memorialize the terms of that contract. (See Doc. 15, ¶ 18; Doc. 43, ¶ 18.) For present purposes, the court does not need to determine which party is correct, as the arguments raised in Chesapeake’s instant motion for summary judgment do not require the court to review the specific language of the contract. 2 library project. (Id. ¶¶ 30–31.) Scartelli incurred substantial monetary loss in an attempt to mitigate the damage allegedly caused by Chesapeake. (Id. ¶¶ 32–33.)

Scartelli brought suit against Chesapeake in the Lackawanna County Court of Common Pleas on May 11, 2018, bringing claims arising from the allegedly defective truss system that Chesapeake had delivered. (See Doc. 1-4, pp. 4 –19.)

Chesapeake removed the case to this court on June 7, 2018, invoking the court’s diversity jurisdiction under 28 U.S.C. § 1332. (See Doc. 1.) The case was initially assigned to United States District Judge Richard P. Conaboy. Immediately after removing the case to federal court, Chesapeake filed an

omnibus motion seeking to either dismiss the case for failure to state a claim, have the case transferred to the United States District Court for the District of Maryland, or strike certain portions of the complaint and require a more definite statement as

to other portions of the complaint. (Doc. 2.) Chesapeake’s motion sought to strike the portions of the complaint that pertained to the Dickson City Building project, which was another construction project for which the parties had signed a contract that was not directly pertinent to the issues in this case. (Id.) The court granted

Chesapeake’s motion to the extent that it sought to strike the portions of the complaint pertaining to the Dickson City Building project and to the extent that it sought a more definite statement, but otherwise denied the motion as premature.

(Doc. 14.) 3 Scartelli filed an amended complaint on August 30, 2018, raising claims for breach of contract, breach of an implied in fact contract, breach of warranties, and

promissory estoppel. (Doc. 15.) Scartelli sought $11,521.36 in damages arising from its efforts to mitigate damages, as well as an additional $120,000 “in other direct and main office delay impact costs.” (Id. ¶ 44.)

Chesapeake filed a motion to dismiss or alternatively for a more definite statement on September 12, 2018. (Doc. 17.) Chesapeake additionally moved to transfer the case to the District of Maryland on September 26, 2018. (Doc. 21.) The case was reassigned to United States District Judge A. Richard Caputo on

November 18, 2018, and Judge Caputo denied both motions on January 23, 2019. (Docs. 39–40.) Chesapeake then filed an answer to the amended complaint and a counterclaim against Scartelli on February 6, 2019. (Doc. 43.)

Scartelli moved to strike portions of Chesapeake’s answer and counterclaim on February 25, 2019, arguing that Chesapeake had improperly included allegations pertaining to the Dickson City Building project in contravention of Judge Conaboy’s earlier ruling. (Doc. 46.) The court granted the motion on May

21, 2019, striking Paragraph 34 of the answer and Paragraphs 7–11 of the counterclaim. (see Docs. 51–52.) Chesapeake moved for partial reconsideration on June 4, 2019, arguing that Paragraph 34 of the answer should only be stricken in

part because it only partially pertained to the Dickson City Building project. (Doc. 4 55.) The court granted the motion for reconsideration on July 22, 2019, ruling that only the portion of Paragraph 34 that followed “Denied” was stricken from the

record. (Doc. 57.) The case was reassigned to the undersigned on March 18, 2020. Following the close of fact discovery, Chesapeake filed the instant motion for partial

summary judgment on January 5, 2021, along with a supporting brief and a statement of material facts. (Docs. 75–77.) Chesapeake’s motion seeks summary judgment as to two issues: (1) Scartelli’s claim that it is entitled to office overhead costs as part of its damages; and (2) Scartelli’s breach of warranties claim. (Doc.

76.) Scartelli filed a brief in opposition to the motion and a response to the statement of material facts on January 25, 2021. (Docs. 80–81.) Chesapeake then filed a reply brief in support of the motion on February 12, 2021, and filed a

request for oral argument on the motion on February 12, 2021. (Docs. 88–89.) With briefing on the motion complete, it is now ripe for the court’s disposition. JURISDICTION This court has jurisdiction under 28 U.S.C. § 1332, which allows a district

court to exercise subject matter jurisdiction where the parties are citizens of different states and the amount in controversy exceeds $75,000.

5 STANDARD OF REVIEW A court may grant a motion for summary judgment when “there is no

genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). A dispute of fact is material if resolution of the dispute “might affect the outcome of the suit under the governing law.”

Anderson v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lesnefsky v. Fischer & Porter Co., Inc.
527 F. Supp. 951 (E.D. Pennsylvania, 1981)
D.E. v. Central Dauphin School District
765 F.3d 260 (Third Circuit, 2014)
Emil Jutrowski v. Township of Riverdale
904 F.3d 280 (Third Circuit, 2018)
Briaheen Thomas v. Tice
943 F.3d 145 (Third Circuit, 2019)
Royal Pioneer Paper Box Manufacturing Co. v. DeJonge
115 A.2d 837 (Superior Court of Pennsylvania, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
Scartelli Construction Services, Inc. v. Chesapeake Building Components, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/scartelli-construction-services-inc-v-chesapeake-building-components-pamd-2021.