Sand Point Services, LLC

CourtArmed Services Board of Contract Appeals
DecidedJanuary 13, 2021
DocketASBCA No. 61819, 61820
StatusPublished

This text of Sand Point Services, LLC (Sand Point Services, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sand Point Services, LLC, (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of - ) ) Sand Point Services, LLC ) ASBCA Nos. 61819, 61820 ) Under Contract No. NNG14WA50C )

APPEARANCES FOR THE APPELLANT: Nathan Rouse, Esq. Traeger Machetanz, Esq. Davis Wright Tremaine LLP Seattle, WA

Eric S. Lammers, Esq. Rees Broome P.C. Tysons Corner, VA

Neil Lowenstein, Esq. Anthony J. Mazzeo, Esq. Vandeventer Black LLP Norfolk, VA

APPEARANCES FOR THE GOVERNMENT: Scott W. Barber, Esq. NASA Chief Trial Attorney David S. Schuman, Esq. Senior Trial Attorney NASA Goddard Space Flight Center Greenbelt, MD Paul H. Kim, Esq. Trial Attorney NASA Ames Research Center Moffett Field, CA

OPINION BY ADMINISTRATIVE JUDGE WITWER

These appeals involve disputes arising out of a contract between the National Aeronautics & Space Administration (NASA) and appellant Sand Point Services, LLC (SPS) to repair the Wallops Flight Facility’s aircraft parking apron (hereinafter “the project”). SPS alleges that NASA constructively changed the contract by initially waiving minor deviations from the contract specifications, and then insisting upon strict compliance with those specifications. It also alleges that insistence upon strict compliance with the specifications resulted in economic waste. Further, SPS alleges that it incurred extra costs and encountered delays because of a differing site condition. Fidelity and Deposit Company of Maryland (F&D), a non-party surety, furnished performance and payment bonds under the Miller Act, 40 U.S.C. § 3131 et seq., relating to the project at issue in these appeals. On October 16, 2020, NASA served F&D with a subpoena duces tecum. F&D has moved to quash the subpoena in its entirety. For the reasons set forth below, F&D’s motion is GRANTED.

Appellant also moves to quash the subpoena served on F&D. Additionally, appellant moves to quash a subpoena duces tecum issued to, but not yet served on, David Bresel, an attorney employed by F&D. For reasons set forth below, appellant’s motion to quash the subpoena directed to F&D is DENIED as moot and its motion to quash the subpoena directed to Mr. Bresel is DISMISSED.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTIONS

I. The Miller Act Dispute

On September 8, 2014, NASA entered into Contract No. NNG14WA50C with appellant to repair the Wallops Flight Facility’s aircraft parking apron (R4, tab 1 at 1-2, 4, tab 3 at 3). The contract required appellant to obtain a bond (R4, tab 1 at 4), which it obtained from F&D (F&D mot. at 2). In 2016, F&D received a claim from appellant’s subcontractor, Atlantic Contracting and Material, Inc. (ACM), on the Miller Act payment bond furnished by F&D (id.). After performing an investigation commensurate with its role as surety, F&D denied ACM’s claim (id).

ACM subsequently filed suit in Federal district court. Appellant intervened in the litigation and the same counsel represented F&D and appellant (id.). Appellant argued, inter alia, that the Miller Act action was premature because ACM had not completed its subcontract work to NASA’s satisfaction. In support of its argument, appellant’s general manager, Christopher Woodruff, submitted a declaration, alleging that “ACM has not fully and duly performed its subcontract work under the terms of the ACM subcontract” (gov’t opp’n, ex. 7, Woodruff decl., ¶ 16). In September 2017, the parties to the district court litigation reached an agreement and stipulated to a dismissal with prejudice of ACM’s suit (F&D mot. at 2).

II. Appeals Pending Before the Board

In September 2018, appellant filed two notices of appeal and complaints with the Board. In the first appeal, which we docketed as ASBCA No. 61819 (hereinafter “constructive change and waste appeal”), appellant admits that the project’s concrete texture and mooring eyes were deficient, but alleges that those deficiencies involve minor issues. Moreover, appellant alleges that NASA constructively changed the contract when it waived strict compliance with the specifications by accepting the concrete texture and

2 mooring eyes, but then insisted upon strict compliance with the specifications. Appellant also alleges that insisting upon strict compliance with the specifications caused economic waste.

In the second appeal, which we docketed as ASBCA No. 61820 (hereinafter “differing site condition appeal”), appellant concedes that there were delays, but alleges that those delays were attributable to NASA’s failure to provide directions after appellant notified it of a differing site condition.

III. The Board’s August 5, 2019 Decision

In October 2018, NASA filed a motion to dismiss and, in the alternative, motion for summary judgment. In moving to dismiss, NASA argued that the Board lacked jurisdiction because the contracting officer’s final decision (COFD) was based on a suspicion of fraud. Specifically, NASA contended that the claims appeared to be fraudulent because Mr. Woodruff admitted in his declaration submitted in the Miller Act litigation that ACM’s work was incomplete and not in conformance with the contract specifications. In moving for summary judgment, NASA argued that Mr. Woodruff’s admission entitled NASA to judgment as a matter of law, because it demonstrated that appellant’s failure to perform in accordance with the specifications was ACM’s fault. Finally, NASA argued that a bilateral modification released appellant’s differing site condition claim.

On August 5, 2019, the Board denied NASA’s motions (hereinafter “Decision”). Sand Point Servs., Inc., ASBCA Nos. 61819, 61820, 19-1 BCA ¶ 37,412. Of relevance here, in denying NASA’s motion to dismiss, the Board held that the COFD was not based solely upon a suspicion of fraud, and that the Board could resolve the appeals without making factual determinations of fraud. Id. at ¶ 181,857. In denying NASA’s motion for summary judgment, the Board found that appellant “did not admit that the failure to comply with the specifications was ACM’s fault.” Id. Further, the Board concluded that, even if appellant had made such an admission, the “issue is not material to SPS’s constructive change and waste appeal.” Id.

IV. The Board’s August 28, 2019 Discovery Order

While NASA’s dispositive motions were pending before the Board, the parties engaged in discovery. On May 15, 2019, NASA filed a motion to compel discovery related to the dispute between appellant and its subcontractor. On August 15, 2019, after receipt of the Decision, NASA renewed its motion to compel.

The Board denied NASA’s motion to compel in an order dated August 28, 2019 (hereinafter “Order”). The Order reiterated that the Miller Act dispute was irrelevant to the appeals because “even if SPS’s dispute with its subcontractor established that it was

3 the subcontractor’s fault that performance did not meet the specifications, that fact would not preclude SPS’s claim” (Order at 2). The Order instructed NASA to consider whether it needed to recalibrate future discovery requests in light of the Decision. If NASA concluded that such recalibration was unnecessary, the Board ordered NASA to conduct good faith discussions with SPS to explain how the information sought was relevant in light of the Decision. If such discussions proved unproductive, the Order permitted the government to “file a motion to compel providing such an explanation to the Board” (id.). To date, no motions to compel the production of information related to the Miller Act dispute have been submitted to the Board.

V. Subpoenas Duces Tecum

Turning to the issue of the subpoenas, on October 7, 2020, NASA requested the subpoenas at issue here, which the Board issued on October 14.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wiwa v. Royal Dutch Petroleum Co.
392 F.3d 812 (Fifth Circuit, 2004)
Microsoft Corp. v. United States
162 F.3d 708 (First Circuit, 1998)
Truswal Systems Corp. v. Hydro-Air Engineering, Inc.
813 F.2d 1207 (Federal Circuit, 1987)
United States v. Idema
118 F. App'x 740 (Fourth Circuit, 2005)
Griffin v. Foley
542 F.3d 209 (Seventh Circuit, 2008)
In Re Subpoena Duces Tecum to AOL, LLC
550 F. Supp. 2d 606 (E.D. Virginia, 2008)
Call of the Wild Movie, LLC v. DOES 1-1,062
770 F. Supp. 2d 332 (District of Columbia, 2011)
Dell Inc. v. Decosta
233 F. Supp. 3d 1 (District of Columbia, 2017)
Jade Trading, LLC v. United States
65 Fed. Cl. 188 (Federal Claims, 2005)
JZ Buckingham Investments LLC v. United States
78 Fed. Cl. 15 (Federal Claims, 2007)
Zoltek Corp. v. United States
104 Fed. Cl. 647 (Federal Claims, 2012)
Stevenson v. Stanley Bostitch, Inc.
201 F.R.D. 551 (N.D. Georgia, 2001)
Washington v. Thurgood Marshall Academy
230 F.R.D. 18 (D.C. Circuit, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Sand Point Services, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sand-point-services-llc-asbca-2021.