Santa Maria Del Oro Mines Co. v. International Mining Corp.

20 F. Supp. 316, 1937 U.S. Dist. LEXIS 1609
CourtDistrict Court, D. Delaware
DecidedJune 18, 1937
DocketNo. 1122
StatusPublished
Cited by1 cases

This text of 20 F. Supp. 316 (Santa Maria Del Oro Mines Co. v. International Mining Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Santa Maria Del Oro Mines Co. v. International Mining Corp., 20 F. Supp. 316, 1937 U.S. Dist. LEXIS 1609 (D. Del. 1937).

Opinion

NIELDS, District Judge.

This is a suit in equity either to enforce or to rescind certain contracts. The contracts call upon defendant to furnish money, labor, and engineering skill to develop old Mexican gold mines belonging to plaintiff.

In the bill of complaint filed July 30, 1935, by Santa Maria Del Oro Mines Company, plaintiff (hereinafter called “Santa Maria”), against the defendant International Mining Corporation (hereinafter called “International”), plaintiff alleges in substance: For more than twenty years it had been the owner of certain gold mines located in the state of Durango, Republic of Mexico. It had expended large sums of money upon their development and maintenance but had never extracted any gold. Since 1918 “Cocinera,” the principal mine, had been flooded with water. By three contracts, to wit, (1) the contract made August 28, 1933, between plaintiff and defendant (hereinafter called the “First Contract”), (2) a contract dated July 27, 1934 (hereinafter called the “Mexican Contract”), between defendant and Compañía Minera Santa Maria del Oro, S. A., a Mexican corporation (hereinafter called “Mexican”), and (3) a contract between plaintiff and defendant made November 13, 1934 (hereinafter called the “Second Contract”), defendant undertook to advance such sums as in its judgment were “reasonably necessary for the proper exploration and development of the mines and properties of Santa Maria, and for the purchase and installation of an adequate mill and other equipment for production operations and for working capital in connection therewith; provided, however, that the maximum which International was obligated to advance to Santa Maria, pursuant to the terms of the said contract was riot to exceed the sum of $500,000,” subject also to the right of defendant to cease making advances at any time at its election. By said contracts plaintiff and defendant became associated as joint adventurers in the enterprise of placing upon a commercially productive basis said mines. By said contracts defendant was bound to purchase and install an adequate mill and other equipment for production, if and when the entire sum of $500,000 was advanced under said contracts. In said contracts plaintiff granted to defendant an option to acquire 60 per cent, of its common stock to be delivered when and if defendant advanced the sum of $500,000. Defendant also became bound to purchase and install an adequate mill for production if and when it exercised said option. Defendant advanced part of the $500,000 to plaintiff before July 12, 1934, when Mexican was organized and thereafter advanced the balance to Mexican. The bill further alleges that defendant violated its fiduciary duty and its obligation under the contracts to build and equip an adequate mill and that it failed to set aside a sufficient sum therefor out of the $500,000, but spent $325,000 thereof for improper, unnecessary, speculative and reckless development. And, that defendant caused Mexican to borrow additional moneys in violation of plaintiff’s rights. The bill prays for an accottnting and for the specific performance of the contracts. However, there is one prayer for rescission of the contracts predicated upon the theory of a failure of consideration.

By answer filed September 7, 1935, defendant denies that it ever assumed any [318]*318fiduciary relationship towards plaintiff. ■Defendant avers that the full measure of its obligation is set forth in article 7 of the First Contract reading:

“7. International shall exercise full control and direction of all mining and milling operations in the said mining properties (except that the treatment of ore on the stock piles at the mine shall not be undertaken by International without the express approval in writing of Santa Maria) and over all expenditures in connection therewith, through such engineers as it may have designated for appointment by Santa Maria •for such direction, control and supervision, provided, however, that one consulting mining engineer may be selected and appointed by Santa Maria to act with such engineer or engineers as are designated by International for appointment by Santa Maria (such consulting engineer- designated by Santa Maria may be paid by Santa Maria from funds advanced by International) . * * * ”

Defendant aVers that it has fully and fairly performed every obligation imposed upon it with respect to the furnishing and spending of 'the said $500,000, and that the uses and purposes for which said $500,-000 were spent were uses and purposes provided for in the contract and that said expenditures were shown on weekly progress reports and their accompanying financial statements, which were regularly sent from week to week to plaintiff.

Upon the issues thus framed by the bill and answer hearings were held between November 25, 1935, and January 23, 1936. Briefs and requests for findings of fact and conclusions of law were duly filed by May, 1936.

June 4, 1936, and before final argument defendant filed a motion for leave to introduce additional testimony. June 17 and July 6, 1936, further hearings were held. The issues before the court at these hearings were subsequently framed by an amendment to the bill of complaint and the answer thereto. The amendment charges-:

“Fiftieth: For some years prior to August 28, 1933, one George A. Schroter, who is by profession a Consulting Mining Engineer was in the employ of the plaintiff company as its Consulting Engineer and was as well its confidential agent entrusted with the authority and responsibility of negotiating for the sale or operation of the property herein involved. ■ The said George A. Schroter on behalf of the plaintiff as its agent carried on the negotiations with the defendant company mentioned in paragraph Fifth, which resulted in the contract ‘Exhibit 1’ [of August 28, 1933] attached to this bill. Prior to August 28, 1933 plaintiff through its President, Grant Curry, had agreed with the said George A. Schroter that for his services in effecting an arrangement similar to that entered into between plaintiff and defendant, that said George A. Schroter would receive as his compensation, ten per cent (10%) of the proceeds of said transaction, as received by plaintiff. Pursuant to said agreement the plaintiff company has delivered to said George A. Schroter 62,400 shares of the common capital stock of the Mexican corporation. herein mentioned. Unknown to the plaintiff company and without its consent and in violation of its fiduciary obligation to the plaintiff company, the defendant company at, or about, [August 28, 1933] the date of the contract ‘Exhibit 1’ hereto entered into a secret arrangement with the said George A. Schroter by which it agreed to pay to the said George A. Schroter 2% of the Common stock as received by it as a result of the transaction between plaintiff and defendant. Said arrangement was confirmed by a resolution of the Board of Directors of the defendant company on June 12, 1935, a true and correct copy of the minutes of said corporation on said subject being here'to attached and marked ‘Exhibit 5’. The defendant was fully aware that said Schroter was the confidential agent of the plaintiff company and that the plaintiff company was relying upon the said Schroter for his unprejudiced and unbiased judgment in the negotiations above referred to, and as well for the unbiased and unprejudiced advice of the said Schroter in the matters provided for in the contract between the parties. Plaintiff avers that the act of the defendant in paying or promising to pay the said Schroter a secret commission has deprived the plaintiff of .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reed v. Consolidated Feldspar Corp.
23 N.W.2d 154 (South Dakota Supreme Court, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
20 F. Supp. 316, 1937 U.S. Dist. LEXIS 1609, Counsel Stack Legal Research, https://law.counselstack.com/opinion/santa-maria-del-oro-mines-co-v-international-mining-corp-ded-1937.