Saturn Construction Co., Inc. v. State, No. Cv94 542073 (May 6, 1996)

1996 Conn. Super. Ct. 4154
CourtConnecticut Superior Court
DecidedMay 6, 1996
DocketNo. CV94 542073
StatusUnpublished

This text of 1996 Conn. Super. Ct. 4154 (Saturn Construction Co., Inc. v. State, No. Cv94 542073 (May 6, 1996)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Saturn Construction Co., Inc. v. State, No. Cv94 542073 (May 6, 1996), 1996 Conn. Super. Ct. 4154 (Colo. Ct. App. 1996).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION On April 16, 1991, the plaintiff, Saturn Construction Co., Inc. ("Saturn"), entered into a $22,049,800 contract ("the Contract") with the defendant, the State of Connecticut Department of Public Works ("DPW"), to build the State of Connecticut Transportation Office Complex ("the Complex"). (Plaintiff's Verified Complaint, Count One, ¶ 6). In accordance with Article 35 of the Contract and General Statutes § 49-4, Saturn executed a labor and material bond and performance bond with the Insurance Company of America ("INA"). Id., ¶ 8.

The Contract provided that Saturn was to complete the Complex by July 25, 1992. Id., ¶ 7. However, Saturn alleges that construction and building code disputes caused periodic and significant suspensions of work, the issuance of more than 80 change orders in the Complex plan and specifications, and a substantial delay in the completion of the Complex. Id., ¶ 9. In addition, Saturn alleges that the DPW issued more than 320 change orders, further delaying the completion of the Complex. Id., ¶ 10. Therefore, on May 11, 1992, Saturn told the Commissioner of the DPW that due to the large number of change orders, it could not finish the project by July 25, 1992. Id., ¶ 11. Saturn alleges that the Commissioner of the DPW told Saturn that the change orders would cease. Id. Saturn alleges CT Page 4155 that the DPW did not cease issuing changes; rather, Saturn alleges that the DPW issued 226 additional change orders after May 11, 1992. Id.

On January 20, 1993, Saturn met with the Commissioners of the DPW, the Department of Transportation ("the DOT"), and a representative from the Attorney General's Office. Id., ¶ 12. At that meeting the Commissioner of the DOT told Saturn that it had to complete the Complex by April 30, 1993. Id. In response, Saturn stated that it could not complete the Complex by said date without accelerating its work. Id. Therefore, Saturn alleges that it asked the DPW to stop issuing change orders and to authorize and compensate the accelerated work. Id. Saturn estimated that the accelerated work and pending change orders would cost $1 million to $1.5 million. Id. Saturn alleges that although the DPW agreed to these requests, between the dates of January 20, 1993 and April 13, 1993, 77 additional change orders were issued. Id., ¶¶ 13-14.

On February 26, 1993, the DPW told Saturn to decelerate its work and advise it of Saturn's anticipated completion date. Id., ¶ 15. On March 4, 1993, Saturn responded, stating that it could not return to its previous schedule due to commitments made to subcontractors. Id. On March 18, 1993, pursuant to General Statutes § 4-61 (b), Saturn served a Demand for Arbitration on the Commissioner of the DOT and the American Arbitration Association based on the delays caused by the change orders, the failure to pay additional costs due to the change orders, and the failure to pay the acceleration costs. Id., ¶ 16.

By a letter dated April 14, 1993, the DPW terminated its contract with Saturn, citing Saturn's failure to comply with Article 33(1)(c-f) of the Contract. Id., ¶ 20. Article 33(1)(c) provides that Saturn may be terminated if it "refuse or fail, after notice of warning from the Commissioner, to supply enough properly skilled workmen or proper materials. Id., ¶ 26. Article 33(1)(d) provides that Saturn may be terminated if it "shall refuse or fail to prosecute the work or any part thereof, with such diligence as will insure its completion within the period herein specified (or any duly authorized extension thereof) or shall fail to complete the work within said period." Id. Article 33(1)(e) provides that Saturn may be CT Page 4156 terminated if it "shall fail to make prompt payment to persons supplying labor or materials for the work." Id. Article 33(1)(f) provides that Saturn may be terminated if it "shall fail or refuse to regard laws, ordinances, or the instructions of the Commissioner or otherwise be guilty of a substantial violation of any provisions of this contract, then the owner, without prejudice to any other rights or remedy it may have, may by seven (7) days notice to the contractor, terminate the employment of the contractor and his right to proceed, and may take possession of the work and complete the work by contract or otherwise, as the owner may deem expedient." Id.

On June 24, 1993, the State of Connecticut approved a bond referendum for additional funds. Id., ¶ 22. Subsequently, the DOT and the Office of Policy and Management ("the OPM") entered into a Takeover Agreement with Saturn's surety, INA. Id. The Takeover Agreement stated that INA had to finish the Complex by September 22, 1993. Id. On June 24, 1993, Saturn entered into a Completion Agreement with INA to finish the Complex. Id., ¶ 24. On July 20, 1993 the OPM notified Saturn, by letter, that it would not rescind Saturn's termination. Id., ¶ 25. On November 12, 1993, after completion of the Complex, Saturn filed an amended arbitration claim. Id., Count Three, ¶ 28.

On June 15, 1994, Saturn filed a complaint against the DPW, the DOT, and the OPM seeking injunctive relief. This action, designated as Docket No. 0705198, was withdrawn on October 11, 1994.

On September 20, 1994, Saturn filed its second action, a seven-count complaint against the DPW, the DOT, and the OPM alleging that the April 14, 1993 termination was wrongful, factually unsupported, and/or made in bad faith. Specifically, Saturn contests the DPW's bases for terminating Saturn. First, Saturn alleges that it supplied a sufficient quantity of properly skilled workmen and materials to construct the Complex, thus complying with Article 33(1)(c) of the Contract. Id., Count One, ¶ 27. Second, Saturn alleges that it exercised due diligence to ensure the completion of the Complex, as evidenced by the acceleration of the work, thus complying with Article 33(1)(d) of the Contract. Id. Third, Saturn alleges that CT Page 4157 it paid all persons supplying labor and materials for the Complex, thus complying with Article 33(1)(e) of the Contract. Id. Fourth, Saturn alleges that it complied with all applicable laws, ordinances, and instructions, thus fulfilling Article 33(1)(f) of the Contract. Id. In addition, Saturn alleges that it did not receive the seven-day notice required by Article 33(1)(f) of the Contract. Id.

Saturn's allegation that the April 14, 1993 termination was wrongful, factually unsupported and/or made in bad faith forms the basis for Saturn's claims. In Count One, Saturn claims that the defendants' April 14, 1993 termination deprived Saturn of its right to the benefits of the Contract in violation of Saturn's substantive and/or procedural due process rights under theFourteenth Amendment of the United States Constitution. In Count Two, Saturn claims that the defendants' April 14, 1993 termination deprived Saturn of its right to the benefits of the Contract in violation of Saturn's substantive and/or procedural due process rights under Article 1, Section 10 of the Constitution of the State of Connecticut.

In Count Three, Saturn claims that the defendants failed to comply with General Statutes § 4-61 in violation of Saturn's due process rights under theFourteenth Amendment of the United States Constitution. In Count Four, Saturn claims that the defendants failed to comply with General Statutes § 4-61

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gomillion v. Lightfoot
364 U.S. 339 (Supreme Court, 1960)
Board of Regents of State Colleges v. Roth
408 U.S. 564 (Supreme Court, 1972)
Logan v. Zimmerman Brush Co.
455 U.S. 422 (Supreme Court, 1982)
Cleveland Board of Education v. Loudermill
470 U.S. 532 (Supreme Court, 1985)
Hartford Accident & Indemnity Co. v. Williamson
216 A.2d 635 (Supreme Court of Connecticut, 1966)
City of Hartford v. American Arbitration Ass'n
391 A.2d 137 (Supreme Court of Connecticut, 1978)
England v. Town of Coventry
439 A.2d 372 (Supreme Court of Connecticut, 1981)
Hartford Electric Light Co. v. Water Resources Commission
291 A.2d 721 (Supreme Court of Connecticut, 1971)
Dennison v. Klotz
535 A.2d 1317 (Supreme Court of Connecticut, 1988)
Carchidi v. Rodenhiser
551 A.2d 1249 (Supreme Court of Connecticut, 1989)
Connecticut Education Ass'n v. Tirozzi
554 A.2d 1065 (Supreme Court of Connecticut, 1989)
Double I Ltd. Partnership v. Plan & Zoning Commission
588 A.2d 624 (Supreme Court of Connecticut, 1991)
Novametrix Medical Systems, Inc. v. BOC Group, Inc.
618 A.2d 25 (Supreme Court of Connecticut, 1992)
RK Constructors, Inc. v. Fusco Corp.
650 A.2d 153 (Supreme Court of Connecticut, 1994)
Harkless v. Rowe
657 A.2d 562 (Supreme Court of Connecticut, 1995)
Advest, Inc. v. Wachtel
668 A.2d 367 (Supreme Court of Connecticut, 1995)
Dennison v. Klotz
532 A.2d 1311 (Connecticut Appellate Court, 1987)
International Ass'n of Firefighters, Local 786 v. Serrani
602 A.2d 1067 (Connecticut Appellate Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
1996 Conn. Super. Ct. 4154, Counsel Stack Legal Research, https://law.counselstack.com/opinion/saturn-construction-co-inc-v-state-no-cv94-542073-may-6-1996-connsuperct-1996.