Sauer Construction, LLC v. MC3 Solutions, LLC

CourtDistrict Court, W.D. Virginia
DecidedDecember 10, 2024
Docket7:23-cv-00193
StatusUnknown

This text of Sauer Construction, LLC v. MC3 Solutions, LLC (Sauer Construction, LLC v. MC3 Solutions, LLC) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sauer Construction, LLC v. MC3 Solutions, LLC, (W.D. Va. 2024).

Opinion

CLERK'S OFFICE US. DISTRICT COURT IN THE UNITED STATES DISTRICT COURT AT ROANOKE, VA FOR THE WESTERN DISTRICT OF VIRGINIA FILED ROANOKE DIVISION December 10, 2024 LAURA A. AUSTIN, CLER BY: s/ M.Poff, Deputy Cler SAUER CONSTRUCTION, LLC, f/k/a ) SAUER INCORPORATED ) Plaintiff/Counterdefendant, ) Civil Action No. 7:23-cv-00193 ) Vv. ) ) By: Elizabeth K. Dillon QBE INSURANCE CORPORATION, ) Chief United States District Judge Defendant, and ) ) MC3 SOLUTIONS, LLC, ) Defendant/Counterclaimant/ ) Third-Party Plaintiff ) ) Vv. ) ) BONITZ, INC., ) Third-Party Defendant. ) MEMORANDUM OPINION The claims in this case arise from contracts related to the construction of a production office lab at the Radford Army Ammunition Plant (the Project). Plaintiff Sauer Construction, LLC (Sauer) contracted with BAE Systems Ordnance Systems, Inc. to complete the Project and served as its general contractor. Sauer sub-contracted with MC3 Solutions Inc. (MC3) to perform some of the work on the Project. MC3, in turn, contracted with third-party defendant Bonitz, Inc. (Bonitz) to install resinous epoxy flooring. In its second amended complaint against MC3, Sauer alleges that MC3 performed deficiently and did not perform in a timely fashion, causing delays on the Project and damages to Sauer. (See generally 2nd Am. Compl., Dkt. No. 51.) MC3 filed a counterclaim and also a third-party complaint against Bonitz. In its first motion to dismiss, Bonitz raised several grounds for dismissal, but the court found it necessary to rule only on one. Specifically, the court

reasoned that MC3’s third-party complaint was not derivative of Sauer’s complaint—which did not mention flooring as a problem with MC3’s contract performance—and thus it was not proper under Rule 14. (See generally Mem. Op., Dkt. No. 49.) Subsequent to the court’s ruling, Sauer filed a second amended complaint with defendants’ written consent, against the same defendants. (Dkt. No. 51.) MC3 again filed an

Answer and Counterclaim against Sauer (Dkt. No. 54) and a separate third-party complaint against Bonitz (Dkt. No. 56). Currently pending before the court is Bonitz’s second motion to dismiss the second amended complaint (Dkt. 63), which MC3 opposes.1 The motion is fully briefed, was argued before the court, and is ripe for resolution. For the reasons set forth herein, the court will grant in part and deny in part the motion to dismiss. I. BACKGROUND

Sauer entered into a subcontract with MC3 to complete certain work on the Project. (2nd Am. Compl. ¶ 11, Dkt. No. 51; see also Dkt. No. 1-1 (copy of the Sauer-MC3 Subcontract).) The scope of work for that subcontract included pages of detailed tasks MC3 was to perform. The tasks fell into the following general categories, for which MC3 was to “furnish and install all . . . work”: framing, drywall/gypsum board, paint/special coatings, resilient flooring/ceramic tile, resinous epoxy floor, acoustical ceilings, and millwork. (Sauer-MC3 Subcontract, Dkt. No. 1-1, at 20–25.) Like its original complaint, Sauer’s second amended complaint contains three claims: a breach of contract claim and claim for indemnity against MC3 (Counts 1 and II, respectively) and a claim for a breach of the performance bond against defendant QBE Insurance Corp., the surety. The second amended complaint contains additional language, however, making clear that

1 Sauer has taken no position on the motion. the resinous epoxy flooring was one of the problems with MC3’s contract performance. First, Sauer specifically notes that part of the scope of work included “furnishment and installation of all resinous epoxy flooring.” (2nd Am. Compl. ¶ 13.) Moreover, the second amended complaint includes the following language: 17. Throughout the course of the Project, numerous issues arose with regard to MC3’s work and performance under the Subcontract. These issues included: MC3’s failure to supply sufficient skilled workmen and materials; failure to properly perform work with promptness and diligence; submission of inadequate submittals; and resultant delays to the critical path. These issues were experienced in connection with, without limitation, the resinous epoxy flooring scope of work.

18. Sauer incurred significant costs attributable to MC3’s deficient performance under the Subcontract and the delays caused by MC3. Much of these damages relate to and result from a failure to timely and properly complete the resinous epoxy flooring scope of work, which was, upon information and belief, subcontracted by MC3 to Bonitz, Inc.

(Id. ¶¶ 17–18 (emphasis added).) Because of these amendments, the court finds that the third- party complaint is sufficiently derivative under Rule 14.2 Thus, that basis—the sole one given by the court previously—no longer supports dismissal. MC3’s counterclaim (Dkt. No. 54), which is contained within its Answer to the Second Amended Complaint, contains a single claim for breach of contract. (Id. at 9–10 (seeking “at least $209,731.08” in damages against Sauer plus interest, legal fees, and court costs).) MC3’s amended third-party complaint (Dkt. No. 56) is brought against Bonitz. It contains four claims: (1) “contractual indemnity,” (2) “equitable indemnity,” (3) “implied contractual indemnity,” and (4) “contribution and apportionment.” (Am. 3rd-Party Compl. 4–7, Dkt. No. 56.)

2 Bonitz does not argue to the contrary. II. DISCUSSION A. Motion to Dismiss A motion to dismiss under Rule 12(b)(6) tests the complaint’s legal and factual sufficiency. See Ashcroft v. Iqbal, 556 U.S. 662, 677–80 (2009); Bell Atl. Corp. v. Twombly, 550 U.S. 544, 554–63 (2007); Giarratano v. Johnson, 521 F.3d 298, 302 (4th Cir. 2008).3 Here,

Bonitz does not challenge the third-party complaint as factually insufficient. Instead, its challenges are to the legal viability of MC3’s claims. B. Bonitz’s Arguments for Dismissal4 In its supporting memorandum, Bonitz sets forth four main arguments, some with sub- parts. Its first argument is that none of the three types of indemnification are ripe for adjudication (contractual, implied, equitable) because indemnity is only available where there has been an adjudication of the liability of the party seeking indemnity. Thus, the argument goes, the indemnity claims are not ripe and must be dismissed. At oral argument, counsel for

Bonitz essentially withdrew this argument, agreeing with MC3 that Virginia Code Ann. § 8.01-

3 Unless otherwise noted, the court omits internal citations, alterations, and quotation marks throughout this opinion. See United States v. Marshall, 872 F.3d 213, 217 n.6 (4th Cir. 2017).

4 The contract between MC3 and Bonitz does not have a choice-of-law provision. Because the court is sitting in diversity, it applies Virginia’s choice-of-law rules, which provide that the nature, validity, and interpretation of a contract are governed by the law of the place where the contract was “made.” Lexie v. State Farm Mut. Auto. Ins. Co., 469 S.E.2d 61, 63 (Va. 1996). In Virginia, a contract is “made” at the place “where the final act is done which is necessary to make the contract binding.” Hunter Innovations Co. v. Travelers Indem. Co. of Ct., 753 F. Supp. 2d 597, 602–03 (E.D. Va. 2010) (citations omitted). The parties here do not identify where that last act occurred, but even if it occurred elsewhere, it is undisputed that the contract was performed in Virginia.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Lehman v. Revolution Portfolio LLC
166 F.3d 389 (First Circuit, 1999)
Duke v. Reconstruction Finance Corp.
209 F.2d 204 (Fourth Circuit, 1954)
Giarratano v. Johnson
521 F.3d 298 (Fourth Circuit, 2008)
Uniwest Construction, Inc. v. Amtech Elevator Services, Inc.
714 S.E.2d 560 (Supreme Court of Virginia, 2011)
UNIWEST CONST. v. Amtech Elevator Services
699 S.E.2d 223 (Supreme Court of Virginia, 2010)
Estes Exp. Lines v. Chopper Exp.
641 S.E.2d 476 (Supreme Court of Virginia, 2007)
Green v. Ingram
608 S.E.2d 917 (Supreme Court of Virginia, 2005)
Lexie v. State Farm Mutual Automobile Insurance
469 S.E.2d 61 (Supreme Court of Virginia, 1996)
Carr v. Home Insurance
463 S.E.2d 457 (Supreme Court of Virginia, 1995)
Branch v. Virginia Employment Commission & Virginia Chemical Co.
249 S.E.2d 180 (Supreme Court of Virginia, 1978)
Hunter Innovations v. Travelers Indem. Co. of Ct.
753 F. Supp. 2d 597 (E.D. Virginia, 2010)
United States v. Andracos Marshall
872 F.3d 213 (Fourth Circuit, 2017)
Erie Ins. Exchange v. EPC MD 15, LLC
822 S.E.2d 351 (Supreme Court of Virginia, 2019)
Johnson's Adm'x v. Richmond & Danville R. R.
11 S.E. 829 (Supreme Court of Virginia, 1890)
Borbas v. Virginia Employment Commission
440 S.E.2d 630 (Court of Appeals of Virginia, 1994)
RSC Equipment Rental, Inc. v. Cincinnati Insurance
54 F. Supp. 3d 480 (W.D. Virginia, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Sauer Construction, LLC v. MC3 Solutions, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sauer-construction-llc-v-mc3-solutions-llc-vawd-2024.