Sauer, Inc. v. American Bituminous Power Partners, L.P.

451 S.E.2d 451, 192 W. Va. 150, 1994 W. Va. LEXIS 198
CourtWest Virginia Supreme Court
DecidedNovember 23, 1994
DocketNo. 22087
StatusPublished
Cited by1 cases

This text of 451 S.E.2d 451 (Sauer, Inc. v. American Bituminous Power Partners, L.P.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sauer, Inc. v. American Bituminous Power Partners, L.P., 451 S.E.2d 451, 192 W. Va. 150, 1994 W. Va. LEXIS 198 (W. Va. 1994).

Opinion

PER CURIAM:

This is an appeal by Sauer, Inc., from an order of the Circuit Court of Marion County dismissing its action to enforce a mechanic’s lien. In granting the dismissal, a dismissal under Rule 12(b)(6) of the West Virginia Rules of Civil Procedure, the circuit court found that Sauer, Inc., had failed to comply with the accounting requirements of W.Va. Code § 38-2-19 to maintain a mechanic’s lien and that it was thus banned from enforcing the lien. On appeal, Sauer, Inc., contends that, under the circumstance of the case, it did provide an adequate accounting and that the accounting which it provided was adequate to preserve its claim. Sauer, Inc., claims that the circuit court’s ruling was, therefore, erroneous. After reviewing the questions presented and the documents filed, this Court agrees with the appellant’s assertions. The judgment of the Circuit Court of Marion County is, as a result, reversed, and this case is remanded for further development.

By contract dated November 9, 1989, American Bituminous Power Partners, one of the appellees in the present proceeding, engaged Fru-Con Construction Corporation to design and construct a waste coal cogeneration facility in Grant Town, West Virginia. Fru-Con Construction Corporation hired a number of subcontractors to work on the project, including the appellant, Sauer, Inc. Sauer, Inc., specifically entered into three very elaborate contracts with Fru-Con Construction Corporation to provide labor and materials for portions of the cogeneration facility.

In documents filed in the present proceeding, Sauer, Inc., claims that it completely performed and fulfilled its duties under the contracts and that it provided labor and materials with a total value of $7,796,461.00. It also claims that, of this amount, it has been paid only $4,883,707.00.

Within the period prescribed by law, Sauer, Inc., on July 23, 1992, recorded a notice of mechanic’s lien in the amount of $2,912,744.00 in the Office of the Clerk of the County Commission of Marion County, West Virginia. On the next day, July 24, 1992, Sauer, Inc., caused a copy of the notice of mechanic’s lien to be served on the land owner, American Bituminous Power Partners.

Following the filing of the mechanic’s lien, American Bituminous Power Partners requested an accounting from Sauer, Inc., of the work done and the materials supplied under the contracts giving rise to the mechanic’s lien. Such request or demand is authorized by W.Va.Code § 38-2-19, which provides:

The owner may, at any time, by notice in writing, require such subcontractor, laborer, mechanic, workman or other person doing, or causing to be done, work or labor upon such building or other structure or improvement appurtenant thereto, or any such materialman or other person furnishing materials, machinery or other necessary equipment for such work, to file with such owner an itemized account of the work done or caused to be done by such laborer or other person, or of the materials or machinery or other equipment furnished by such materialman or other person for such work, which account shall show the dates upon which such work was done, or such materials were furnished, the price charged therefor, and the nature of such work or materials, and the neglect or failure of any such laborer, mechanic or other person furnishing materials, machinery or other necessary equipment for the doing of the same, so to file such itemized statement with such owner, within ten days after the receipt by him of such written notice so to do, shall release such owner from all responsibility and his property from all lien or charge for all labor done and for all materials furnished by the person so failing to file such required itemized statement, prior to the giving of such notice.

[152]*152In response to the request for an accounting, Sauer, Inc., acting through its attorney, on August 25, 1992, responded that it had provided labor and materials under three subcontracts. It rather clearly identified the subcontracts and suggested that it had performed as required. A typical part of the response stated:

The first of the subcontracts is Fru-Con Contract No. 409503.1 000137, under which Sauer agreed generally to provide all work necessary for “the planning, construction documentation (as-built drawings/layout), installation, unloading, care, custody and control of all materials required to perform the Material Handling System Work.” Sauer performed this work by mobilizing its project manager on July 15, 1991, and by supplying field labor and material beginning on August 13, 1991, and proceeding continually through and including April 19,1992. The work was substantially complete on or about March 25, 1992. The price charged for this work is $2,280,461, of which $1,718,700.50 has been paid, leaving a balance due of $561,760.50.

After receiving this response, American Bituminous Power Partners requested an itemized accounting.

On August 31, 1992, Sauer, Inc., again wrote American Bituminous Power Partners and provided somewhat more detailed information as to the work performed. For example, relating to a materials handling contract, Sauer stated:

The original material handling contract was for $1,539,000. I believe you understand the scope of this work, but nonetheless I am providing you with a copy of Sauer’s subcontract with Fru-Con. It contains a detailed listing of the drawings which define the scope of Sauer’s work. These drawings form a part of the contract between the owner and Fru-Con, thus they are in your possession and available for reference.
The material handling contract was increased by change order to $1,912,750.15, of which only $1,718,700.50 has been paid. This leaves an unpaid and undisputed balance past due and owing of $194,049.65. In addition, Sauer has claims against Fru-Con totalling $561,760.50 on this subcontract, arising out of Fru-Con’s numerous breaches.
The dates on which Sauer performed work under the original scope of the contract, the change orders, and the claim are substantially identical. These were set forth in my previous letter to you in which I advised that Sauer began supplying field labor on August 13, 1991, and proceeded continually through and including April 19, 1992. More specifically, Sauer provided approximately 26,000 man-hours of direct labor in connection with this subcontract, and worked on substantially every working day between the time it began and the time it completed. Sauer has an itemized payroll listing of all men who provided labor in connection with this subcontract, and I will provide it to you if you request it.

It appears that at this time Sauer, Inc., also provided a packet of supplementary information over three inches thick.

American Bituminous Power Partners never responded to the transmission of the additional information.

Subsequent to this activity, Sauer, Inc., timely filed an action in the Circuit Court of Marion County to enforce its mechanic’s lien.

Following the filing of the action, American Bituminous Power Partners and the other defendants filed a motion under Rule 12(b)(6) of the West Virginia Rules of Civil Procedure to dismiss for failure to state a claim upon which relief could be granted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
451 S.E.2d 451, 192 W. Va. 150, 1994 W. Va. LEXIS 198, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sauer-inc-v-american-bituminous-power-partners-lp-wva-1994.