Sands v. Kambouris Contruction

CourtDistrict Court, M.D. Pennsylvania
DecidedDecember 31, 2021
Docket3:18-cv-02426
StatusUnknown

This text of Sands v. Kambouris Contruction (Sands v. Kambouris Contruction) is published on Counsel Stack Legal Research, covering District Court, M.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sands v. Kambouris Contruction, (M.D. Pa. 2021).

Opinion

UNITED STATES DISTRICT COURT MIDDLE DISTRICT OF PENNSYLVANIA WILLIAM J SANDS,

Plaintiff, CIVIL ACTION NO. 3:18-CV-02426

v. (MEHALCHICK, M.J.) KAMBOURIS CONSTRUCTION, et al.,

Defendants.

MEMORANDUM Plaintiff William J. Sands (“Sands” or “Plaintiff”) initiated this action on November 2, 2018, in the Court of Common Pleas of Carbon County. (Doc. 1-1, at 5). In his complaint, Sands alleges that Defendants Kambouris Construction and Hristos Kambouris (“Kambouris” or “Defendants”) breached a construction contract between the parties when Kambouris failed to adhere to the agreed upon terms of the contract. (Doc. 1-1, at 8-11). Kambouris filed a notice of removal on December 21, 2018, removing the case to the United States District Court for the Middle District of Pennsylvania. (Doc. 1). Defendants filed their answer, affirmative defenses, and counterclaim against Sands on January 27, 2018. (Doc. 2). Kambouris contends that Sands breached a construction contract between the parties when he failed to tender the total amount of compensation to Kambouris. (Doc. 2, at 20). Sands filed an answer to Kambouris’s counterclaim on January 20, 2019. (Doc. 5). The parties consented to proceed before a United States Magistrate Judge on February 14, 2019. (Doc. 11). A non-jury trial was conducted before Chief Magistrate Judge Karoline Mehalchick on April 12, 2021, and April 20, 2021. (Doc. 40); (Doc. 43). Both parties were represented by counsel at trial, and both parties filed proposed findings of fact and conclusion of law following trial. (Doc. 48); (Doc. 49). Based on these submissions, the Court has distilled four issues requiring resolution; namely: (1) whether Kambouris or Sands breached the contract created between the two parties; (2) whether Kambouris or Sands were subjected to unjust

enrichment; (3) whether Kambouris violated the Pennsylvania Home Improvement Consumer Protection Act, 73 P.S. 517.1 (“HICPA”); and (4) whether Sands is entitled to recovery under Pennsylvania’s Unfair Trade Practices and Consumer Protection Law, 73 P.S. 201-1 (“UTPCPL”). The Court, having heard the testimony and reviewed all documentary evidence, now enters the following Findings of Fact, Conclusions of Law, and Decision pursuant to Rule 52 of the Federal Rules of Civil Procedure. Fed. R. Civ. P. 52. FINDINGS OF FACT The following findings of fact are based upon the stipulations of the parties, as well as

the testimony and evidence that the Court found credible as presented at trial. 1. The Plaintiff and Counterclaim - Defendant is William J. Sands, a resident of Plantation, Florida. Sands also owns a home in Albrightsville, Pennsylvania (the “Property”). (Doc. 2, at 1, 18; Doc. 45, at 4, Tr. of Trial, 4:11-15, April 12, 2021). 2. The Defendants and Counterclaim – Plaintiffs are Hristos Kambouris and Kambouris Construction. (Doc. 2, at 1, 18). 3. Hristos Kambouris is a general contractor licensed in Pennsylvania who trades and does business under the name Kambouris Construction. (Doc. 45, at 5, 100, Tr. of Trial, 5:8-14, 100:11-12, April 12, 2021).

2 4. Sands bought the Property with the intent to perform renovations. (Doc. 45, at 5, Tr. of Trial, 5:3-5, April 12, 2021). 5. Sands’s brother, Tom (“Tom”), introduced Sands and Kambouris with the intent that Kambouris could perform construction work on the Property. (Doc. 45, at 5, Tr. of

Trial, 5:15-20, April 12, 2021). 6. The two spoke in person around Thanksgiving of 2017 about the work Sands wanted done on the Property. (Doc. 45, at 5-6, 103, Tr. of Trial, 5-6:21-8, 103:16-23, April 12, 2021). 7. Kambouris did not take notes during his first conversation with Sands. (Doc. 45, at 202, Tr. of Trial, 202:1-4, April 12, 2021). 8. Sands hired Kambouris to perform work at the Property. (Doc. 45, at 5, Tr. of Trial, 5:6-11, April 12, 2021). 9. Kambouris started the project in January 2018 without a written contract because of his positive relationship with Tom. (Doc. 45, at 10, 113, Tr. of Trial, 10:19-23, 113:7-

17, April 12, 2021). 10. The project originally was going to cost $60,000.00 and was intended to be completed before Sands’s mother’s birthday party which was in July 2018. (Doc. 45, at 8, 104-05, Tr. of Trial, 8:1-10, 104:21-25, 105:1, April 12, 2021). 11. In the initial meeting, the two discussed the addition of a bathroom and a closet in the master bedroom, renovations to the kitchen cabinets, an addition, and some electrical work. (Doc. 45, at 6, 104, Tr. of Trial, 6:11-15, 104:14-17, April 12, 2021).

3 12. On December 26, 2017, Kambouris, Sands, and Tom met to discuss expanding the scope of the project including the addition of hardwood flooring. (Doc. 45, at 106, Tr. of Trial, 106:10-16, April 12, 2021). 13. Kambouris informed Sands that the project would now cost $100,000.00 and would

be difficult to complete by the original agreed upon date. (Doc. 45, at 107-08, Tr. of Trial, 107:17-25, 108:1-8, April 12, 2021). 14. Kambouris began work on the project in January 2018 and was given $5,000.00 in cash by Tom to begin work. (Doc. 45, at 10, 108, 111 Tr. of Trial, 10:21-23, 108:9-11, 111:12-14, April 12, 2021). 15. Tom monitored the progress throughout the project because he lived in Pennsylvania and Sands did not. (Doc. 45, at 109, Tr. of Trial, 109:6-8, April 12, 2021). 16. Upon starting the project, Kambouris discovered issues throughout the home, complicating the renovation and delaying the projected completion date. (Doc. 45, at 112, 114, 116-117, Tr. of Trial, 112:1-24, 114:12-19, 116:24-25, 117:1-17, April 12,

2021). 17. Kambouris discovered rot throughout the house. (Doc. 45, at 112, Tr. of Trial, 112:1- 24, April 12, 2021; Defendants Ex. 7-9). 18. Kambouris discovered that the tile in the master bedroom had been installed incorrectly and was difficult to remove. (Doc. 45, at 114, Tr. of Trial, 114: 12-19, April 12, 2021; Defendants Ex. 4-6). 19. Kambouris discovered that there was a variance in the levels of the floors in the bedroom and the rest of the house, which required additional work to level the

4 flooring. (Doc. 45, at 116-117, Tr. of Trial, 116:24-25, 117:1-17, April 12, 2021; Defendants Ex. 10). 20. Sands requested that Kambouris prioritize certain projects, however Kambouris explained to Sands that he was unable to do so. (Doc. 45, at 97-98, Tr. of Trial, 97:18-

25, 98:1-13, April 12, 2021). 21. Kambouris only communicated with Sands through phone calls, whereas Kambouris communicated and updated Tom through text message. (Doc. 45, at 12, 109, Tr. of Trial, 12:5-7, 109:1-11, April 12, 2021; Defendants Ex. 16, 77, 79-80, 83-84B). 22. Sands visited the property three times over the course of Kambouris’s work on the project. (Doc. 46, at 38, Tr. of Trial, 38:7-8, April 20, 2021). 23. Kambouris believed that Tom, who was frequently at the property, was communicating the progress to Sands. (Doc. 45, at 109, Tr. of Trial, 109:12-14, April 12, 2021; Doc. 46, at 43, 44, Tr. of Trial, 43:14-25, 44:1-4, April 20, 2021). 24. Kambouris sent photos, videos, and updates to Tom regarding the renovations.

(Defenses Ex. 16; 77; 79). 25. Kambouris did not provide Sands with copies of invoices for all purchases for his work on the Property. (Doc. 46, at 42, Tr. of Trial, 42:8-25, April 20, 2021). 26. The project expanded to include construction on the roof, the deck, enlarging the kitchen to accommodate the cabinets, and a laundry room. (Doc. 45, at 109, Tr. of Trial, 109:15-25, April 12, 2021). 27.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hershey Foods Corporation v. Ralph Chapek, Inc.
828 F.2d 989 (Third Circuit, 1987)
Schwartz v. Rockey
932 A.2d 885 (Supreme Court of Pennsylvania, 2007)
Spang & Co. v. United States Steel Corp.
545 A.2d 861 (Supreme Court of Pennsylvania, 1988)
Drysdale v. Woerth
153 F. Supp. 2d 678 (E.D. Pennsylvania, 2001)
Giant Eagle Inc v. Commissioner IRS
822 F.3d 666 (Third Circuit, 2016)
Joan Longenecker-Wells v. Benecard Services Inc
658 F. App'x 659 (Third Circuit, 2016)
iRecycleNow.com v. Starr Indemnity & Liability Co.
674 F. App'x 161 (Third Circuit, 2017)
Johnson v. Fenestra, Inc.
305 F.2d 179 (Third Circuit, 1962)
Mifflinburg Telegraph, Inc. v. Criswell
277 F. Supp. 3d 750 (M.D. Pennsylvania, 2017)
TriState HVAC Equipment, LLP v. Big Belly Solar, Inc.
836 F. Supp. 2d 274 (E.D. Pennsylvania, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Sands v. Kambouris Contruction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sands-v-kambouris-contruction-pamd-2021.