Sargent v. State Road Commission

2 Ct. Cl. 228
CourtWest Virginia Court of Claims
DecidedDecember 14, 1943
DocketNo. 239
StatusPublished

This text of 2 Ct. Cl. 228 (Sargent v. State Road Commission) is published on Counsel Stack Legal Research, covering West Virginia Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sargent v. State Road Commission, 2 Ct. Cl. 228 (W. Va. Super. Ct. 1943).

Opinion

ROBERT L. BLAND, Judge.

On November 20, 1934, the state road commission received sealed proposals for building and completing, according to plans and specifications prepared therefor, a certain road in Tyler county, West Virginia, known as project no. 3389— p.w.s. — 828, being approximately 27,984 feet in length. Claimant Charley Sargent was the successful bidder. He entered into a contract with the state under date of November 28, 1934, for the completion of the project in accordance with [229]*229the plans and specifications provided therefor. The work was to begin on or before December 1, 1934, and be completed on or before June 1, 1935. It was agreed that time should be of the essence of the contract. The work to be done under the terms of the contract contemplated approximately 200 cubic yards of excavation according to plans, including refilling, at $1,00 per cubic yard, 5000 cubic yards of gravel bottom course, complete in place, at $4.10 per cubic yard, 5000 cubic yards of gravel top course, complete in place, at $4.T0 per cubic yard, 800 lineal feet 8 inch perforated corrugated metal pipe underdrain, complete in place, at .75 per lineal foot, 150 cubic yards loose stone for underdrains, delivered in place at $2.00 per cubic yard and 28,228 lineal feet of prepared subgrade and shoulders at .05 per lineal foot. Thus it will be seen that said contract provided different items for different types of work.

The contractor agreed that he was fully informed as to all conditions affecting the work to be done, as well as to the labor and materials to be furnished for the completion of the contract, and that such information was received by personal investigation and research and not wholly from the estimates of the engineers, and that he would not make claim against the state by reason of estimates, tests or representations theretofore made by any officer or agent of the state.

It was provided that the work to be done under the contract should be performed in accordance with the true intent and meaning of the plans and specifications, made parts of the contract.

The project was accepted by the road commission and the contractor released from further responsibility under the terms of the contract on November 25, 1935.

The full length of the road when completed was 27,295 lineal feet with a width of 18 feet.

[230]*230The final es límale shows 1hat (he road commission paid claimant $40,634.04 for work done and performed by him under said contract.

On January 11, 1943, seven years, one month and sixteen days after the completion of the project, said Sargent filed a claim in this court against the state for additional compensation to which he insists he is entitled to be paid, and for which he now seeks an award, on account of said road project in the principal sum of $9,710.00, made up of the following items, to-wit:

1. Payment for 553.18 cubic yards of gravel at $4.10 per cubic yard $2,368.03

2. Reimbursement for 6,605.35 tons of gravel at .50 per ton .3,302.67

3. Reimbursement for the cost of erecting scales 300.00

4. Reimbursement for extra maintenance 3,840.00

Claimant also maintains that he is entitled to be paid interest at the rate of 6% annually on the above aggregate amounts from January 1, 1936.

We shall consider the amount claimed under the first item, namely, $2,368.03. It may be stated, however, at this juncture that there is an error of $100.00 in the amount of this claim. It is apparent that 553.18 cubic yards at $4.10 per cubic yard would amount to $2,268.03 instead of the sum of $2,368.03 as asserted by claimant.

The specifications provided that the yardage should be paid for on the number of cubic yards of surface material, compacted by manipulation and traffic, in place on the road. It appears from the evidence that when claimant concluded that he had placed a sufficient quantity of gravel on the top and bottom courses to make six inches in thickness, when compacted, that the inspector on the project disagreed with him [231]*231and insisted that he should place still more and additional gravel thereon which he accordingly did. Subsequently a core drill test disclosed that claimant had not only placed the required six inches of thickness on the road when compacted as required by the specifications but had in addition thereto placed three-eighths inch on its entire width of eighteen feet and length of 27,295 lineal feet. These tests showed that claimant had actually placed 553.18 cubic yards on the road over and above the thickness of six inches required by the specifications, and 553.18 cubic yards at $4.10 per cubic yard would amount to $2,268.03.

L. B. White, assistant to the state construction engineer, one of whose duties is to pass on final payments to contractors, and who is shown by the evidence to have reviewed every final payment made by the state road commission since 1930, introduced as a witness on behalf of the state, testified that claimant was paid for 9,098.33 cubic yards, the actual planned thickness of the road at six inches, and also 266.54 cubic yards additional which he said was on account of the extra thickness, making a total of 9,364.84 cubic yards. At $4.10 per cubic yard 9,364.84 cubic yards would amount to $38,395.85. Claimant admits having been paid for 9,364.84 cubic yards, but he says that 266.84 cubic yards thereof was for sand and extra gravel. He states that 123.22 yards represented sand delivered to the job by him under authorization of H. McGraw, district engineer, in a letter addressed to him under date of September 12, 1935, and that 133.29 yards was for extra gravel used in widening places where the road was over eighteen feet, in approaches coming into the road and at a point where the subgrade was soft.

The final estimate shows that claimant was paid for the bottom course the sum of $18,651.60 and for the top course the sum of $19,744.25. These two payments would include the actual planned thickness of six inches for the two courses, and in addition thereto 266.84 cubic yards, the amount for which claimant says he was paid for the additional sand delivered [232]*232and extra gravel used in widening the road, and approaches coming therein and in filling a soft place in the road. Claimant says, however, that although he has been paid for the 266.84 cubic yards aforesaid, he has received no payment whatever for the additional thickness over and above the planned depth of six inches.

Mr. White explains the manner of payment as follows: “Well, from the theoretical thickness, actual thickness called for in the plans, we computed the yardage. Then we took the actual tonnage that Mr. Sargent said he placed on the road after the controversy arose as to whether it was actually six inches thick or not. That was taken from the récords furnished by the contractor. From those records I arrived at the actual weight, and reduced it back to cubic yards, which made 266 cubic yards.” Assuming, therefore, that it was the purpose of the road commission in paying the final estimate to include therein compensation to claimant at the contract price for the additional gravel placed by him on the road over and above the planned thickness of six inches, it would appear from the testimony of Mr. White that claimant was not really paid for the actual additional number of cubic yards of gravel placed by him on the road.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
2 Ct. Cl. 228, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sargent-v-state-road-commission-wvctcl-1943.