Sanitary & Improvement District No. 304 v. International Fidelity Insurance Company

CourtDistrict Court, D. Nebraska
DecidedNovember 19, 2021
Docket8:21-cv-00260
StatusUnknown

This text of Sanitary & Improvement District No. 304 v. International Fidelity Insurance Company (Sanitary & Improvement District No. 304 v. International Fidelity Insurance Company) is published on Counsel Stack Legal Research, covering District Court, D. Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sanitary & Improvement District No. 304 v. International Fidelity Insurance Company, (D. Neb. 2021).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEBRASKA

SANITARY & IMPROVEMENT DISTRICT NO. 304, Sarpy County, Nebraska;

8:21-CV-260 Plaintiff,

vs. MEMORANDUM AND ORDER

INTERNATIONAL FIDELITY INSURANCE COMPANY;

Defendant.

I. INTRODUCTION Sanitary and Improvement District No. 304, Sarpy County, Nebraska (“SID 304”) has sued International Fidelity Insurance Company (“IFIC”) for breach of contract.1 Before the Court is SID 304’s Motion for Default Judgment. Filing 8. For the reasons stated herein, the Court denies SID 304’s motion without prejudice to reassertion. II. BACKGROUND SID 304 is a political subdivision in Sarpy County, Nebraska. Filing 1 at 1. On October 17, 2017, SID 304 contracted with nonparty TLC Construction, LLC,2 to construct a sanitary sewer and storm sewer. Filing 1 at 2. The agreement provided that TLC Construction would complete

1 While SID 304’s Complaint states “Breach of Contract” as its cause of action, Filing 1 at 6, its current motion states that it sued IFIC for “Breach of Implied Contract and Unjust Enrichment.” Filing 8 at 1. 2 TLC Construction, LLC, has filed for bankruptcy. Filing 1 at 1. the project by May 7, 2018, and stated that time was of the essence. Filing 1 at 2; Filing 9-3 at 11. If TLC Construction failed to complete construction by May 7, 2018, the agreement allowed for liquidated damages of $500 per calendar day to be assessed against TLC Construction until it substantially completed the work. Filing 1 at 2; Filing 9-3 at 11–12. The agreement required TLC Construction to provide a performance bond. Filing 1 at 2;

Filing 1 at 2; Filing 9-3 at 20–22. On October 3, 2017, TLC Construction provided a performance bond for the construction project, which listed it as principal, defendant IFIC as surety, and SID 304 as owner. Filing 1 at 2–3; Filing 9-3 at 20. The bond stated that IFIC and TLC Construction would be jointly and severally liable for the penal sum of $1,012,369.88, and that TLC Construction would “faithfully perform all of [its] obligations regarding and pertaining to [the] construction work.” Filing 9-3 at 20. On October 18, 2017, SID 304’s engineer notified TLC Construction to begin work on the project within five business days. Filing 1 at 3; Filing 9-3 at 31. TLC Construction began construction, but unilaterally ceased performance for unknown reasons. Filing 1 at 3. SID 304’s

engineer contacted TLC Construction requesting them to return to the project and resume construction work. Filing 1 at 3–4; Filing 9-3 at 32. TLC Construction did not complete any construction work in 2018. Filing 1 at 4. On May 7, 2018, SID 304’s engineer notified TLC Construction that the time required to complete the project had expired and that SID 304 had begun assessing liquidated damages against TLC Construction. Filing 1 at 4; Filing 9-3 at 33. SID 304’s engineer sent another letter to TLC Construction on May 24, 2018, telling it that there was approximately $600,000.00 of work remaining, that the work would take sixty days to complete, and that TLC Construction’s rate of progress was unacceptable. Filing 1 at 4 Filing 9-3 at 34. The letter further stated that if TLC Construction did not provide an explanation for how it was going to dramatically increase its productivity, SID 304 would have to engage another contractor to complete the work. Filing 1 at 4; Filing 9-3 at 34. On November 2, 2018, SID 304’s engineer recommended that it terminate the contract with TLC Construction due to its failure to perform the construction work on the project. Filing 1 at 5; Filing 9-3 at 36.

SID 304 engaged L.G. Roloff Construction Company, Incorporated, to complete the work on the project. Filing 1 at 5. SID 304 claims that it incurred damages of $251,741.70.3 Filing 8 at 2. It calculates its damages by stating the original contract price was $912,032.34 and it paid TLC Construction $712,729.10, leaving $200,303.24 on the original contract price. Filing 1 at 5. SID 304 further alleges it incurred costs and liquidated damages totaling $452,044.94 which, less the $200,303.24 remaining on the original contract price, results in the total damages amount of $251,141.70. Filing 1 at 5. Pursuant to the performance bond, SID 304 presented a claim to IFIC for its damages. Filing 1 at 6. IFIC denied that claim. Filing 1 at 6. On July 12, 2021, SID 304 sued IFIC for breach of contract. Filing 1. On July 13, 2021,

the Court issued summons for IFIC, which was delivered on July 19, 2021. Filing 4; Filing 5 at 3– 4. IFIC did not file a response. SID 304 then filed a Motion for Clerk’s Entry of Default against IFIC on September 16, 2021, which the Clerk entered on September 20, 2021. Filing 6; Filing 7. Later that day, SID 304 filed its Motion for Default Judgment against IFIC. Filing 8.

3 While SID 304 claims this amount in its Motion for Default Judgment, its Complaint lists both this amount ($251,741.70) and $251,171.40 as its total damages. Compare Filing 1 at 5 (“SID 304 has suffered damages in the amount of $251,171.40 . . . .”), with Filing 1 at 7 (“IFIC is liable to pay SID 304 $251,741.70 . . . .”). As set forth below, because SID 304 fails to support its damages calculation with any evidence, it is impossible for the Court to determine if these differences represent a typographical error and if so, which is the correct amount. III. ANALYSIS A. Standard of Review Entering default judgment is governed by Federal Rule of Civil Procedure 55. See Fed. R. Civ. P. 55. “When a party ‘has failed to plead or otherwise defend’ against a pleading listed in [Federal Rule of Civil Procedure] 7(a), entry of default under Rule 55(a) must precede grant of a

default judgment under Rule 55(b).” Johnson v. Dayton Elec. Mfg. Co., 140 F.3d 781, 783 (8th Cir. 1998) (quoting Fed. R. Civ. P. 55(a)). It is “appropriate for a district court to enter a default judgment when a party fails to appropriately respond in a timely manner.” Marshall v. Baggett, 616 F.3d 849, 852 (8th Cir. 2010) (citing Inman v. Am. Home Furniture Placement, Inc., 120 F.3d 117, 119 (8th Cir. 1997)). “Upon default, the factual allegations of a complaint (except those relating to the amount of damages) are taken as true.” Murray v. Lene, 595 F.3d 868, 871 (8th Cir. 2010); see also Fed. R. Civ. P. 8(b)(6) (“An allegation—other than one relating to the amount of damages—is admitted if a responsive pleading is required and the allegation is not denied.”). “[I]t is incumbent upon the district court

to ensure that ‘the unchallenged facts constitute a legitimate cause of action’ prior to entering final judgment.” Marshall, 616 F.3d at 852-53 (quoting Murray, 595 F.3d at 871). B. SID 304 Has Stated a Legitimate Cause of Action IFIC failed to respond or otherwise defend against SID 304’s suit within 21 days after receiving service on July 19, 2021 as required by Federal Rule of Procedure 12(a)(1)(A)(i). Therefore, the Court turns to whether the unchallenged facts in this case give rise to a legitimate cause of action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pope v. United States
323 U.S. 1 (Supreme Court, 1944)
Marshall v. Baggett
616 F.3d 849 (Eighth Circuit, 2010)
Murray v. Lene
595 F.3d 868 (Eighth Circuit, 2010)
Berens & Tate v. Iron Mt. Info. Mgmt.
747 N.W.2d 383 (Nebraska Supreme Court, 2008)
Abel Construction Co. v. School District of Seward
195 N.W.2d 744 (Nebraska Supreme Court, 1972)
Parsons Construction Co. v. Metropolitan Utilities District
104 N.W.2d 272 (Nebraska Supreme Court, 1960)
Henriksen v. Gleason
643 N.W.2d 652 (Nebraska Supreme Court, 2002)
Kozlik v. Emelco, Inc.
483 N.W.2d 114 (Nebraska Supreme Court, 1992)
Johnson v. Dayton Electric Manufacturing Co.
140 F.3d 781 (Eighth Circuit, 1998)
Growney v. C M H Real Estate Co.
238 N.W.2d 240 (Nebraska Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
Sanitary & Improvement District No. 304 v. International Fidelity Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sanitary-improvement-district-no-304-v-international-fidelity-insurance-ned-2021.