correspondence between [the parties] show that Sturtevant was sometimes referred to
by the Town, and by himself, as an individual and sometimes as a corporation ... [f]or
example, the Town payment records ...show that he was paid .. .in various capacities,"
the Law Court nonetheless upheld the finding of the trial court that no assignment had
occurred).l Therefore, the Court does not find sufficient evidence to support the
Plaintiffs' claim that the Contracts were assigned to Mason individually.
1 The Court also does not find sufficient evidence to support a piercing the corporate
veil argument. The Law Court has stated that before a court may pierce the corporate veil, a plaintiff must establish (1) that "the defendant abused the privilege of a separate corporate identity" and (2) that "an unjust or inequitable result would occur if the court
6 Thus, the Court does not find that Mason is personally liable for any of the
Plaintiffs' Counts. Nor does the Court find sufficient evidence to implicate J. Mason
Contract Cutting, Inc. as liable for any of the Plaintiffs' asserted Counts. Accordingly,
the Court dismisses all claims against Mason individually and J. Mason Contract
Cutting, Inc.
At the close of the Plaintiffs' case, the Court granted the Defendants' Rule 50(d)
Motion as to Counts VI through XI of the Plaintiffs' Complaint. The Court addresses
the remaining Counts below.
A. Breach of Contract
The Court finds that the termination of the Subdivision Contract and the Gravel
Pit Contract by the Plaintiffs was proper as FLH had breached the Contracts in two
specific ways. First, FLH failed to keep full, detailed and accurate accounts and records.
Second, FLH failed to manage compliance with State of Maine laws and to timely
process and obtain necessary State approvals.
The Plaintiffs have also claimed other breaches of contract, including that FLH
failed to perform the work required under the Contracts in a competent, timely, good
and workmanlike manner and that FLH failed to perform under the Contracts in the
best interest of the Plaintiffs. The credible evidence does not support these claims.
recognized the separate corporate existence." Johnson v. Exclusive Properties Unlimited, 1998 ME 244, <]I 6, 720 A.2d 568, 571. In this case, both Sargent and Mason established limited liability companies for the purposes of developing the subdivision and gravel pit and executing the contracts related to each. There is no credible evidence that Mason used FLH as a means to cover up fraud or illegality. Accordingly, Mason did not abuse the privilege of FLH. Nor does equity require piercing the corporate veil in this case. Sargent is an experienced businessman well aware of the characteristics of separate corporate identities (as evidenced by the fact that he established two new limited liability companies of his own to be signatories to the Subdivision and Gravel Pit Contracts); he chose to contract with FLH and must now accept what he agreed to.
7 1. Damages: Subdivision Contract
The Plaintiffs paid to FLH the sum of $407,204.96 under the Subdivision Contract
after credit for the balance remaining in the bank account, which sum includes the
$100,000.00 advance.
Under the Subdivision Contract, FLH was obligated to complete the subdivision
for the contract price of $195,500.00 plus the actual power installation costs, the
management fee and agreed upon change orders. In connection with the subdivision,
the Plaintiffs agreed to contribute $10,000.00 toward the cost of a solar model home;
widening the road by 6 feet and paving it; chipping wood for the roadside entrances to
the individual house lots; installing 20 driveway culverts; and erecting a 52-foot rock
wall at the subdivision entrance. The Court finds the allowable costs associated with
the development of the subdivision beyond the $195,500.00 Contract price are as
follows:
Solar Model Home $10,000.00
Road Paving $59,118.10
Wood Chipping for House Lots $7,063.20 (Exhibit 60) Driveway Culverts (Exhibit 60) $3,904.21
52' Rock Wall (Exhibit 60) $4,976.83
Management Fee through termination (June $40,000.00 1, 2005 - May 22, 2006) Actual Power Installation Costs Reasonably $54,323.38 Incurred TOTAL $179,385.72
Thus, the total of both the Contract price ($195,500.00) and the combined power
installation costs, management fee and further agreed upon costs ($179,385.72) is
8 $374,885.72. The Plaintiffs are entitled to a credit for the $407,204.96 paid plus th
expenses reasonable to complete the contract, including:
Detention Pond $15,000.00
Grading and Seeding Erosion Control $2,500.00
TOTAL $17,500.00
Therefore, FLH owes $49,819.24 in damages to the Plaintiffs for breach of the
Subdivision Contract.
2. Damages: Gravel Pit Contract
While the Gravel Pit Contract states that "[t]he work shall continue as business
requires or until the $100,000.00 allowance is fully used if sooner unless otherwise
agreed in writing by the parties," and no such written agreements were ever executed
by the parties, the Court finds that the parties waived this provision requiring a writing
by their course of dealing. Accordingly, Sargent Gravel, LLC was obligated to pay the
actual costs incurred in the development of the gravel pit, to the extent those charges
were reasonable under the circumstances or expressly agreed to. By June 10, 2005, more
money was needed for the gravel pit than the $100,000.00 set forth in the Gravel Pit
Contract and from then until at least March 20, 2006, the Plaintiffs advanced money to
FLH (see Pl.'s Ex. 19 and De£"s Ex. 14) for the gravel pit project. In addition, the
Plaintiffs made payments to others or were entitled to credit for additional sums,
including extracted material sale proceeds. The Court finds that the Plaintiffs' total
post-purchase investment in the gravel pit was $572,971.82.
Prior to the termination of the Contract, FLH was not accurately differentiating
the costs attributable to the Gravel Pit Contract from the costs chargeable under the
9 Subdivision Contract and the Plaintiffs were not insisting on such specificity or
questioning the allocation made by FLH in its requests for additional funds. As a
consequence, there was not a meeting of the minds as to what charges were properly
allowable to the Gravel Pit Contract or what expenses were reasonable under the
Contract as it evolved. The Court finds that the charges that are reasonable under the
Gravel Pit Contract and pursuant to the parties' course of dealing is a function of how
much material was processed at the gravel pit. The parties are in substantial
disagreement about this and considerable evidence was adduced by each side as to the
volume of material handled.
The Court finds that Kurt Youland, a retired excavator and developer is a
credible witness insofar as he testified about reasonable expenses in the industry to
process extracted materials. However, the court does not find his testimony concerning
the volume of material processed at the site to be credible because that testimony relies
on the testimony of John Toothaker and Greg Holt, two witnesses the Court does not
find credible.
The court further finds that the amount of materials processed at the gravel pit
and the reasonable costs associated with the processing are as follows:
49,300 Cubic Yards of Crushed Rock @ $5.00 $246,500.00 per yard Blasting $72,000.00 Clearing 4 Acres @ $6,000.00 per acre $24,000.00 Removal of 22,000 Cubic Yards of $22,000.00 Overburden @ $1.00 per yard Processing 40,000 Cubic Yards of $120,000.00 Overburden @ $3.00 per yard Screening 4,000 Cubic Yards of Loam @ $3.50 $14,000.00 per yard Hammering 10,000 Cubic Yards of Rock @ $20,000.00 $2.00 per yard TOTAL $518,500.00
10 In addition to the extraction and processing costs, the Plaintiffs were obligated to
pay FLH $1,667.00 per month until termination of the contract, or $20,000.00, and 3% of
gross sales of $20,000.00, or $600.00. Further, the Plaintiffs agreed to pay $4,000.00 for
bathroom renovations in connection with the gravel pit operation. Thus, in addition to
the $518,500.00 set forth above, the Plaintiffs also properly paid $24,600.00.
Therefore, the total allowable costs with respect to the gravel pit equal
$543,100.00 and the amounts paid or credited to the Plaintiffs total $572,971.82, leaving
a balance owed to the Plaintiffs by FLH of $29,871.82.
3. Effect of the Mortgage Deeds, Security Agreements and Financing Statements
At the same time that the P&S Agreement, Subdivision Contract and Gravel Pit
Contract were executed, two Mortgage Deeds, Security Agreements and Financing
Statement ("mortgages") were also executed. One of the mortgages was executed by
Mason individually and the other by Land and Legacy, Inc. For purposes of this
decision, the Court will assume that the mortgages were properly executed. 2 Both
mortgages state that they are being given "as security for payment and performance of
Mortgagor's obligations under a certain Subdivision Construction and Development
Agreement and as may be required by a Gravel Pit Development and Operation
Agreement. .." The mortgagors are Mason individually and Land and Legacy, Inc.,
neither of which owe any obligations under either the Subdivision Contract or the
Gravel Pit Contract (see discussion supra setting forth the reasons why this Court does
not find that Mason individually is obligated under either Contract). Accordingly,
these mortgages are a nullity.
2 As noted above, the mortgage from Mason personally is actually signed by Mason as President of Land and Legacy, Inc. and the mortgage from Land and Legacy, Inc. is actually signed by Mason individually.
11 B. Conversion
The credible evidence does not support the Plaintiffs' claim that the Defendants
converted their property except in two specific instances: the Napa Auto Parts retained
by FLH and the blue Chevy pick-up truck disposed of by FLH. The Court therefore
awards damages to the Plaintiffs in the amount of $1,000.00 for the Napa Auto Parts
and $1,800.00 for the Chevy truck for a total damages award of $2,800.00 on the
Plaintiffs' Conversion Count.
C. Breach of Fiduciary Duty
The Court finds no breach of fiduciary duty by the Defendants. Both the
Subdivision Contract and the Gravel Pit Contract expressly state that the relationship of
FLH thereto is "as an independent contractor and not an agent of" the Plaintiffs.
Subdivision Contract § 3.1; Gravel Pit Contract § 3.1. Thus, there is no contractual
fiduciary relationship. Nor is there a common law fiduciary relationship. The Law
Court has identified the two "salient elements" of a fiduciary relationship as: (1) "the
actual placing of trust and confidence in fact by one party in another" and (2) "a great
disparity of position and influence between the parties at issue." Bryan R., 1999 ME 144,
<[ 19, 738 A.2d at 846, quoting Morris v. Resolution Trust Corp., 622 A.2d 708, 712 (Me.
1993) (internal quotations omitted). The credible evidence does not support a finding
that a disparity existed between the parties. Indeed, Sargent is an experienced
businessman whose various companies and affiliates produce gross annual revenue of
$220 million dollars. Accordingly, the Court finds no evidence of the existence of a
fiduciary relationship; therefore, there can be no breach of such a relationship.
D. Unjust Enrichment
"Unjust enrichment describes recovery for the value of the benefit retained when
there is no contractual relationship, but when, on the grounds of fairness and justice, the
12 law compels performance of a legal and moral duty to pay." A.F.A.B., Inc. v. Town of
Old Orchard Beach, 639 A.2d 103, 105 n. 3 (Me. 1994). In the instant case, there are
various express contracts between the parties, the existence or validity of which are not
disputed. Therefore, unjust enrichment is not proper in this case.
E. Negligent and Intentional Misrepresentation
The Plaintiffs have claimed that the Defendants engaged in intentional and
negligent misrepresentation. The credible evidence in this case does not support those
claims.
II. The Defendants' Counterclaims
The Defendants ,asserted various Counterclaims against the Plaintiffs. The Court
finds that the credible evidence does not support Counterclaims I through VIII. The
Defendants did not present evidence on Counterclaim IX. The Court finds no breach of
the option contract, as asserted in Counterclaim X, and therefore does not find that the
option contract is voided. On all Counterclaims, the Court finds for the Plaintiffs and,
accordingly, awards no damages to the Defendants.
III. Attorney's Fees
The Plaintiffs assert that they are entitled to attorney's fees pursuant to this
clause, which appears in both the Subdivision Contract and the Gravel Pit Contract:
[FLH] agrees to indemnify, defend and hold harmless the [Plaintiffs] from and against any and all claims, losses, damages, expenses (including reasonable attorney's fees), suits, or actions whatsoever caused by [FLH's] negligence, acts, omissions, or violation of applicable laws, rules or regulations, or for acts in violation of this Agreement which continue after written notice of default.
Subdivision Contract § 3.1; Gravel Pit Contract § 3.1.
13 The Court notes as an initial matter that it is not clear whether this provision
entitles the Plaintiffs to collect attorney's fees from FLH in all instances or only when
claims are asserted by a third party. However, even assuming that first party claims are
included within the scope of this indemnification clause, the Court finds that the
Plaintiffs did not send written notice of default to FLH as they are required to do as a
prerequisite to indemnification from FLH. In May 2006, the Plaintiffs via their attorney
sent a letter claiming that FLH had defaulted under the Contracts. This letter also
terminated the Contracts. Thus, there were no continuing violations of the Agreement
after written notice of default because the Contracts had been terminated. Nor did the
letter sent in May 2006 allege that FLH had converted the Napa Auto Parts and Chevy
truck. Accordingly, the Plaintiffs are not entitled to attorney's fees.
Therefore, the entry is:
Judgment for the Plaintiffs Bruce Sargent, Sargent Holdings, LLC and Sargent Gravel, LLC against Frontier Land Holdings, LLC in the amount of $82,491.06, together with pre-judgment interest at the rate of 7.36% and post-judgment interest at the rate of 10.99%, and for their costs.
The clerk shall incorporate this Decision into the docket by reference pursuant to M.R. Civ. P. 79(a).
Dated at Portland, Maine this 11 ~ day of J<46..,4, 2007.
Robert E. Crowley Justice, Superior Court
14 ,-~ • T •• ... CUMBERLAND COUNTY SUPERIOR COURT PO BOX 287 PORTLAND ME 04112
First Class Mail 11811\1 SSel~ ISAI:I
~ DAVID HIRSHON ESQ 0.fD~· TOMPKINS CLOUGH HIRSHON & LANGER PO BOX 15060 PORTLAND ME 04112-5060
~ ~ ... • CUMBERLAND COUNTY SUPERIOR COURT ~ ~ PO BOX 237 PORTLAND ME 04112
~ First Class Mail 11811\1 SSBIO ISJ!:J
~ CHRISTOPHER BRJUIS0N ESQ -'ar ~ THOMAS DOUGLAS ESQ MURRAY PLlWill & HURRAY PO BOX 9785 PORTLAND ME 04104
~ ~ A. A. .. ....