Sands Aviation, LLC v. Ais-Int'l, Ltd. C/W 73522

CourtNevada Supreme Court
DecidedMarch 28, 2019
Docket73522
StatusUnpublished

This text of Sands Aviation, LLC v. Ais-Int'l, Ltd. C/W 73522 (Sands Aviation, LLC v. Ais-Int'l, Ltd. C/W 73522) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sands Aviation, LLC v. Ais-Int'l, Ltd. C/W 73522, (Neb. 2019).

Opinion

IN THE SUPREME COURT OF THE STATE OF NEVADA

SANDS AVIATION, LLC, A NEVADA No. 73522 LIMITED LIABILITY COMPANY; AND INTERFACE OPERATIONS BERMUDA LTD., A FOREIGN LIMITED COMPANY, FILED Appellants, MAR 28 20 19 vs. E.: A, MOWN MS-INTERNATIONAL, LTD., A Cli..11470F SUPREME COURT

FOREIGN LIMITED COMPANY, Respondent. SANDS AVIATION, LLC, A NEVADA No. 74114 LIMITED LIABILITY COMPANY; AND INTERFACE OPERATIONS BERMUDA LTD., A FOREIGN LIMITED COMPANY, Appellants, vs. AIS-INTERNATIONAL, LTD., A FOREIGN LIMITED COMPANY, Respondent.

ORDER AFFIRMING IN PART AND REVERSING IN PART

These are consolidated appeals from a final judgment and award of attorney fees and costs in a contract action Eighth Judicial District Court, Clark County; Joseph Hardy, Jr., Judge. Appellant Sands Aviation, LLC, entered into a contract with respondent MS International, Ltd. (AIS) to remodel an airplane owned by appellant Interface Operations Bermuda, Ltd. (lOB). The parties agreed that MS would provide its design and engineering services for a fixed fee of $6.9 million. The contract provided that Sands Aviation had the right to

SUPREME Coon OF NEVADA

(0) 1947T e lq-1332 Id terminate the contract at any time and for any reason, including no reason at all. If Sands Aviation elected to terminate the contract, AIS had to submit a written request for incurred costs for [s]ervices performed through the date of termination." Sands Aviation was required to pay the nvoice within 30 days. The contract also provided a reconciliation and settlement process in case the parties disputed the amount owed. XIS agreed to complete the project in 12 months, though it estimated that a project of that scope typically required 38 months. However, three days before a major project deadline, and 10 weeks into the project, Sands Aviation terminated the contract. Approximately 14 days after the termination, AIS sent Sands Aviation its invoiceS charging 37.5 percent of the contract work. Sands Aviation did not respond to or reject the invoice. After waiting approximately three months and not receiving a payment, AIS sued Sands Aviation and JOB for breach of contract, breach of the implied covenant of good faith and fair dealing, unjust enrichment and quantum meruit, and a garagemen's lien. Following a four-day bench trial, the district court found in favor of XIS on its claims for breach of contract and breach of the implied covenant of good faith and fair dealing against Sands Aviation. As against JOB, the district court found in favor of AIS on the unjust enrichment claim. The court awarded AIS $891,250 in principal damages, plus attorney fees and costs, totaling $113,635.43, after deducting AIS's post-termination and travel costs, which it found were not owed under the contract. Sands Aviation appealed. The district court did not err in finding that Sands Aviation breached the contract and its allocation of damages is supported by substantial evidence Sands Aviation contends that the district court erred in finding that it breached the terms of the contract by failingS to respond to AIS's SUPREME COURT OF NEVADA 2 (0) 0147A et.

-taE7 invoice, arguing that its finding was essentially a rewriting of the contract by imposing on Sands Aviation a duty to respond to an incorrect invoice. Sands Aviation further challenges the district court's allocation of damages to AIS as a result of the breach of contract. We review a district court's interpretation of a contract de novo. Golden Rd. Motor Inn, Inc. v. Islam, 132 Nev. 476, 481, 376 P.3d 151, 155 (2016). "[W]hen a contract is clear, unambiguous, and complete, its terms must be given their plain meaning and the contract must be enforced as written; the court may not admit any other evidence of the parties' intent because the contract expresses their intent." Ringle v. Bruton, 120 Nev. 82, 93, 86 P.3d 1032, 1039 (2004). As a preliminary matter, we note that the contract contained a time-is-of-the-essence clause and it was a fully integrated agreement. A plain reading of the contract's termination and reconciliation provisions makes clear that, after receiving "a correct, adequately documented written request," Sands Aviation was required to pay the requested amount within 30 days. If the invoice was incorrect or not adequately documented, Sands Aviation could begin the reconciliation and settlement process to dispute the amount owed. Otherwise, the invoice became due after the 30 days. Reading these provisions together, we agree with the district court that Sands Aviation's failure to object or respond to AIS's invoice constituted a breach of the express terms of the contract. Once Sands Aviation elected to terminate the contract and AIS submitted its invoice, the 30-day deadline began. Sands Aviation sent AIS its termination letter on November 10, 2014. AIS sent its invoice and included a reconciliation report supporting the invoice two weeks later on November 24, 2014. AIS and Sands Aviation held a telephone conference

SUPREME COURT OF NEVADA 3 (0) 1947A ce• to discuss the invoice on December 8, 2014, but Sands Aviation did not reject or agree to the invoice at that time. AIS inquired about payment in January 2015 and offered to provide additional information to substantiate the invoice. Sands Aviation did not respond. After waiting three months for payment, AIS sued Sands Aviation and JOB to recover. Given the contract's specific deadlines and method for disputing the invoice, we conclude that Sands Aviation's failure to pay within the 30-day deadline, without any objection to the invoice amount, was a breach of the express terms of the contract. Having found that Sands Aviation breached the contract, the district court allocated damages to AIS based on its finding that AIS had completed a substantial amount of the contracted work. Sands Aviation argues that the district court's error on thefl breach of contract issue extended into its award of damages to AIS, and that MS failed to prove that its costs were "fair and equitable" under the contract. A district court's award of damages will be affirmed so long as it is supported by substantial evidence. Wyeth, v. Rowatt, 126 Nev. 446, 470, 244 P.3d 765, 782 (2010), and the district court's factual findings will be upheld unless those findings are clearly erroneous and unsupported by substantial evidence. Sowers v.

Forest Hills Subdivision, 129 Nev. 99, 105, 294 P.3d 427, 432 (2013). "Substantial evidence is that which a reasonable mind might accept as adequate to support a conclusion." Mason-McDuffie Real Estate, Inc. v. Villa Fiore Dev., LLC, 130 Nev. 834, 838, 335 P.3d 211, 214 (2014) (internal quotation marks and citation omitted). Following the conclusion of the bench trial, the district court found that MS earned a total of $2,591,250 under the contract but that Sands Aviation had only paid $1.7 million. In its letter dated November 24,

SUPREME COURT OF NEVADA 4 (0) 1947A e

MIK 1 iL 1111111 2014, AIS informed Sands Aviation that its invoice was "[b]ased upon the level of completeness of the design, the additional design and program related services provided, as well as other labor, materials, supplies, tools, equipment, and facility costs, which t[ook] into account over 10,000 engineering and program management hours." Additionally, AIS provided Sands Aviation with 22 gigabytes of data "relat[ing] to its design of the Airplane" The district court noted that Sands Aviation terminated the contract just three days before the preliminary-design-review benchmark, which would have entitled AIS to an additional $1.7 million.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hilton Hotels Corp. v. Butch Lewis Productions, Inc.
862 P.2d 1207 (Nevada Supreme Court, 1993)
Dass v. Epplen
424 P.2d 779 (Supreme Court of Colorado, 1967)
Asphalt Products Corp. v. All Star Ready Mix, Inc.
898 P.2d 699 (Nevada Supreme Court, 1995)
Hilton Hotels Corp. v. Butch Lewis Productions, Inc.
808 P.2d 919 (Nevada Supreme Court, 1991)
Wyeth v. Rowatt
244 P.3d 765 (Nevada Supreme Court, 2010)
Ringle v. Bruton
86 P.3d 1032 (Nevada Supreme Court, 2004)
Unionamerica Mortgage & Equity Trust v. McDonald
626 P.2d 1272 (Nevada Supreme Court, 1981)
Edwards v. Emperor's Garden Restaurant
130 P.3d 1280 (Nevada Supreme Court, 2006)
Sowers v. Forest Hills Subdivision
294 P.3d 427 (Nevada Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Sands Aviation, LLC v. Ais-Int'l, Ltd. C/W 73522, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sands-aviation-llc-v-ais-intl-ltd-cw-73522-nev-2019.