San Miguel v. Municipality of Caguas

69 P.R. 895
CourtSupreme Court of Puerto Rico
DecidedMay 10, 1949
DocketNo. 9722
StatusPublished

This text of 69 P.R. 895 (San Miguel v. Municipality of Caguas) is published on Counsel Stack Legal Research, covering Supreme Court of Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
San Miguel v. Municipality of Caguas, 69 P.R. 895 (prsupreme 1949).

Opinion

Me. Justice Marrero

delivered the opinion of the Court,

By ordinance approved in 1928, the Municipality of C’a-guas made a loan for the sum of $146,000 to cover the cost, of certain improvements to its waterworks and of other mu--nicipal public works. Of this loan the amount of $60,000 ' was allotted for the filtration plant of the waterworks but-by a subsequent ordinance approved on January 8 of the-: following year it was increased to $80,000. The award for-the construction of the filtration plant was adjudicated at; a public bid to engineer Robert R. Prann for the sum of.' $33,976.64, a final contract being executed between the parties on February 3, 1931 which was approved by the Commissioner of the Interior of Puerto Rico on April 13 of the same year, The work was completed by the contractor to the satisfaction of the parties, but upon the final liquidation being made by the Commissioner of the Interior it disclosed! that the total cost of the work amounted to $45,753.33, the excess of $12,484.63 being certified by the Commissioner to be paid by the municipality.

Since the contractor owed, on other accounts, a larger sum to the Banco Territorial y Agrícola de Puerto Rico which at that time was in liquidation, the District Court of San. Juan shortly thereafter authorized the conveyance to said bank of the credit which Prann had acquired by the aforesaid contract with the Municipality of Caguas. Several, years elapsed and since the Banco Territorial was still in possession of the credit conveyed to it, which still remained unpaid, on March 25, 1943 it sold said credit to the plaintiff for the amount of $2,500. To collect this credit the appellant instituted a mandamus proceeding which it abandoned before the court disposed of it on its merits. Thereafter it filed the proceeding which is now before .us. It prays that judgment be rendered ordering the municipality defendant to pay the aforesaid $12,484.63, with legal interest from November 4, 1933 until its full payment; or, in the alternative, to establish the existence of a lien on said filtration [898]*898plant in its favor for the stated amount with interest; or to decree the acknowledgment by said municipality of a condominium on said filtration plant for the aforesaid amount with interest in favor of the plaintiff; or to grant any other adequate remedy with costs and'attorney’s fees.

The case was heard bn its merits and after both parties introduced ample oral and • documentary evidence, the District Court of Caguas dismissed the complaint with costs on the plaintiff. The gist of the decision was that since the contractor had failed to make his claim .within the period of one month for the extra work performed by him his right had prescribed, and, hence, so had plaintiff’s. From this judgment the present appeal was taken.'

Appellant insists that the lower court erred in deciding that the contractor’s failure to require the payment .for the extra work within the period of one month barred plaintiff’s right to claim it.

Clause 6 of the contract executed between Prann and the Municipality of Caguas on February 3, 1931 provides “That the General Conditions of the Contract for Insular Public Works in force since July 1902, are applicable to this contract and are a part thereof.” And § 30 of the aforesaid General Conditions reads thus:

“Extra Work”

“Any alteration or changes in the project producing work not provided for in the contract shall be considered as extra work.

.“No claim for extra, work shall be allowed unless such work shall have been previously ordered in writing by the local engineer with the approval of the Superintendent of Public Works, and an agreement upon the prices to be paid for such extra work has been reached between the engineer and the contractor and ■such prices duly approved.

“The claims for extra work, when it is ordered, shall be presented and paid in the next monthly estimate for extra xvork, ■otherwise, said claims shall be forfeited and. waived,.

[899]*899“Alterations or changes in the details of .the work not entailing new prices shall not be considered as extra work, and the contractor will be required to perform such' alterations or changes under the direction of the local engineer at the prices named in the Contract; Provided, however, That said alterations and changes do not increase the quantities over 20 per cent of the original, estimate. For all work in excess of 20 per cent of the original quantities caused by such alterations and changes, the Bureau of Public Works reserves the right to enter into a written agreement with the contractor to execute such additional work upon prices mutually agreed upon, or to have the same carried out by day labor or by any other method it may direct. Should, however, any alterations or changes in the work produce a diminution in the original cost or quantities not reaching 20 °/o, the reduction thus made shall not constitute a claim for damages by the contractor or for profits supposed to be lost by him on the work that may be altered or dispensed with.” (Italics ours.)

There is nothing in . the record to show that contractor. Prann presented his claim to the municipality in the next monthly estimate, for extra work, as required by § 30. In the absence of evidence to this effect said claim, according to the very terms of said Section, should be considered as forfeited for nonfulfillment and as waived. The first error was not committed. . ■.

Under the second assignment plaintiff maintains that “in the event that the stipulated period of prescription should be considered. applicable,” the lower court erred “in not limiting its effect to any quantity in excess of twenty (20) per cent of the amount of the contract.”

We do not agree with the plaintiff. It is true that'in the Contract Specifications and General Conditions supplied to all those .persons who appeared at the public bid advertised by _the -Municipality of Caguas in connection with the improvements to its waterworks, the following condition .appeals under No. 26:

. “.-, . Any work in-excess of twenty (20) per cent of the amo,unt of the..contract shall be..dealt with pursuant .to sec. SO of the General'.'.Cohditions .of the Contract for insular 'public works.” ' ' •' ' ” •'*•v‘

[900]*900It is likewise true that pursuant to § 20 thereof, said specifications form part of the contract. But in our analysis of the first assignment of error we have become acquainted with § 30 of the General Conditions and nowhere does it specifically provide that when the extra work exceeds 20 per cent, the contractor shall be entitled to recover the 20 peí cent thereof, even if he has failed to make his claim within the next month. The object of referring in paragraph 26 of the Specifications to § 30 of the General Conditions was undoubtedly to stress the point that the Bureau of Public Works reserved the right, with respect to every Work in excess of 20 per cent of the original amount, to execute a written contract with the contractor but not to make an exception for the recovery Of the 20 per cent When the extra work performed exceeded that percentage. The parties adhiit that the extra Work was harried out and that it was duly certified by the proper municipal officer and by the Commissioner of the Interior.

Free access — add to your briefcase to read the full text and ask questions with AI