Sandoval v. Qualcomm Incorporated

CourtCalifornia Court of Appeal
DecidedOctober 19, 2018
DocketD070431
StatusPublished

This text of Sandoval v. Qualcomm Incorporated (Sandoval v. Qualcomm Incorporated) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sandoval v. Qualcomm Incorporated, (Cal. Ct. App. 2018).

Opinion

Filed 10/19/18 CERTIFIED FOR PUBLICATION

COURT OF APPEAL, FOURTH APPELLATE DISTRICT

DIVISION ONE

STATE OF CALIFORNIA

JOSE M. SANDOVAL, D070431

Plaintiff and Appellant,

v. (Super. Ct. No. 37-2014-00012901- CU-PO-CTL) QUALCOMM INCORPORATED,

Defendant and Appellant.

APPEALS from a judgment and posttrial orders of the Superior Court of

San Diego County, Joan M. Lewis, Judge. Affirmed.

Horvitz & Levy, Stephen E. Norris, Jason R. Litt and Joshua C. McDaniel;

Wingert Grebing Brubaker & Juskie, Alan K. Brubaker and Colin H. Walshok for

Thon Beck Vanni Callahan & Powell and Daniel P. Powell; Esner, Chang &

Boyer and Stuart B. Esner for Plaintiff and Appellant.

Plaintiff Jose M. Sandoval was severely burned by an "arc flash" from a live

circuit breaker while working with contractor TransPower Testing, Inc., and its principal, Frank Sharghi (sometimes collectively, TransPower),1 at a cogeneration plant owned by

defendant Qualcomm Incorporated (Qualcomm). The jury returned a special verdict

finding that Qualcomm retained control over the safety conditions at the jobsite; that it

negligently exercised such control; and that its negligence was a substantial factor in

causing Sandoval's harm. The jury found Sandoval's employer, ROS Electrical Supply

(ROS), not liable, and apportioned fault as follows: 46 percent to Qualcomm; 45 percent

to TransPower; and 9 percent to Sandoval.

Following the verdict, Qualcomm moved for judgment notwithstanding the verdict

(JNOV) and for a new trial. The trial court denied the JNOV motion but granted the

motion for new trial on the theory the jury had improperly apportioned liability.

Qualcomm appeals from the order denying its JNOV motion, arguing Sandoval

failed to proffer any evidence to show that Qualcomm, as the hirer of an independent

contractor, "affirmatively contributed" to Sandoval's injury under the "retained control"

exception to the general rule that a hirer is not liable for the injuries of an independent

contractor's employees or its subcontractors; from the order only partially granting its

new trial motion; and from the original judgment. Sandoval appeals from the order

granting Qualcomm a new trial on the apportionment of fault issue.

As we explain, we conclude substantial evidence supports the jury's finding that

Qualcomm negligently exercised retained control over the safety conditions at the jobsite.

We thus conclude the court properly denied Qualcomm's JNOV. We further conclude

1 Neither TransPower nor Sharghi is a party to this appeal. 2 the court properly exercised its discretion when, sitting as an independent trier of fact, it

granted Qualcomm a limited new trial only on the issue of apportionment of fault as

between Qualcomm and TransPower. Affirmed.

FACTUAL BACKGROUND

The Cogeneration Plant/Switchgear

To power its facilities, Qualcomm at the time of the accident operated a

cogeneration plant at its Morehouse "campus" in San Diego. The cogeneration plant

generates electricity from two sources: a utility (i.e., San Diego Gas & Electric) and

Qualcomm's own on-site gas turbine generator. Qualcomm used this system, sometimes

referred to as a "switchgear," to ensure it had an "[u]ninstructable [p]ower [s]upply"; that

is, if the utility supply stopped, Qualcomm had a system in place to ensure its facilities,

equipment, and data remained "powered up." Qualcomm's switchgear was manufactured

in 1982.

Sharghi

Qualcomm in 2013 was in the process of upgrading its power generation system.

As part of that upgrade, Qualcomm hired TransPower, an electrical engineering service

company. Sharghi testified that he began working on the switchgear in 1993, before it

was owned by Qualcomm; that he thus was very familiar with the switchgear, as he

estimated he had worked on it "hundreds of times" over the years; that beginning in about

2013, TransPower typically was at Qualcomm's facility about two or three times per

week, during the upgrade; that Qualcomm's "old" generator could generate electricity at

1200 amps, but that, once installed, its "new" generator could generate electricity at 2000

3 amps; and that TransPower was asked among other things to evaluate whether

Qualcomm's breaker system, and in particular the "bus bars," could accommodate 2000

amps that would be generated by the new gas turbine.

Regarding Sandoval, Sharghi testified that they had known each other for 20

years; that Sandoval was "safe" in his work and very reliable; that Sandoval and the

company he worked for, ROS, helped TransPower locate certain parts it needed for its

customers including Qualcomm, as specified by TransPower; that although Sandoval was

not an engineer, he nonetheless understood how "all the components" worked and "what

kind of ampacity the equipment can take or not"; and that TransPower thus hired

Sandoval for a lot of jobs, including on August 3, 2013, when TransPower inspected

Qualcomm's breaker system to determine if it could handle the additional amperage.

TransPower on June 15, 2013, had inspected the bus bars after Qualcomm had

shut down, or "de-energized," a portion of the switchgear while moving some cables.

Sharghi testified that during the June 15 inspection, he could not determine whether the

"bus bar that goes out of the breaker on the bottom of the breaker" could support the

additional amperage that would be generated by the upgrade. As a result, Sharghi asked

Sandoval to accompany him to Qualcomm's cogeneration plant to look at the bus bars, as

this analysis was a "big responsibility" for TransPower because if Sharghi was wrong

about the bus bars, the "whole thing" could melt.

Sharghi recalled telling Sandoval during a phone conversation before August 3

that they could safely do an inspection on that particular day because the main

cogeneration (or cogen) breaker of the switchgear would be "de-energized." During that

4 same telephone conversation, Sharghi did not tell Sandoval to bring personal protective

equipment (PPE) to conduct the inspection. Sharghi testified he always carried his PPE

with him, but only used it when a job involved "high voltage stuff" in order to prevent or

minimize injury due to arc flash. Sharghi recalled telling Sandoval during this particular

phone conversation he would bring PPE and another TransPower employee, George

Guadana, who also would be doing the inspection, would also have PPE.

Regarding arc flash, Sharghi testified that electricity is in a copper conduit; that air

acts as a partial insulator; and that, when the "electricity gets out of the copper conduit"

or there is a "short" or "fault" "somewhere in [a] . . . system downstream," the breaker is

"trip[ped] . . . and turns the power off." Sharghi noted electrical engineers used certain

software to calculate the "arc flash zones of safety." Once factors such as the size of the

conductor and the amount of load that is carried are determined, a computer model

provides the "caliber [of] clothing" a person must wear when working around a breaker

and the distance that must be kept from the breaker when the system is energized. This

information is then printed out and placed on each individual breaker, as it varies from

breaker to breaker. Sharghi testified that neither he nor his company had ever worked on

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mercer v. Perez
436 P.2d 315 (California Supreme Court, 1968)
Schelbauer v. Butler Manufacturing Co.
673 P.2d 743 (California Supreme Court, 1984)
Soule v. General Motors Corp.
882 P.2d 298 (California Supreme Court, 1994)
Scala v. Jerry Witt & Sons, Inc.
475 P.2d 864 (California Supreme Court, 1970)
Privette v. Superior Court
854 P.2d 721 (California Supreme Court, 1993)
Aronowicz v. Nalley's, Inc.
30 Cal. App. 3d 27 (California Court of Appeal, 1972)
O'KELLY v. Willig Freight Lines
66 Cal. App. 3d 578 (California Court of Appeal, 1977)
Red Mountain, LLC v. Fallbrook Public Utility District
48 Cal. Rptr. 3d 875 (California Court of Appeal, 2006)
Traxler v. Varady
12 Cal. App. 4th 1321 (California Court of Appeal, 1993)
Hooker v. Department of Transportation
38 P.3d 1081 (California Supreme Court, 2002)
McKown v. Wal-Mart Stores, Inc.
38 P.3d 1094 (California Supreme Court, 2002)
Sweatman v. Department of Veterans Affairs
18 P.3d 29 (California Supreme Court, 2001)
Kinsman v. Unocal Corp.
123 P.3d 931 (California Supreme Court, 2005)
Orichian v. BMW of North America, LLC
226 Cal. App. 4th 1322 (California Court of Appeal, 2014)
Regalado v. Callaghan CA
3 Cal. App. 5th 582 (California Court of Appeal, 2016)
IIG Wireless, Inc. v. Yi
231 Cal. Rptr. 3d 771 (California Court of Appeals, 5th District, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Sandoval v. Qualcomm Incorporated, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sandoval-v-qualcomm-incorporated-calctapp-2018.