Sauve v. Title Guaranty & Surety Co.

158 P. 112, 29 Idaho 146, 1916 Ida. LEXIS 68
CourtIdaho Supreme Court
DecidedMay 25, 1916
StatusPublished
Cited by6 cases

This text of 158 P. 112 (Sauve v. Title Guaranty & Surety Co.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sauve v. Title Guaranty & Surety Co., 158 P. 112, 29 Idaho 146, 1916 Ida. LEXIS 68 (Idaho 1916).

Opinion

BUDGE, J.

This is an action by one of the purchasers of water rights under the Big Lost River Carey Act Project to determine whether or not she is entitled to recover damages upon a bond given to the state of Idaho in connection with the contract between the state and one George S. Speer. The action was brought upon four causes of action; three having been assigned.

It appears from the record that a corporation known as the Big Lost River Land & Irrigation Company, Limited, organized under the laws of this state, on April 30, 1907, entered into a contract with the state for the purpose of constructing irrigation works under the terms of the Carey Act for the reclamation of about eighty thousand acres of land. In the month of February, 1909, the Big Lost River Land & Irrigation Company, Limited, which had then become insolvent, sold and conveyed to George S. Speer whatever property it had, including its right, title and interest in the irrigation project. Prior to this time, while the Big Lost River Land & Irrigation Company, Limited, was solvent, it sold for cash and on time a number of water right contracts to settlers, among which was the contract of appellant.

On May 27, 1909, Speer entered into a new contract with the state of Idaho which, it is contended, was to take the place of the contract previously made between the Big Lost River Land & Irrigation Company, Limited, and the state, and to embrace the contracts with the original locators. The contract included some additional lands within the project. On the same date that the contract was entered into between Speer and the state, Speer, as principal, and the Title Guaranty & Surety Company, the respondent corporation here, made, executed and delivered to the state of Idaho an under[151]*151taking in the sum of $175,000. This undertaking was conditioned for the performance of the contract. Shortly after-Speer made his contract with the state and gave the bond sued upon in this action, to wit, on or about June, 1909, he sold and conveyed all his right, title and interest in and to the irrigation project to the Big Lost River Irrigation Company, which corporation was organized by him and his associates for the construction of the project. This latter corporation was the construction company that undertook and agreed to complete the project, commonly known as the Big Lost River Project, after which it, like its predecessor, became insolvent. Neither Speer nor the construction company is made a party to this action.

The present suit is brought against the Title Guaranty & Surety Company to recover damages for the failure of the Big Lost River Irrigation Company to complete the project, and furnish water to appellant and her assignors.

To the complaint in the trial court a demurrer was interposed upon the grounds, first, that the complaint as a whole and as to its various parts did not state facts sufficient to constitute a cause of action; second, that there was a misjoinder of causes of action, for the reason that separate and distinct causes of action on separate and distinct contracts with different persons are united in one complaint; and third, that the plaintiff has not legal capacity to sue. The demurrer'was sustained and upon failure to amend, a judgment of dismissal was entered. This appeal is from the judgment.

Speer’s contract with the state contains, among others, the following terms:

“Whereas it appears that said Big Lost River Land and Irrigation Company, Limited, has entered into contracts to a large extent with settlers upon the lands to be reclaimed to supply said settlers with water for their lands, and which contracts are still in force and unfulfilled on the part of said Company, and it further appearing to the Board that it is to the interest of the State and to the settlers holding water contracts with said Big Lost River Land and Irrigation Company, Limited, the rights of which latter it is the purpose to [152]*152secure by the terms of such altered and amended contract, that the reque°st of said George S. Speer should be granted to the end that the said works may be completed as originally proposed, and that the rights of the settlers upon the lands included in said project may be secured.....”

It is the contention of appellant that under the terms of the contract as above recited, it was the purpose of the state land board to protect the rights of the purchasers of contracts from the Big Lost River Land & Irrigation Company, Limited, both cash and time, by placing them in a different position from that occupied by subsequent purchasers of contracts upon the irrigation tract; and that, under other terms of the contract, presently to be recited, it is specifically provided that if default should be made by the Big Lost River Irrigation Company, these former contract holders would be entitled to recover such damages as they may sustain, irrespective of any action taken by other settlers or by the state on behalf of other settlers on the project.

Paragraph 21 of the contract between Speer and the state, upon which appellant also relies for relief as above indicated, provides:

“Said party of the second part hereby assumes and undertakes the fulfillment of each and every of the contracts, both time and cash, for water rights heretofore sold and contracted to be furnished by the Big Lost River Land & Irrigation Company, Limited, with the several persons, or the assigns of such persons, mentioned and set forth in the Schedule hereunto attached and marked Schedule ‘C’ and made a part of this agreement and it is agreed that, upon the execution of the said party of the second part or his assigns, of contracts in the form heretofore approved by said Board and which are hereunto annexed, made a part of this agreement and marked Schedule ‘D,’ the said several parties holding time water contracts with said Big Lost River Land & Irrigation Company, as per Schedule ‘C,’ shall surrender said contracts so held and receive in lieu thereof a new contract as herein provided. The price for shares of water rights in such new contract to be the same as is provided in the contract surrendered [153]*153and the holder of a time contract as per said Schedule ‘C,’ shall, at the time of executing such new contract, receive credit for the payment heretofore made on such former contract and the remaining payments shall correspond in amount to those provided for in such former contract.”

To secure the fulfilment of the provisions of the contract heretofore recited, Speer, as principal, and the Title Guaranty & Surety Company, executed to the state and delivered to the state land board the bond before mentioned, which contains the following provisions:

“That if the above bounden George S. Speer does well and truly perform or cause to be performed all the covenants, conditions and stipulations of said contract above recited on his part to be kept and performed and shall keep harmless and protect the said State of Idaho from and against all loss by reason of the non-fulfillment by said George S. Speer, Principal, of the covenants contained in the said contract, to be performed by him as aforesaid, and also against actual loss by reason of any and all claims, defects, errors, liens and encumbrances arising from the non-fulfillment by the said Principal of said covenants, then this obligation to be void; otherwise to be and remain in full force and virtue.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stewart v. Arrington Construction Company
446 P.2d 895 (Idaho Supreme Court, 1968)
Rudeen v. Howell
283 P.2d 587 (Idaho Supreme Court, 1955)
Williams v. Neddo
163 P.2d 306 (Idaho Supreme Court, 1945)
Fullmer v. Proctor
82 P.2d 1103 (Idaho Supreme Court, 1938)
Skinner v. Jordan Valley Irrigation District
3 P.2d 534 (Oregon Supreme Court, 1931)
American Surety Co. v. State ex rel. HUMFELD
299 F. 357 (Ninth Circuit, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
158 P. 112, 29 Idaho 146, 1916 Ida. LEXIS 68, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sauve-v-title-guaranty-surety-co-idaho-1916.