SBR Roofing, Inc. v. Richfield Springs Central School District
Opinion
Appeal from an order of the Supreme Court (Dowd, J.), entered June 27, 2002 in Otsego County, which granted petitioner’s application pursuant to General Municipal Law § 50-e (5) for leave to file a late notice of claim.
Petitioner and respondents entered into a contract for reconstruction work on facilities owned and operated by respondents. The contract provided for petitioner to commence work on July 25, 2000 and to substantially complete the work by August 28, 2000. In August 2000, while continuing to perform work, petitioner submitted to the project architect an application for payment in the amount of $167,988.50. Citing deficiencies in the work, the architect certified payment for $65,507 in September 2000. The architect indicated that a second application for payment would be entertained after he received a written report and a laboratory analysis from an engineering firm assessing the quality of petitioner’s work. A second application for payment was submitted, but respondents refused to make further payment until completion of the project. Petitioner continued working until July 6, 2001. On July 16, 2001, while petitioner waited to receive a punch list detailing final improvements to be made, the Superintendent [887] of Schools of respondent Richfield Springs Central School District sent petitioner a letter terminating the contract due to deficiencies in the work. Petitioner contends that respondents refused to permit it to reenter the construction site to complete the punch list.
In preparation for a breach of contract action, petitioner applied for leave to file a late notice of claim in September 2001 (see Education Law § 3813 [2-a]; General Municipal Law § 50-e [5]). Petitioner asserted that the claim accrued in July 2001. Petitioner requested leave to file a late notice of claim, however, in anticipation that respondents would argue that the claim accrued in September 2000, when payment was initially refused, and, thus, that the claim was untimely.
Footnotes
Free access — add to your briefcase to read the full text and ask questions with AI
303 A.D.2d 886 (SBR Roofing, Inc. v. Richfield Springs Central School District) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.