Santosh Mukerji and Trimcos, LLC v. Aquatic Solutions of Texas
Opinion
Opinion issued August 19, 2025
In The
Court of Appeals
For The
First District of Texas
Mukerji agreed in writing to guarantee payment to AST, but is factually sufficient to support the jury’s finding regarding the amount of money Trimcos owes AST.
Background
Raffy Bell hired Trimcos, which Mukerji owned at the time, to be the general contractor for the construction of a commercial building in Harris County. Trimcos entered into three written contracts with subcontractor AST regarding steel, glass, and facade work for the project. AST asserts that it later entered into additional contracts with Trimcos for various other aspects of the project.
Claiming that Trimcos failed to pay all monies owed, AST sued Trimcos and Mukerji for breach of contract and other claims.1 Trimcos and Mukerji answered, and Trimcos asserted counterclaims against AST. After three days of evidence, the jury found in favor of AST on its claims for breach of contract2 and quantum meruit against Trimcos, determining AST is entitled to $97,801.00 in damages. The jury also found Mukerji agreed in writing to answer for Trimcos’s debt. The jury rejected Trimcos’s counterclaims.
The parties filed post-verdict motions, and the trial court rendered judgment on the jury’s verdict. Trimcos and Mukerji now appeal.
1 AST also sued other defendants who are not parties to this appeal.
2 The only additional contract claimed by AST that the jury found did not exist was for beam and angle work.
Analysis
On appeal, Mukerji challenges the jury’s finding that he guaranteed Trimcos’s debt to AST, and Trimcos challenges the jury’s damages award (but not the jury’s liability findings). A. No evidence supports finding that Mukerji is a guarantor In issue one, Mukerji argues the evidence is legally and factually insufficient to support the jury’s finding that he agreed “in a writing signed by him to answer for the debt or default, if any, of Trimcos.” We agree.
In support of the jury’s finding, AST refers to two credit-card receipts which show that downpayments of $25,000 each were made to AST regarding glass work for the subject project. The receipts bear Mukerji’s electronic signature, but there is no language indicating that Mukerji was agreeing to guarantee any aspect of Trimcos’s debt to AST. We hold there is no evidence to support the challenged jury finding and sustain this issue. See Altice v. Hernandez, 668 S.W.3d 399, 409 (Tex. App.—Houston [1st Dist.] 2022, no pet.) (providing established standard for reviewing legal sufficiency of evidence); Wheelock v. Trim Elec., Inc., No. 01-12- 00475-CV, 2013 WL 3233239, at *6 (Tex. App.—Houston [1st Dist.] June 25, 2013, no pet.) (mem. op.) (explaining guarantee agreement must be in writing and contain all essential elements of the agreement, including “a manifestation of intent to guaranty the obligation”).
B. The evidence is factually sufficient to support the amount of damages In issue two, Trimcos argues that the evidence is factually insufficient to support the jury’s finding that Trimcos owed AST $97,801.
When reviewing a factual-sufficiency challenge, we must consider and weigh all the evidence in a neutral light, understanding that the jury is the sole judge of the credibility of witnesses and the weight to be given their testimony. Altice, 668 S.W.3d at 410. After considering and weighing all the evidence, we set aside the judgment only if the evidence supporting the finding is so weak as to make the judgment clearly wrong and manifestly unjust. Ifiesimama v. Haile, 522 S.W.3d 675, 683–84 (Tex. App.—Houston [1st Dist.] 2017, pet. denied).
Trimcos begins by arguing the jury incorrectly determined Trimcos’s credit for past payments to AST was $497,909 because the following evidence proved the past payment totaled $583,436.87: (1) K1 forms3 AST signed indicating Trimcos had paid $457,363 regarding various aspects AST’s work; (2) checks from Trimcos to AST totaling $92,950 in additional payments; and (3) an AST invoice showing Trimcos paid $33,123.87 for stucco material. But AST presented testimony and documents establishing that Trimcos’s past payments totaled $497,909, including
3 Trimcos also appears to argue that the payments reflected in the K1 forms should have been automatically credited because the forms comply with section 53.284 of the Texas Property Code, titled “Forms for Waiver and Release of Lien or Payment Bond Claim.” See TEX. PROP. CODE § 53.284. We do not consider this issue because Trimcos failed to preserve it in the trial court. See TEX. R. APP. P. 33.1(a).
Trimcos’s own payment ledger. The jury was free to believe this evidence over the evidence Trimcos highlights for the following three reasons. See FMC Techs., Inc. v. Murphy, 679 S.W.3d 788, 815 (Tex. App.—Houston [1st Dist.] 2023, pet. denied) (“We assume that the jury resolved all conflicts in the evidence in accordance with its decision if a reasonable factfinder could have done so.”).
First, AST’s representative, Fadi Harb, testified that AST signed the K1 forms because Mukerji told him the bank needed the forms to pay Trimcos but that AST would be paid the money owed. Harb testified he was deceived into signing the K1 forms. Mukerji did not appear at trial due to illness, but Trimcos’s representative, Robin Morales, testified it would be untruthful for a contractor to ask a subcontractor to sign a K1 form that misstates the amount of payments made in order for the contractor to obtain the bank’s payment. Morales also could not explain why Trimcos’s internal ledger showed Trimcos made almost $100,000 less in payments than as reflected in the K1 forms.
Second, Trimcos’s internal ledger showed that the $92,950 in “additional”
payments was actually part of the $497,909 in payments Trimcos made.
Third, Harb testified that, while AST originally credited Trimcos $33,123.87 for purchasing the stucco material, he later confirmed with Trimcos that the correct amount of the credit was $25,963.
Trimcos next argues AST’s records show that project-owner Bell—not Trimcos—authorized $9,750 in additional glass work, which AST improperly increased to $29,000 in a later invoice. Trimcos contends that, because it did not approve this additional work,4 and AST artificially inflated the amount owed, the jury should not have included it in the damages finding.
Again, there is evidence rebutting Trimcos’s argument. Harb testified Trimcos approved a change to the type of glass used which increased the amount owed, and Bell simply chose the color of glass. Harb had multiple discussions with Mukerji about the price of the additional glass work and told Mukerji there was a certain price-range within which the work would be done. Harb’s testimony further supports a finding that he prepared a prework invoice quickly that had the additional work priced at $9,750, but that AST sent an invoice after the work had been completed reflecting the actual amount owed as $29,000. Harb explained the reason for this price increase was because Trimcos decided to switch from black to white “spender glass.” Additionally, the representative of AST’s glass sub-subcontractor,
4 On appeal, Trimcos notes that the written contracts required that Trimcos approve in writing any additional work. Trimcos did not seek a legal ruling from the trial court that the written contracts barred oral approval of additional work, and the unobjected-to jury charge included an instruction that oral agreements may be enforceable. The jury found Trimcos and AST entered into a contract for the additional glass work separate from the original glass work contract, and Trimcos does not challenge that finding on appeal. Accordingly, we are not tasked with determining whether the written-approval provision legally barred AST’s reliance on Trimcos’s oral approval.
Free access — add to your briefcase to read the full text and ask questions with AI
Santosh Mukerji and Trimcos, LLC v. Aquatic Solutions of Texas (Santosh Mukerji and Trimcos, LLC v. Aquatic Solutions of Texas) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.