JUSTICE LEAPHART

delivered the Opinion of the Court.

Marlen G. Savik and Jack Piippo (Savik and Piippo) appeal from the jury verdict of the Fourth Judicial District Court, Missoula County, denying their request for damages for breach of contract. We affirm in part, reverse in part and remand.

For purposes of this decision, this Court will discuss only the following dispositive issues:

1) Did the District Court err in dismissing Savik and Piippo’s breach of contract claim?
2) Did the District Court err in instructing the jury on parol evidence when Savik and Piippo sought recovery under a theory of fraudulent inducement?

BACKGROUND

In 1983, Savik and Piippo organized Touch America, Inc., a long distance telephone company with services in Montana. In May of 1990, Savik and Piippo were the sole stockholders and principal officers of Touch America and were in control of all of its operations. Entech is a Montana corporation that has owned and operated various non-utility businesses including businesses involved in communications technology. On May 15, 1990, Savik and Piippo entered into a written contract with Entech for the sale of all of the assets of Touch America. During negotiations and following the negotiation period, Entech’s Vice President, Michael J. Meldahl (Meldahl) was the chief negotiator for Entech. Following negotiations, Entech pur *155 chased all of Touch America’s assets pursuant to a written sale agreement.

The Sale Agreement (Agreement) set forth a variable sale price consisting of a $1.15 million down payment, plus a distribution to Savik and Piippo of twenty percent of the net profits of the business generated during the first five years after the sale. The net profits distribution had a maximum payment of $783,545.

The Agreement also required that Savik and Piippo be permitted to work for Entech for three years after the sale of Touch America. The Agreement stated that Savik and Piippo would “be entitled to those benefits that are afforded to other employees under Entech’s employment policies.” In accordance with the Agreement, Savik and Piippo worked for Entech for three years prior to their termination.

In 1993, Savik and Piippo brought an action in District Court claiming damages based on two theories. First, Savik and Piippo claimed that Entech breached the Agreement by terminating their employment after three years. Second, Savik and Piippo claimed that they were fraudulently induced into entering the Agreement. The District Court granted summary judgment dismissing Savik and Piippo’s claims of breach of contract finding that the express terms set forth in the contract were clear and the parol evidence rule barred consideration of the oral communication between Meldahl and Savik and Piippo. Therefore, the only remaining issue before the District Court was whether Entech fraudulently induced Savik and Piippo into entering the Agreement.

At trial, Savik and Piippo argued that the employment clause, along with various representations by Meldahl, created the impression that they would become permanent Entech employees. Meldahl’s alleged representations are the basis of the fraudulent inducement claims made by Savik and Piippo. Following a jury verdict in favor of Entech, Savik and Piippo brought this appeal challenging, among other things, the District Court’s decision to dismiss their breach of contract claim as well as jury instructions regarding parol evidence.

DISCUSSION

1) Did the District Court err in dismissing Savik and Piippo’s breach of contract claim?

Our standard of review in appeals from summary judgment rulings is de novo. Mead v. M.S.B., Inc. (1994), 264 Mont. 465, 470, 872 P.2d 782, 785. When we review a district court’s grant of summary judgment, we apply the same evaluations as the district court based *156 on Rule 56, M.R.Civ.P. Bruner v. Yellowstone County (1995), 272 Mont. 261, 264, 900 P.2d 901, 903.

Savik and Piippo’s claims of breach of contract stem from their interpretation of the intent of paragraph 4.13 of the Agreement. That paragraph provided in relevant part:

Subject to satisfying Entech’s hiring policies, Entech shall retain Messrs. Savik and Piippo for terms of three (3) years each at annual initial salaries of $60,000 each. Messrs. Savik and Piippo will be entitled to those benefits that are afforded to other employees under Entech’s employment policies [.]

Savik and Piippo maintain that the “benefits” available to them as Entech employees included not only vacation, health insurance, and pension, but also permanent employment terminable only for good cause. Savik and Piippo based their interpretation of the contract on oral representations that they claim were made to them by Meldahl. They also claim that the term “benefits,” as used in the contract, was ambiguous and thus parol evidence was needed to explain what the parties intended in using that term.

The parol evidence rule in Montana has been codified under §§ 28-2-904, and 28-2-905, MCA. Section 28-2-904, MCA, explains, “[t]he execution of a contract in writing, whether the law requires it to be written or not, supersedes all the oral negotiations or stipulations concerning its matter which preceded or accompanied the execution of the instrument.” Section 28-2-905, MCA, further provides that when an agreement has been reduced to writing by the parties, there can be no evidence of the terms of the agreement other than the contents of the writing except when a mistake or imperfection of the writing is claimed or when the validity of the agreement is the fact in dispute. In their claim for breach of contract, Savik and Piippo contend that the term “benefits” was ambiguous and thus the court should have allowed parol evidence as to statements made to them by Meldahl which led them to believe that “benefits” included permanent employment.

This Court has held that where the terms of the contract are ambiguous and uncertain, evidence of attending circumstances is admissible. Molerway Freight Lines v. Rite-Line Transp. (1995), 273 Mont. 95, 100, 902 P.2d 9, 12. In Monte Vista Co. v. Anaconda Co. (1988), 231 Mont. 522, 528-29, 755 P.2d 1358, 1362, this Court explained:

An ambiguity exists when a contract is subject to two interpretations and parol testimony can be used to determine what the *157 parties intended. [Citations omitted.] However, intent of the parties is only looked to when the agreement in issue is not clear on its face. [Citation omitted.]

In the present case, the District Court gave the following rationale for granting summary judgment:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Richards v. JTL Group, Inc.
2009 MT 173 (Montana Supreme Court, 2009)
Hartle v. Nelson
2000 MT 356 (Montana Supreme Court, 2000)
Barnes v. City of Thompson Falls
1999 MT 77 (Montana Supreme Court, 1999)
Schumacher v. Stephens
1998 MT 58 (Montana Supreme Court, 1998)
Harwood v. Glacier Electric Cooperative, Inc.
949 P.2d 651 (Montana Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
923 P.2d 1091, 278 Mont. 152, 53 State Rptr. 894, 12 I.E.R. Cas. (BNA) 60, 1996 Mont. LEXIS 184, Counsel Stack Legal Research, https://law.counselstack.com/opinion/savik-v-entech-inc-mont-1996.