SBA Network Services, Inc. v. Telecom Procurement Services, Inc.

250 F. App'x 487
CourtCourt of Appeals for the Third Circuit
DecidedOctober 9, 2007
DocketNo. 06-4162
StatusPublished
Cited by4 cases

This text of 250 F. App'x 487 (SBA Network Services, Inc. v. Telecom Procurement Services, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SBA Network Services, Inc. v. Telecom Procurement Services, Inc., 250 F. App'x 487 (3d Cir. 2007).

Opinion

OPINION

BARRY, Circuit Judge.

Appellant Telecom Procurement Services, Inc. (“TPS”) appeals from orders of the District Court granting summary judgment in favor of Appellee SBA Network Services, Inc. (“SBA”) and awarding $355,334.71 in damages, interest, fees, and costs. TPS also contends that the District Court erred in dismissing its crossclaims. For the reasons discussed below, we will affirm in part, reverse in part, and remand for further proceedings consistent with this opinion.

I.

This action arises out of a fire that occurred on October 9, 2003 in a wireless telecommunications tower (the “Tower”) owned by Sprint Communications and located in Catskill, New York. Cingular Wireless, seeking to add its phone service to the Tower, contracted with Bechtel Corporation (“Bechtel”) for the installation of communications equipment. Bechtel, in turn, subcontracted the work to SBA, a Florida corporation.

In need of a certified welder, SBA contacted TPS, a New York corporation that was performing work on nearby telecommunications towers. Pursuant to this inquiry, TPS, on September 29, 2003, submitted a “pricing proposal” to SBA for the installation of three hand holes and an entry port on the Tower. SBA accepted the proposal on October 1, 2003. The next day, SBA and TPS representatives executed a Purchase Order Subcontract (the “Subcontract”) for TPS’s installation of the three hand holes and the entry port. Just above the signature of TPS’s authorized representative, the Subcontract expressly incorporated four exhibits, which included, among other things, the pricing proposal and acceptance, as well as “General Conditions” and “Minimum Safety Requirements.”

On October 4, 2003, TPS issued a purchase order to Appellee TNT Communications (“TNT”), an Iowa business entity, for the very work that TPS had contracted with SBA to perform. Although the purchase order originated with TPS and appeared under its letterhead, TPS contends that it provided no instruction or assistance to TNT, and that SBA made all necessary arrangements. Nonetheless, TPS charged a 15. percent markup for its service.

On October 9, 2003, between 9 and 10:00 A.M., TPS foreman Terry Pennell dis[490]*490patched a TNT work crew, consisting of Gerald Kershner and Rick Rollert, to the Tower. There, Kershner and Rollert met with Joseph Rains, the SBA site superintendent. No TPS representative was present, although TPS’s president testified that Pennell held ultimate responsibility for the job, including the responsibility to ensure that all work was performed by qualified workers and in accordance with TPS and Bechtel standards. Rains gave the TNT employees access to the Tower, provided the ports to be installed, and remained onsite for several hours while Kershner and Rollert performed the work.

While Kershner and Rollert were welding, a fire started inside the Tower. Heat from the fire caused the Tower to buckle, rendering it unusable. SBA subsequently had the Tower disassembled and replaced with a new structure. The total cost to SBA for replacing the Tower was $268,408.13.

On October 4, 2005, SBA filed a complaint in the U.S. District Court for the Western District of Pennsylvania, naming as defendants TPS, TNT, Kershner, and Rollert. Count 1 alleged that TPS had breached the Subcontract by, among other things, failing to indemnify SBA for more than $237,000 in damages incurred as a result of the fire. Counts 2 through 5 alleged negligence on the part of TPS, TNT, Kershner, and Rollert, respectively. TPS answered and filed crossclaims against TNT, Kershner, and Rollert for indemnification and contribution, although Rollert was never successfully served. At no point did TNT, Kershner, or Rollert answer or otherwise defend SBA’s claims or TPS’s crosselaims.

After the completion of discovery, SBA and TPS filed cross-motions for summary judgment. On July 20, 2006, the District Court granted summary judgment for SBA as to the breach of contract claim, granted summary judgment for defendants as to the negligence claims, and reserved decision on the question of damages. TPS moved, pursuant to Federal Rule of Civil Procedure 59(e), to alter or amend the judgment, and SBA simultaneously filed a second motion for summary judgment on the question of damages. On August 23, 2006, the Court denied TPS’s Rule 59(e) motion. After hearing argument, the Court, on August 31, 2006, 2006 WL 2561236, granted SBA’s second motion for summary judgment and ordered the entry of judgment against all defendants in the amount of $355,334.71, including damages of $268,408.13, prejudgment interest of $51,668.55, and attorneys’ fees and costs in the amount of $35,258.03. TPS never raised its crossclaims at any point during the summary judgment proceedings, and none of the Court’s memoranda or orders specifically addressed them. This appeal followed.

II.

The District Court had diversity jurisdiction under 28 U.S.C. § 1332. We have jurisdiction to review the final decision of the District Court under 28 U.S.C. § 1291. We apply the same standard as the District Court. In conducting our plenary review of the record, we view all evidence and draw all reasonable inferences in a light most favorable to the nonmoving party. Matreale v. N.J. Dep’t of Military & Veterans Affairs, 487 F.3d 150, 152 (3d Cir.2007). Summary judgment is appropriate only if “there is no genuine issue as to any material fact and ... the moving party is entitled to a judgment as a matter of law.” Fed.R.Civ.P. 56(c).1

[491]*491TPS contends that its contract with SBA consists of TPS’s September 29, 2003 price proposal, SBA’s October 1, 2003 acceptance, and an undated one-page exhibit on TPS letterhead describing the general nature of the work to be performed. In support of this position, TPS notes that when SBA returned the signed price proposal, its facsimile cover sheet stated, “Here is the signed contract. Please accept [t]his as your notice to proceed.” (App. at 197.) TPS would have us ignore, therefore, the Subcontract that the parties executed on October 2, 2003.

We easily conclude, as did the District Court, that TPS is bound by the October 2, 2003 Subcontract and the exhibits expressly incorporated therein. On its face, TPS’s September 29 proposal related only to “pricing,” and SBA’s October 1 acceptance served only to fix the price term of the parties’ agreement. The next day, SBA proposed the remaining terms and conditions, which TPS promptly accepted. No additional consideration was needed because the Subcontract merely complemented, and did not modify, the parties’ earlier price agreement. (See App. at 62 (“The Contract Documents are intended to be correlative and complementary....”).) See Newkirk Constr. Corp. v. Gulf County, 366 So.2d 813, 815 (Fla.Dist.Ct.App.1979) (“Modifications of contracts must be supported by new consideration as well as the consent of both parties.” (emphasis added)); see also Whitley v. Royal Trails Prop. Owners’ Ass’n,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LHR, INC. v. T-MOBILE USA, INC.
112 A.D.3d 1293 (Appellate Division of the Supreme Court of New York, 2013)
Benchmark Group, Inc. v. Penn Tank Lines, Inc.
612 F. Supp. 2d 562 (E.D. Pennsylvania, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
250 F. App'x 487, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sba-network-services-inc-v-telecom-procurement-services-inc-ca3-2007.