Sauer v. McClintic-Marshall Construction Co.

146 N.W. 422, 179 Mich. 618, 1914 Mich. LEXIS 545
CourtMichigan Supreme Court
DecidedMarch 27, 1914
DocketDocket No. 6
StatusPublished
Cited by20 cases

This text of 146 N.W. 422 (Sauer v. McClintic-Marshall Construction Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sauer v. McClintic-Marshall Construction Co., 146 N.W. 422, 179 Mich. 618, 1914 Mich. LEXIS 545 (Mich. 1914).

Opinion

Steere, J.

Plaintiffs recovered a judgment of $1,026.34 against defendant in the circuit court of Washtenaw county for breach of a contract by the terms of which defendant agreed to furnish plaintiffs a quantity of structural steel for use in constructing a building at the University of Michigan, in Ann Arbor, at the price of $1,450. Plaintiffs were a firm of contractors and builders doing business under the [620]*620firm name of Chas. A. Sauer & Co., having offices in the cities of Detroit and Ann Arbor. Defendant was a large company engaged in the fabrication of structural steel at Pittsburg, Pa., having an office at Detroit in charge of a designing engineer. In preparation for bidding on a contract for the construction of a storehouse and shop building for the University of Michigan, upon which the regents of that institution were about to receive bids, plaintiffs obtained estimates from various sources for material which would be necessary in the construction of said building, the cost of which it was essential to ascertain before bidding. Defendant’s representative at Detroit entered into communication with plaintiffs upon that subject, with a view to furnishing them whatever structural steel would be required for the building under consideration in case they were the successful bidders. These negotiations resulted in a proposal in writing, dated July 6, 1912, to furnish the structural steel according to certain drawings referred to, for $1,450, further providing:

“Shipment to be made in ten weeks. * * *
“Two hundred dollars will be added to the above price if shipment is made in five weeks.
“Terms of payment and details of contract to be as we may mutually agree.
“We trust you will find this price attractive and that it will be of assistance to you in landing this order.”

In their competitive bid for the erection of said building plaintiffs made use of and relied upon said proposál. They were the successful bidders and obtained the contract, which by its terms required that the building should be completed on November 1, 1912. In pursuance of their previous negotiations the contract in question in this case was made by letter of proposal from defendant dated July 22, 1912, accepted by one from plaintiffs the following day. The [621]*621proposal was to furnish at a stated price the structural steel for said building “in accordance with drawing No. 7412 — 1, prepared by the Trussed Concrete Steel Company and approved by Mr. James H. Marks, architect.” Amongst other things it stated, “All materials to be delivered f. o. b. cars, Ann Arbor, within eight to ten weeks after receipt of complete information for detail drawings,” which were to be made by defendant subject to the approval of the engineer, or architect, who was Mr. Marks. The acceptance concluded as follows:

“We are to furnish you with the pattern for holes to be punched in the lintels for our bolts. Kindly prepare your shop drawings at once and submit your copy for the O. K. of Mr. Marks, and also one copy for his files. Please arrange to make your delivery within the specified time and prevent any delay.”

The shop drawings mentioned in the acceptance were the detail drawings named in the proposal, which are made by the fabricator of structural steel from the general plans of the architect and such other and more complete information as is necessary in preparing accurate drawings for steel construction, relative to patterns of holes to be bored, etc. Under the contract this “complete information” was to be furnished by plaintiffs. Correspondence was had upon this subject, with requests for information and answers claimed not sufficient or complete, giving rise to some controversy as to when and how the complete information was obtained. It is clear, however, that it had been furnished defendant as early as August 6th. Mr. Walker, defendant’s agent at Detroit, testifies:

“On August 6th I got the information from Mr. Sauer and Mr. Flook * * * which was sent to Pittsburg, where our detail drawings were made up. * * * I came out to Ann Arbor on August 6th and went to Mr. Sauer’s office and from there to the architect’s office. From the architect’s office I got complete [622]*622information and took it with me. We did not think we had complete- information and we got that on August 6th.”,

On August 15, 1912, defendant wrote plaintiffs, inclosing prints of the shop drawings, asking for their approval. These were approved by the architect and received back by defendant on or before August 19th. On August 26th defendant sent plaintiffs prints of certain sheets “for your files.” On September 11, 1912, plaintiffs wrote defendant, calling attention to the fact that under their contract the building must be completed by November 1st, stating that they could not be held up waiting for steel, and if defendant could not fill its contract, entered into on July 23d for delivery in from 8 to 10 weeks, it was necessary for plaintiffs to be advised at once, saying further:

“If you find that you cannot furnish this material from your own mill or stock on hand then go out into the open market and procure it, but do not delay the shipment of this material under any condition.
“Should you fail to make arrangements for the shipment from your own mill or market, then we request that you instruct us to protect our interests in the way of going into the market and procuring some at the best price possible and charge your firm the difference in price, if any. This is very much against our wishes, but the situation demands some immediate action. You must appreciate the fact that since the signing of this contract July 23d seven weeks have elapsed with nothing being accomplished. Kindly advise us at once your wishes in the matter and greatly oblige.”

Nine days later, on September 20th, defendant replied :

“At the request of our Detroit office we telephoned you today, stating that the best promise we have been able to secure for delivery of unpunched material required for storehouse and shop building for the University of Michigan, was delivery complete November 20th to 30th. On this account there is no prospect [623]*623that we can ship you all this material prior to December 15th.
“There are a variety of sections requiréd for this work, and, although orders were placed promptly, the above is the result. We do not consider ourselves entirely at fault for this state of affairs on account of the delay in furnishing us with information absolutely necessary to get out the work.
“We will continue to do everything in our power to hasten this work, and if by any means we can anticipate the dates given above, we will do so, but we cannot find reason to hope that we can ship it much earlier.”

On September 27th plaintiffs answered, stating they could not be delayed, that to permit the building to go ahead they were obliged to pay in excess of defendant’s contract price $1,002 for the steel, and to that end were placing an order for the same with another company in a position to furnish it in three weeks, closing with a discussion of the subject unimportant here. The material specified in the contract was furnished by the Toledo Wire & Iron Works, and delivered f. o. b.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Todd Oakley v. Robert Rutan
Michigan Court of Appeals, 2018
Schrier v. French
242 N.W.2d 454 (Michigan Court of Appeals, 1976)
June v. Vibra Screw Feeders, Inc.
149 N.W.2d 480 (Michigan Court of Appeals, 1967)
Van Lierop v. Chesapeake & Ohio Railway Co.
57 N.W.2d 431 (Michigan Supreme Court, 1953)
Midwest Commercial Credit Co. v. Meyers
231 N.W. 49 (Michigan Supreme Court, 1930)
Triplett v. Nichols
123 S.E. 339 (Supreme Court of Virginia, 1924)
Beebe v. Cullinane
181 N.W. 1016 (Michigan Supreme Court, 1921)
Winget v. Grand Trunk Western Railway Co.
177 N.W. 273 (Michigan Supreme Court, 1920)
Rossello v. Trella
172 N.W. 420 (Michigan Supreme Court, 1919)
People v. Biossat
172 N.W. 933 (Michigan Supreme Court, 1919)
Maurer v. Greening Nursery Co.
165 N.W. 861 (Michigan Supreme Court, 1917)
Rennie v. Stelter
162 N.W. 997 (Michigan Supreme Court, 1917)
Seaman v. Rindge, Kalmbach, Logie & Co.
161 N.W. 919 (Michigan Supreme Court, 1917)
Missaukee Farm & Investment Co. v. Ferris
159 N.W. 490 (Michigan Supreme Court, 1916)
Carland v. Heckler
233 F. 504 (Sixth Circuit, 1916)
Sauer v. McClintic-Marshall Construction Co.
155 N.W. 586 (Michigan Supreme Court, 1915)
Hager v. Schliess
151 N.W. 552 (Michigan Supreme Court, 1915)
Zemon v. Trim
147 N.W. 540 (Michigan Supreme Court, 1914)
Cross v. Leonard
147 N.W. 540 (Michigan Supreme Court, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
146 N.W. 422, 179 Mich. 618, 1914 Mich. LEXIS 545, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sauer-v-mcclintic-marshall-construction-co-mich-1914.