Santana Row Hotel Partners, L.P. v. Zurich America Insurance

446 F. Supp. 2d 1108, 2006 U.S. Dist. LEXIS 9007, 2006 WL 449129
CourtDistrict Court, N.D. California
DecidedFebruary 22, 2006
DocketC 05-00198 JW
StatusPublished
Cited by2 cases

This text of 446 F. Supp. 2d 1108 (Santana Row Hotel Partners, L.P. v. Zurich America Insurance) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Santana Row Hotel Partners, L.P. v. Zurich America Insurance, 446 F. Supp. 2d 1108, 2006 U.S. Dist. LEXIS 9007, 2006 WL 449129 (N.D. Cal. 2006).

Opinion

ORDER DENYING ZURICH’S MOTION TO DISMISS

JAMES WARE, District Judge.

I. INTRODUCTION

Plaintiff Santana Row Hotel Partners, L.P. (“Plaintiff’) brings this suit against Defendants Zurich American Insurance Company (“Zurich”), Gallagher-Pipino, Inc. (“Gallagher”), and Arthur J. Gallagher & Co. (collectively “Defendants”) alleging breach of contract and fraud. Plaintiff alleges that Zurich failed to pay losses resulting from a fire which were covered by an insurance policy. Zurich has filed a Motion to Dismiss the First Amended Complaint, which contains six claims for relief. The Motion is noticed for hearing on February 27, 2006. The Court finds it appropriate to take the motion under submission for decision without oral argument pursuant to Civil Local Rule 7 — 1(b). Based on the papers submitted by the parties, the Court DENIES Zurich’s Motion to Dismiss.

II. BACKGROUND

A. Factual Background

In May 2000 Zurich issued a builders risk insurance policy (“Policy”) to Federal Realty Investment Trust (“FRIT”), covering certain losses associated with FRIT’s construction and development of a retail and residential community in San Jose known as Santana Row. (Zurich’s Notice of Motion and Motion to Dismiss (“Mot.”), Docket Item No. 69, at 1:4-7.) At the time Zurich issued the Policy, Plaintiff was leasing from FRIT the upper floors of a Santana Row building to build and operate a hotel. Zurich subsequently added Plaintiff as an Additional Insured under the Policy, although the date on which this occurred is in dispute. On August 19, 2002 there was a fire at the Santana Row development which caused massive damage and significant delays in the hotel’s scheduled opening. (First Amended Complaint (“FAC”), Docket Item No. 58, ¶ 11.)

On August 29, 2002, ten days after the fire, and January 8, 2003 Defendants issued two Certificates of Insurance (“Certificates”) which Plaintiff alleges are evidence that it was insured at the time of the fire. (FAC ¶ 10.) The Certificates, entitled “Evidence of Property Insurance,” state at the top: “THIS IS EVIDENCE THAT INSURANCE AS IDENTIFIED BELOW HAS BEEN ISSUED, IS IN FORCE, AND CONVEYS ALL THE RIGHTS AND PRIVILEGES AFFORD *1110 ED UNDER THE POLICY.” (FAC, Exhibits A & B.) The effective date of the Policy on the Certificates is May 15, 2000, preceding the fire by two years. Both forms list Gallagher-Pipino as the producer of the document and Zurich as the insurance company. The Certificates identify FRIT as the insured and show that the Hotel Valencia at Santana Row is covered by the Policy under the “Property Information” section. The Certificates further specify the amount of insurance for each type of coverage, as well as the deductibles required by the Policy, and state under the section for special conditions that the Policy does cover, to some degree, delay in completion damages. Both Certificates list Plaintiff as an Additional Insured, but the second Certificate specifically indicates that Plaintiff was added as an additional interest on July 15, 2001. (FAC, Exhibit B.)

In addition, the Certificates contain language near the bottom of the forms which require that upon termination of the Policy, Zurich would give 90 days written notice to the Additional Interest identified in the Certificate and send notification of any changes to the Policy that would affect that interest. (FAC, Exhibits A & B.) When Plaintiff claimed its losses under the Policy after the fire, the parties negotiated for approximately two years before Zurich made a partial payment of $713,839 in September 2004. (FAC ¶ 13.) Approximately three months after this partial payment, Zurich formally denied Plaintiffs claims under the Policy. (FAC ¶ 15.)

Plaintiff alleges its losses are covered by the Policy since Zurich added Plaintiff as an insured on July 15, 2001. (Plaintiffs Memorandum of Points and Authorities in Opposition to Defendant’s Motion to Dismiss (Opp’n), Docket Item No. 80, at 7:26-28; see FAC ¶ 9 (although the FAC does not specify the date on which Defendant allegedly insured Plaintiff, Plaintiff clearly states that this occurred before the fire).) Plaintiffs losses include without limitation property damage, rental income loss, extended general conditions, and soft costs in excess of $10 million. (FAC ¶ 11.)

B. Procedural Background

Plaintiff filed the original Complaint on January 12, 2005. The first and second claims for relief allege breach of contract against Zurich. In the first claim, Plaintiff alleges that Zurich’s failure to pay covered losses proximately caused Plaintiffs damages in excess of $10 million. (Complaint for Damages (“Compl.”), Docket Item No. 1, ¶¶ 18-19.) Plaintiffs second claim for tortious and bad faith breach of contract is based on allegations that Zurich unreasonably delayed payment, failed to effectuate prompt and equitable payment of Plaintiffs claims, and denied its obligation to pay despite representations to Plaintiff that its losses were covered by the Policy. (ComplJ 21.) In addition to actual damages (Comply 22), Plaintiff seeks punitive damages because of Zurich’s allegedly conscious disregard of Plaintiffs rights and fraud committed with regard to the Policy (Comply 24).

The third claim in the original Complaint for breach of third party beneficiary contract alleges that, in March 2001, FRIT and Defendants entered into a written contract by which Gallagher would procure an insurance policy from Zurich for Plaintiff. (ComplY 27.) Plaintiff alleges the contract was expressly made for its benefit, to provide insurance coverage for a variety of hazards associated with construction and also against delay in completion damages. (Compl.f 28.) Defendants allegedly breached the contract in failing to obtain Plaintiff insurance and Plaintiff suffered damage as a result. (Complin 30-31.)

*1111 The fourth claim in the original Complaint alleges fraud with regard to the Certificates issued by Defendants. Following the fire, Defendants issued the Certificates on August 29, 2002 and January 8, 2003 to confirm to Plaintiff that the Policy covered its losses. (Compl. ¶¶ 34 & 37.) Plaintiff alleges Defendants issued both Certificates, purporting to show that the Policy covered Plaintiff, with an intent to conceal Plaintiffs lack of coverage and to deceive Plaintiff into believing it was insured for losses resulting from the fire. (Compl. ¶¶ 34-35 & 37-38.)

Zurich moved to dismiss the entire original Complaint. In an Order dated May 25, 2005, the Court summarily denied Zurich’s Motion to Dismiss without prejudice, explaining that the Court preferred to have the parties proceed with cross-motions for partial summary judgment on the issue of insurance coverage. (Order Denying Zurich’s Motion to Dismiss and Scheduling Hearing Date Regarding Motions for Partial Summary Judgment on the Issue of Insurance Coverage (“Dismissal Order”), Docket Item No. 31, at 1:20-22) Although the Dismissal Order did not explicitly so indicate, the Court directed parties to file motions for partial summary judgment because it recognized that the issue of insurance coverage was factually complex. On November 16, 2005, Plaintiff sought and obtained leave to file the FAC.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
446 F. Supp. 2d 1108, 2006 U.S. Dist. LEXIS 9007, 2006 WL 449129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/santana-row-hotel-partners-lp-v-zurich-america-insurance-cand-2006.