Sbaraglio v. Vicarisi

164 A. 402, 110 N.J.L. 280, 1933 N.J. LEXIS 480
CourtSupreme Court of New Jersey
DecidedJanuary 31, 1933
StatusPublished

This text of 164 A. 402 (Sbaraglio v. Vicarisi) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sbaraglio v. Vicarisi, 164 A. 402, 110 N.J.L. 280, 1933 N.J. LEXIS 480 (N.J. 1933).

Opinion

The opinion of the court was delivered by

Wells, J.

This is an appeal by the defendant from a judgment entered on a postea signed by Judge Porter, sitting as a Circuit Court judge in a Supreme Court issue, which postea was based upon the findings of Julian Berla, a referee to whom the case had been referred by consent.

Tiie suit was to recover the sum of $3,695, which the plaintiffs claim is the balance owing by defendant to them on a contract for the construction of three-story brick building and four garages in the city of Newark, and for extras less certain allowances. Among the extras was a claim for $4,000 for the installation of a heating plant, which had been inadvertently omitted by the plaintiffs in making up their bid, which plaintiffs allege defendant agreed to pay; and also a claim for $1,375 (less an allowance of $400 for an omitted incinerator) representing the price for additional cost of erection occasioned by the bursting of a sewer pipe without any fault of plaintiffs, resulting in a cave-in of the cellar excavation, the filling of the same with water and making it impracticable for plaintiffs to continue with the construction of the building. This additional cost plaintiffs allege defendant agreed to pay. An answer was filed by the defendant in which he denied owing the plaintiffs anything. The first general defense was that plaintiffs failed to finish the contract on time, that the defendant on the request of plaintiffs for the payment of extras, refused to pay for the extras but counter-demanded *282 a sum for the loss of rentals caused by the delay in completing the contract; that plaintiffs failed to produce architect’s certificate that work was done as per contract; that the painting ■was defective, the roof leaked, the cellar was not water-tight, piping was improperly covered, that steam valves were not installed in radiators as required by the contract, &c.; and that thereupon in consideration of the demands by the plaintiffs and the counter-demands by the defendant the plaintiffs and defendant mutually agreed that their respective claims should be satisfied by the defendant paying the plaintiffs $3,000, which the defendant says he did, and that the same was in full accord and satisfaction of plaintiffs’ claims and demands.

There were no law points raised in the answer. The issue . framed was, therefore, an issue of fact.

After the filing of a reply the parties consented to a reference. This reference is not in the usual form and, with the exception of the concluding paragraphs, pertaining to the payment of the expenses of the reference and to the entry of the rule in the minutes, is set out in full as follows:

“The above entitled cause being regularly on the daily call in this December term, 1931, and it appearing to the court that counsel for the plaintiffs and for the defendant have consented hereto, and it further appearing to the court that the matters in controversy between the parties hereto involve the alleged performance of and the alleged non-performance of the terms and provisions of a certain building contract and extra work thereunder, and also a complete accord and satisfaction of the alleged claims.
“It is on this 28th day of December, 1931, ordered, that the above matters in controversy existing therein be and they are hereby referred to Julian Berla, a competent architect, to ascertain and report to this court his findings of fact, after hearing all of the evidence submitted by the respective parties hereto and also from a personal examination of the premises involved in the within litigation.
“And it is further ordered that the said report of said referee shall have the same force and effect, as to factual issues found by him, as a jury verdict on said facts;
*283 “And it is further ordered that upon the coming in of said report, either party hereto, upon days’ notice to the other party hereto, may make application to the Honorable Newton H. Porter, Esq., Circuit Court judge, for a poslea on said report and the law applicable to such cases.”

After hearing the evidence submitted by the respective parties and making a personal examination of the premises, the referee found the sum of $2,180 to be due from the defendant to the plaintiffs and after due notice, an order was made confirming the referee’s report and the poslea was signed and judgment entered accordingly.

The amended postea gives a lucid recital of the proceedings before Judge Porter as follows:

“Upon the application of the plaintiffs for an order confirming the referee’s report and the signing of the postea, the ■defendant, by his attorney, moved for a judgment in favor of the defendant on the said referee’s report upon the following grounds:
(a) That the referee’s report had the effect of a special verdict by a jury and was conclusive as to findings of fact only and not as to a general verdict, and that the trial court upon ■such findings of fact and the law applicable to such cases should enter a verdict in favor of the defendant and against the plaintiffs in spite of the referee’s recommendation in favor of the plaintiffs.
(b) That the plaintiffs are not entitled to collect for the work done by them on the excavation for the reason that the ■plaintiffs were obligated by law to perform what they had already agreed to do, regardless of what happened by way of accidents or unforeseen circumstances, and because their contract did not provide against such emergencies and that any .agreement for payment for said extra work was nudum pactum.
(c) That plaintiffs were not entitled to recover for the steam heating plant for the same reason as urged under (b) ■hereof.
(d) That there was an accord and satisfaction and the {plaintiffs’ claims were fully paid and satisfied.
*284 “After hearing argument of counsel and reading the briefs submitted by counsel, and considering the referee’s report, the motion made by defendant for the direction of a verdict in his favor was denied, to which defendant prayed exception as grounds for appeal and said exception was noted.”

The principal contention raised by this appeal is whether or not the referee’s report had the effect of a jury verdict. The plaintiffs maintain that it did. The defendant says that the referee’s report was not conclusive as a jury general verdict but was only a fact finding inquiry and that the postea should have been entered only after the court had considered the facts so found by the referee and the law applicable to such cases and facts.

This court recently held in Bocchiero v. Carrino, 108 N. J. L. 176, that an order of reference entered by consent of the parties will be treated as a jury verdict, unless the order of reference states to the contrary. Appellant undertakes to differentiate that case from the instant case by a comparison of the two orders of reference. In the Bocchiero

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Worcester Loom Co. v. Heald
72 A. 421 (Supreme Court of New Jersey, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
164 A. 402, 110 N.J.L. 280, 1933 N.J. LEXIS 480, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sbaraglio-v-vicarisi-nj-1933.