Sargent & Lundy v. State

48 Ill. Ct. Cl. 333, 1996 Ill. Ct. Cl. LEXIS 13
CourtCourt of Claims of Illinois
DecidedJanuary 30, 1996
DocketNos. 91-CC-3559, 92-CC-0604 cons.
StatusPublished
Cited by2 cases

This text of 48 Ill. Ct. Cl. 333 (Sargent & Lundy v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sargent & Lundy v. State, 48 Ill. Ct. Cl. 333, 1996 Ill. Ct. Cl. LEXIS 13 (Ill. Super. Ct. 1996).

Opinion

OPINION

Frederick, J.

This case comes before the Court on Respondents motion to dismiss and for summary judgment. These two cases have been consolidated for trial purposes. The Court has carefully reviewed all of the pleadings in this case, and the Court has heard the oral arguments of counsel for all of the parties.

The Facts

Pursuant to the Low-Level Radioactive Waste Policy Act of 1980, 42 U.S.C., 2021b, et seq., the Respondent, State of Illinois, was designated by the Central Midwest Interstate Low-Level Radioactive Waste Commission as the entity responsible for providing a low-level radioactive waste disposal facility for the State of Illinois and the Commonwealth of Kentucky. Acting through the Illinois Department of Nuclear Safety (“IDNS”), the State of Illinois entered into a contract with Westinghouse Electric Corporation (“Westinghouse”) after Westinghouse submitted a proposal for the design, development, construction, and operation of a low-level radioactive waste disposal facility on land to be selected and acquired by IDNS for that purpose. The contract between the State of Illinois and Westinghouse was executed effective September 1,1988.

In May of 1989, Westinghouse abandoned the project. Westinghouse failed to make substantial progress in any phase of the work. After Westinghouse s abandonment of the project, the Respondent was forced to start the project over again with a new contractor. At the time Westinghouse stopped work on the project, the State had paid Westinghouse and its subcontractors, including Claimants, Sargent & Lundy and The Earth Technology Corporation, in excess of $1.85 million for unusable work. Also, at the time Westinghouse stopped working, it had submitted invoices in excess of $1.6 million which the Respondent has declined to pay. Westinghouse has never sued the State of Illinois to recover this $1.6 million from the State of Illinois.

On February 6, 1989, Claimant, The Earth Technology Corporation, executed a subcontract with Westinghouse to provide environmental studies in connection with the low-level waste facility project. In early May of 1989, just weeks before Westinghouse abandoned the project, Claimant, Sargent & Lundy, signed a subcontract with Westinghouse to provide design and engineering services. The Respondent did not participate in the negotiations of these two subcontracts with Westinghouse. A memorandum prepared by R.J. Suslick, Sargent & Lundy’s project manager, indicated the State was purposely excluded from these negotiations. The memorandum stated, “IDNS had expressed an interest to Westinghouse to participate in their subcontract negotiations with Sargent & Lundy. Westinghouse denied this request.”

The Claimants claim that they are owed money for work they did prior to Westinghouse’s abandonment of the project. The Earth Technology Corporation chairman and CEO, Jack Schoustra, repeatedly threatened to sue Westinghouse but The Earth Technology Corporation never acted on those threats, and neither Claimant has sued Westinghouse to recover any monies.

In these consolidated actions, Sargent & Lundy and The Earth Technology Corporation, subcontractors to Westinghouse, seek to recover directly from the State for unpaid invoices that they submitted to Westinghouse. There is no dispute that neither Sargent & Lundy nor The Earth Technology Corporation had a contract with the State. Both Sargent & Lundy and The Earth Technology Corporation were subcontractors of Westinghouse and received payment from the State based on invoices they submitted to Westinghouse. The contract between Westinghouse and the State did specify that the State would pay Sargent & Lundy and The Earth Technology Corporation directly and not through Westinghouse. It is uncontradicted that this procedure was adopted for the benefit of the State in an effort to save the State the cost of Westinghouse’s substantial mark-up.

The Respondent’s contract with Westinghouse provides that Westinghouse was to be paid on a cost plus basis. The State’s contract with Westinghouse provided:

“B. The services of all Subcontractors, other than of Sargent & Lundy and Earth Technology, in performance of the Work and the costs of all materials used by (Westinghouse) or any Subcontractor, other than Sargent & Lundy and Earth Technology, in performance of the Work shall be invoiced to the Department at one hundred ten percent (110%) of the sum of actual cost plus (Westinghouse’s) general and administration cost as hereinafter defined (‘G&A’). (Westinghouse’s) G&A rate for 1988 shall be forty-eight percent (48%) * * “.
C. The services of, and the costs of all materials used by, Sargent & Lundy and Earth Technology shall be invoiced to the Department at face value. In addition, (Westinghouse) may invoice the Department for a fee of not more than ten percent (10%) of any amount invoiced to the Department for Sargent & Lundy and Earth Technology, and any additional direct costs actually incurred by (Westinghouse) in managing and administering the Sargent & Lundy and Earth Technology Subcontracts, using the rates specified in part (A) above.”

The State refuses to pay Claimants.

The Law

Although Claimants have no privity of contract with the Respondent, the Claimants have failed to sue Westinghouse with whom they have privity of contract. Because there is no privity of contract with the State and because this Court will only imply a contract in very limited emergency situations, the Claimants seek to recover against the State of Illinois as third-party beneficiaries. This is not an emergency situation where this Court would consider finding an implied contract. There is no other basis upon which Claimants could recover on their claims before this Court at this time.

Therefore, the only way the Claimants could possibly recover is if Claimants are found to be third-party beneficiaries of the agreement between the State of Illinois and Westinghouse which was a public contract in existence prior to the two subcontracts. However, the public prime contract between the State of Illinois and Westinghouse specifically states, “Nothing in this agreement, however, shall create or be deemed to create any third-party beneficiary rights * * Under Illinois law, there is a strong presumption against creating rights in a third-party beneficiary. (Midwest Concrete Products Co. v. LaSalle National Bank (1981), 94 Ill. App. 3d 394.) To overcome this presumption, the intent to benefit a third party must affirmatively appear from the language of the instrument and the circumstances surrounding the parties at the time of its execution. (Bates & Rogers Construction Corp. v. Greeley & Hansen (1985), 109 Ill. 2d 225.) The Court in Bates & Rogers, supra, stated:

“Only third parties who are direct beneficiaries have rights under a contract. It is not enough that the third parly will reap incidental benefits from the contract. The test is whether the benefit to the third person is direct to him or is but an incidental benefit to him arising from the contract. A third party is a direct beneficiary when the contracting parties have manifested an intent to confer a benefit upon the third party.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Farrell v. State
52 Ill. Ct. Cl. 275 (Court of Claims of Illinois, 2000)
Haendel v. State
50 Ill. Ct. Cl. 224 (Court of Claims of Illinois, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
48 Ill. Ct. Cl. 333, 1996 Ill. Ct. Cl. LEXIS 13, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sargent-lundy-v-state-ilclaimsct-1996.