Sauvie Island Agricultural League v. GGS (Hawaii), Inc.

810 P.2d 856, 107 Or. App. 1, 1991 Ore. App. LEXIS 666
CourtCourt of Appeals of Oregon
DecidedMay 1, 1991
DocketA8910-05964; CA A63718
StatusPublished
Cited by10 cases

This text of 810 P.2d 856 (Sauvie Island Agricultural League v. GGS (Hawaii), Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sauvie Island Agricultural League v. GGS (Hawaii), Inc., 810 P.2d 856, 107 Or. App. 1, 1991 Ore. App. LEXIS 666 (Or. Ct. App. 1991).

Opinion

*3 RICHARDSON, P. J.

Plaintiff brought this declaratory judgment action seeking, along with related relief, a declaration that defendant county’s approval of a conditional use for the development of a golf course had expired pursuant to the county zoning ordinance. The trial court dismissed the action on the ground that a writ of review was the appropriate procedure and the time for bringing that proceeding had passed. Plaintiff appeals. We affirm, although for reasons that differ from the trial court’s.

In October, 1983, the county approved the conditional use, for which defendant Douglas was the applicant. Under sections 11.15.7010(C) and 11.15.7110(C) of the county code, the approval would “expire two years from the date of such approval if substantial construction or development has not taken place.” In September, 1985, Douglas’ attorney wrote to the county planning department to apprise it that a number of development steps had been taken. The planning director responded with a letter “finding” that the activities “constitute substantial progress toward the establishment of the golf course. Therefore, the approval * * * will not expire.” Plaintiff contends that the director’s action was taken without notice, a hearing or related procedures.

Because this case was decided on preliminary motions, we do not know what procedures the director followed. The parties also point to nothing in county or state legislation that defines what procedures were required. Be that as it may, given the reasons for our holding, we need not decide whether the director’s letter or any other action of the county met any applicable procedural requirements for a land use decision.

In December, 1988, Douglas sold the property to GGS (Hawaii), Inc. The next month, Douglas applied to have the golf course site expanded by 55 acres. The application was approved by the planning commission. 1 On June 20, 1989, *4 the Board of County Commissioners reversed the commission’s decision on the expansion. The board also requested advice from county counsel as to whether it could review the planning director’s September, 1985, letter extending the original approval. He responded:

“The Director had legal authority to notify the permittee of the status of the permit under section 11.15.7110(C). 1 See ORS 215.042(1) (Planning Director is chief administrative officer of planning department). The Director exercised that authority over three years ago, advising the permittee that the permit ‘will not expire.’ Can the Board review or reconsider that decision now?
“My research does not disclose a definitive answer. However, it would be risky for the county to revisit the permit-expiration issue at this late stage.
“First, the Board would have the problem of deciding what actions/investments had been taken by the permittee prior to the two year deadline (October 1985), and whether post-deadline actions/investments could be considered. The events in question are over three years old, so difficult proof problems could be presented.
“Second, if the Board reversed the position taken by the Director in 1985,1 would expect a court to take a very hard look at the reversal. The permittee would no doubt argue that he could and did reasonably rely on the Planning Director’s decision. * * *

The board took no action.

Plaintiff then brought this action. The relief that it seeks is that the court

“a) enter a declaratory judgment that defendant Douglas had not performed substantial construction or development of the golf course as of October, 1985, and the conditional use and community service designations expired at that time;
*5 ‘ ‘b) enter a declaratory judgment that the Board, acting through its Planning Director, unlawfully determined that defendant Douglas’ permit to develop and construct a golf course on their Sauvie Island property had not expired;
* ‘c) enter a declaratory judgment that no approval currently exists for development or construction of a golf course on the affected land because any such approval lapsed upon defendant Douglas’s transfer of the land to defendant GGS; and
“d) issue an injunction requiring defendants Douglas and GGS to halt all development and construction of a golf course unless and until a new approval for such development is received.”

The issue that the parties formulate, correctly, is whether the circuit court had jurisdiction. Defendant GGS and intervenors contend that the subject matter of the action comes within LUBA’s exclusive jurisdiction to review “land use decisions.” Plaintiff counters that the action is within the circuit court’s enforcement jurisdiction under ORS 197.825(3)(a), which provides:

“Notwithstanding subsection (1) of this section, the circuit courts of this state retain jurisdiction:
“(a) To grant declaratory, injunctive or mandatory relief in proceedings arising from decisions described in ORS 197.015(10)(b) or proceedings brought to enforce the provisions of an adopted comprehensive plan or land use regulations.” 2

Plaintiff relies on Doughton v. Douglas County, 90 Or App 49, 750 P2d 1174 (1988) (Doughton), where we held that the county’s failure to require a person who had been granted partition rights to comply with a condition that was attached to the approval of the partition could give rise to some enforcement remedy under ORS 197.825(3)(a). However, the only specific relief that the plaintiff sought in the action — that the county be required to rescind the partition approval — was not the exclusive compliance action that the county could take, was not mandatory and was therefore *6 unavailable. We affirmed the trial court’s dismissal of the claims pertaining to the partition. 3

Similarly, here, the only relief that plaintiff seeks is beyond the circuit court’s authority. It asks the court to decide affirmatively that the approval had expired under sections 11.15.7010(C) and 11.15.7110(C). In other words, it asks the court to make a land use decision. Whether “substantial construction or development” has occurred is a question that requires the exercise of “factual or legal judgment” and that the county must answer through a land use decision. Doughton v. Douglas County, 82 Or App 444, 728 P2d 887 (1986), rev den

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bowerman v. Lane County
403 P.3d 512 (Court of Appeals of Oregon, 2017)
Rogue Advocates v. Board of Commissioners
372 P.3d 587 (Court of Appeals of Oregon, 2016)
Grabhorn, Inc. v. Washington County
297 P.3d 524 (Court of Appeals of Oregon, 2013)
Crist v. City of Beaverton
922 P.2d 1253 (Court of Appeals of Oregon, 1996)
Kalmiopsis Audubon Society v. Curry County
884 P.2d 894 (Court of Appeals of Oregon, 1994)
Clackamas County v. Marson
874 P.2d 110 (Court of Appeals of Oregon, 1994)
Weeks v. City of Tillamook
832 P.2d 1246 (Court of Appeals of Oregon, 1992)
State ex rel. Parmenter v. Wallowa County Court
829 P.2d 1054 (Court of Appeals of Oregon, 1992)
Campbell v. Board of County Commissioners
813 P.2d 1074 (Court of Appeals of Oregon, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
810 P.2d 856, 107 Or. App. 1, 1991 Ore. App. LEXIS 666, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sauvie-island-agricultural-league-v-ggs-hawaii-inc-orctapp-1991.