SC&A Construction, Inc. v. Potter

CourtCourt of Chancery of Delaware
DecidedJanuary 6, 2016
DocketCA 10528-VCG
StatusPublished

This text of SC&A Construction, Inc. v. Potter (SC&A Construction, Inc. v. Potter) is published on Counsel Stack Legal Research, covering Court of Chancery of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SC&A Construction, Inc. v. Potter, (Del. Ct. App. 2016).

Opinion

COURT OF CHANCERY OF THE SAM GLASSCOCK III STATE OF DELAWARE COURT OF CHANCERY COURTHOUSE VICE CHANCELLOR 34 THE CIRCLE GEORGETOWN, DELAWARE 19947

Date Submitted: November 17, 2015 Date Decided: January 6, 2016

Donald L. Logan, Esquire Samuel L. Guy, Esquire Victoria K. Petrone, Esquire 1601 Concord Pike, Suite 38C Logan & Petrone, LLC P.O. Box 25464 One Corporate Commons Wilmington, DE 19899 100 W. Commons Blvd., Suite 435 New Castle, DE 19720

Re: SC&A Construction, Inc. v. Potter, Civil Action No. 10528-VCG

Dear Counsel:

This matter involves a home-improvement contract between the Petitioner,

SC&A Construction, Inc. (“SC&A”), a Delaware corporation, and the Respondents,

Charles Potter, Jr. and Velda C. Jones-Potter (collectively, the “Potters”),

Wilmington homeowners.1 Each side contends that the other has breached the

contract. The matter has been arbitrated, although the Potters contest the validity of

that arbitration. Before me is SC&A’s petition for confirmation of the arbitration

award (the “Petition to Confirm”), and its motion for summary judgement on that

petition. For the reasons that follow, summary judgment is appropriate, and I grant

the Petition to Confirm.

1 I refer to Mr. Potter, where appropriate, by his first name throughout this Letter Opinion for the sake of clarity. No disrespect is intended. Unfortunately, this case is a procedural morass. The parties’ dispute was first

litigated in the Superior Court, in which SC&A proceeded in rem, seeking a

mechanic’s lien against the Potters’ property on which the contractual work was

performed, albeit not to the satisfaction of the Potters. The Potters filed an in

personam counterclaim against SC&A, seeking damages. SC&A moved to dismiss,

raising a mandatory arbitration provision (the “Arbitration Provision”) in the

contract as a jurisdictional bar. The Potters responded, arguing that the Arbitration

Provision was inapplicable or unenforceable on a number of grounds. The Superior

Court determined that the matter must be referred to arbitration,2 but reserved one

issue concerning arbitrability—whether Charles was bound by the Arbitration

Provision—for the arbitrator, E. Gerald Donnelly, Jr., Esquire (the “Arbitrator”).

Ultimately, the Arbitrator found that Charles was subject to the Arbitration

Provision. During arbitration, the in rem proceeding in Superior Court was stayed.

The Potters sought an immediate appeal of the Superior Court order referring

the matter to arbitration, but that appeal was rejected as interlocutory. 3 The parties

arbitrated for nine days before the Arbitrator. The Arbitrator issued his “Final

Award of Arbitrator” (the “Arbitration Award”) on September 23, 2014, finding in

2 But see 10 Del C. § 5702(a) (granting the Court of Chancery jurisdiction to enforce an agreement to arbitrate). 3 Potter v. SC&A Constr., 69 A.3d 372 (Del. 2013) (TABLE). 2 favor of SC&A.4 The decision was delivered to the Potters on the same day.5

Pursuant to the Arbitration Award, SC&A was awarded $86,544.78, plus interest at

1.5% per month from October 1, 2014 ($30.49 per day) for the breach of contract

claim; $10,500.00 in attorney’s fees; and $4,582.26 in administrative fees.6

At around the same time, a proceeding before the Wilmington Board of

License and Inspection Review was taking place. At oral argument, counsel for the

Potters informed me that the Board ultimately declined to issue a certificate of

occupancy for the Potters’ home, based on what the Potters characterize as shoddy

or illegal construction by SC&A.

Shortly after receiving the Arbitration Award, on October 1, 2014, SC&A

moved in the Superior Court action to “Enter the Arbitration Award as a Final

Mechanic’s Lien Judgment.” The Potters filed a response to that motion on October

21, 2014, arguing that the Superior Court lacked jurisdiction to enter the requested

relief under the Delaware Uniform Arbitration Act.7 They also raised in defense the

4 Petition to Confirm ¶ 7. The Potters argue that the Arbitrator’s Award is not in fact final, “in that it does not address all matters reflected in the scope of the matters presented” and because “the arbitrator addresses matters outside the scope of the arbitrator[’]s asserted authority such as attorney fees and the arbitrator’s administrative fees.” Response to Pet’r Mot. for Summ. Judgment ¶ 3. 5 Pet’r Mot. for Summ. Judgment 3 n.1. 6 Petition to Confirm ¶ 7. 7 The parties have briefed this matter under the assumption that the Delaware Uniform Arbitration Act (the “DUAA”), and not the Federal Arbitration Act, applies. For purposes of this Letter Opinion, I consider this a stipulation that the applicable law is the DUAA, and I have proceeded accordingly. 3 same contentions about the invalidity or inapplicability of the Arbitration Provision

already rejected by the Superior Court or referred by that court to the Arbitrator. The

Superior Court declined to act on SC&A’s motion, finding that SC&A must first

seek to confirm that Arbitration Award in this Court before it would consider

entering a final mechanic’s lien.8 The Superior Court action remains stayed. SC&A

then filed this action, seeking to confirm the Arbitration Award, and moved for

summary judgment on the ground that the Potters had failed to file a petition to

vacate, modify, or correct the Arbitration Award prior to the running of the statute

of repose under the DUAA. Only after SC&A filed its summary judgment motion

did the Potters file an answer opposing confirmation of the Award. Appended to the

Answer—filed on March 4, 2015—was a counter-petition (the “Petition to Vacate”),

seeking to vacate, modify, or correct the Arbitration Award.

10 Del. C. § 5713 provides the authority for this Court to confirm arbitration

awards:

The Court shall confirm an award upon complaint or application of a party in an existing case made within 1 year after its delivery to the party, unless within the time limits hereinafter imposed grounds are urged for vacating or modifying or correcting the award.9

The “time limits” referred to are those imposing a statute of repose within which a

party may contest the award of an arbitrator: the non-prevailing party may request

8 See 10 Del. C. § 5702(a) (conferring jurisdiction to confirm arbitration awards on this Court). 9 Id. at § 5713 (emphasis added). 4 that the Court vacate, modify, or correct the award pursuant to 10 Del. C.

§§ 5714–15. Those statutes provide that, upon complaint or an application by a party

in an existing case, “made within 90 days after delivery of a copy of the award to the

applicant,” the Court may vacate, modify, or correct the award for certain

enumerated reasons.10 Here, to be timely, application to vacate by the Potters should

have been made in this Court by December 22, 2014. The Potters, however, did not

seek timely vacature or modification; their Petition to Vacate was not filed until

March 4, 2015. According to SC&A, I am therefore without jurisdiction to entertain

such a request here, and must confirm the Arbitration Award under Section 5713.

The Potters contend that their response to the motion of SC&A in the Superior

Court action to “Enter the Arbitration Award as a Final Mechanic’s Lien” either

constitutes a timely “urging of grounds” to vacate, in compliance with Sections

5713–15, or tolls the repose period indefinitely. Their response to SC&A’s Superior

Court motion was not a request to vacate, however. Only this Court has jurisdiction

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 5702
Delaware § 5702(a)
§ 5713
Delaware § 5713
§ 5714
Delaware § 5714

Cite This Page — Counsel Stack

Bluebook (online)
SC&A Construction, Inc. v. Potter, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sca-construction-inc-v-potter-delch-2016.