Santa Fe Snyder Corp v. Babbitt

385 F.3d 884, 59 Fed. R. Serv. 3d 932, 161 Oil & Gas Rep. 789, 2004 U.S. App. LEXIS 20682, 2004 WL 2092647
CourtCourt of Appeals for the Fifth Circuit
DecidedOctober 4, 2004
Docket03-30648
StatusPublished
Cited by15 cases

This text of 385 F.3d 884 (Santa Fe Snyder Corp v. Babbitt) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Santa Fe Snyder Corp v. Babbitt, 385 F.3d 884, 59 Fed. R. Serv. 3d 932, 161 Oil & Gas Rep. 789, 2004 U.S. App. LEXIS 20682, 2004 WL 2092647 (5th Cir. 2004).

Opinion

W. EUGENE DAVIS, Circuit Judge:

The plaintiffs, who .are lessees (the “Lessees”) under offshore federal lease OCS-G 18192, assert that the United States Department of the Interior (“Interior”), Minerals Management Service *886 (“MMS”), regulations implementing the Deep Water Royalty Relief Act of 1995 (“RRA”) conflict with the act itself and are unlawful. The Lessees also challenge the Interior’s final agency decision denying the Lessees royalty relief under the RRA for their lease OCS-G 18192. The district court ruled in favor of the Lessees on the parties’ cross-motions for summary judgment. We affirm.

I.

As stated above, the Lessees brought this action facially challenging both the regulations promulgated by the Interior pursuant to the RRA and the Interior’s order denying royalty relief to the Lessees. Cross motions for summary judgment were filed. The Lessees’ motion sought a declaration that the Interior’s regulations at 30 C.F.R. §§ 260.112— 260.117 violated the RRA and that OCS-G 18192 (the “Lease”) is automatically entitled to royalty relief as set forth in the RRA. The Interior simply requested judgment in favor of itself.

On January 8, 2003, the district court entered judgment in favor of the Lessees. However, this judgment was issued two days before the Interior’s deadline to file its reply brief. On January 23, 2003 (within 10 business days of the issuance of the January 8 Judgment), the Interior timely filed a Motion to Amend the Judgment and Memorandum in Support Thereof. The motion was based on the fact that the district court had entered a decision without the benefit of the Interior’s reply brief and set forth the arguments that would have been made in the reply brief.

On March 14, 2003, the district court denied the January 23 Motion, and stated “the Memorandum Ruling and Judgment issued on January 8, 2003 will remain in effect as issued for the reasons previously stated.” The Lessees contend that the Interior’s 60-day appeal period began to run from this ruling and the Interior had until May 13, 2003 to file a notice of appeal.

On March 28, 2003, the Interior filed a Motion for Reconsideration of the Reformation Remedy and for Presentation of Additional Evidence Pertaining Thereto. The Interior stated that the motion was brought under Fed.R.Civ. P. 59(e). Interi- or argued in this motion that the January 8 Judgment’s declaration that the Lease was entitled to suspension of royalties resulted in a reformation of the Lease. This motion was filed within 10 business days from the entry of the March 14, 2003 Ruling on the Motion to Amend the Judgment, but more than 60 days after the entry of the January 8 Judgment.

On April 28, 2003, the district court denied the Interior’s March 28, 2003 Motion. It treated the motion as a second Rule 59(e) motion and denied it on the basis that it was untimely because it was filed more than 10 days after the entry of the January 8 Judgment and because it raised issues that the Interior could have raised but did not raise before the entry of summary judgment on January 8.

In a motion transmitted on April 28, 2003 and filed on April 29, 2003, the Interior asked the district court to vacate the January 8 Judgment and issue an order recognizing the March 14 Order as the date of initial judgment in the case. The motion noted that, without the requested order, the docket sheet could be read so that March 14, 2003 would mark the date of final judgment so that the Interior would be required to file a Notice of Appeal by May 13, 2003. At the time of filing this motion the Interior was not aware that the district court had already ruled on its March 28, 2003 Motion and was concerned that if it was forced to file a notice *887 of appeal, the district court would no longer have jurisdiction over the case to rule on that motion. The purpose of its April 29 motion was to put the Interior in the position it would have been in had the district court not ruled prematurely on the Motion for Summary Judgment.

On May.l, 2003, the district court granted the Interior’s April 29 Motion. The district court noted the confusion that was created by. its premature entry of judgment and treated the January 23, 2003 Motion as a Reply Brief (not a Rule 59(e) Motion), declared the March 14, 2003 judgment as final judgment, and the March 28 Motion as a timely Rule 59(e) motion. The March 28 Motion was denied, not for untimeliness, but because it raised new issues. Interior appeals.

II.

The Lessees argue first that Interi- or’s appeal is untimely and that we have no jurisdiction over this appeal. Lessees contend that the only post-judgment motion that extended the time for appeal was Interior’s January 23 Motion for Reconsideration under Rule 59(e). Lessees argue that the Interior’s time for appeal began to run from March 14, 2003 — -the date the court denied Interior’s January 23 Motion. Under Lessee’s analysis of the docket sheet, Interior’s notice of appeal was required to be filed no later than May 13, 2003 (60 days after the court’s March. 14 denial of Interior’s January 23 Motion). Thus Lessees argue that the notice of appeal filed on June 26 was untimely.

Although this argument has some technical appeal, it rests entirely on the premise that the district court was without authority to correct its docket sheet as it did in its May 1 Ruling. The Interior argues that the district court has the authority under Rule 60(b) to vacate its own judgment for reasons stated in the rule and correct its own docket. We agree. Under Rule 60(b)(1), “the court may relieve a party or a party’s legal representative from a final judgment, order, or proceeding for the following reasons; (1) mistake, inadvertence, surprise, or excusable neglect.” Fed.R.Civ. P. 60(b)(1). The “mistake” referred to in the rule can apply to the court’s own error.' Oliver v. Home Indem. Co., 470 F.2d 329, 330 (5th Cir.1972). The district court’s May 1 Memorandum Ruling was clearly directed to correct the court’s own “administrative error” in ruling prematurely on January 8th, creating “some confusion as to how to interpret the procedural history that has oc: curred in this case after that date.”

According to Moore’s Federal Practice, “the district court undoubtedly has the power to vacate a judgment in appropriate circumstances and rehear the case, and the judgment entered after rehearing is appealable in due course, although it may be in substance the same as the first.” Moore’s Federal Practice 3D, § 304.14[5]. The ruling on rehearing will delay the time for taking an appeal if the reason for the ruling goes to the propriety of the initial judgment and is not entered simply to give the parties a second chance to file a timely notice of appeal. Id. Although the district court did not explicitly vacate the premature January 8th ruling, it effectively did so by granting the Interior’s motion and ordering that March 14, 2003 “shall be deemed to be the date on which summary judgment was granted in favor of the Plaintiffs.” The district court’s May 1 Ruling did address.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

W & T Offshore, Incorporated v. David Bernhardt, e
946 F.3d 227 (Fifth Circuit, 2019)
Hedlund v. Ryan
854 F.3d 557 (Ninth Circuit, 2016)
United States v. Rolando Fernandez
797 F.3d 315 (Fifth Circuit, 2015)
Alford v. Chevron U.S.A. Inc.
13 F. Supp. 3d 581 (E.D. Louisiana, 2014)
Total E & P USA, Inc. v. Kerr-McGee Oil & Gas Corp.
719 F.3d 424 (Fifth Circuit, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
385 F.3d 884, 59 Fed. R. Serv. 3d 932, 161 Oil & Gas Rep. 789, 2004 U.S. App. LEXIS 20682, 2004 WL 2092647, Counsel Stack Legal Research, https://law.counselstack.com/opinion/santa-fe-snyder-corp-v-babbitt-ca5-2004.