San Diego Coast Regional Commission v. See the Sea, Limited

513 P.2d 129, 9 Cal. 3d 888, 109 Cal. Rptr. 377, 3 Envtl. L. Rep. (Envtl. Law Inst.) 20760, 5 ERC (BNA) 1761, 1973 Cal. LEXIS 235
CourtCalifornia Supreme Court
DecidedAugust 22, 1973
DocketL.A. 30142
StatusPublished
Cited by33 cases

This text of 513 P.2d 129 (San Diego Coast Regional Commission v. See the Sea, Limited) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
San Diego Coast Regional Commission v. See the Sea, Limited, 513 P.2d 129, 9 Cal. 3d 888, 109 Cal. Rptr. 377, 3 Envtl. L. Rep. (Envtl. Law Inst.) 20760, 5 ERC (BNA) 1761, 1973 Cal. LEXIS 235 (Cal. 1973).

Opinion

Opinion

CLARK, J.

Appeal from order denying preliminary injunction. (Code Civ. Proc., § 904.1, subd. (f).)

*890 Defendant owns land within 1,000 yards of the California coastline. Having planned to develop the property since 1968, it applied to the City of San Diego for a building permit in July 1972, for construction of a condominium project.

The permit was granted on 6 December 1972. In the first week of January 1973, defendant demolished a motel on the site and, prior to 1 February, spent $79,000 in construction, also incurring finance charges.

Construction progressed to 2 March 1973 when plaintiff, a regional commission operating pursuant to the California Coastal Zone Conservation Act of 1972 (Pub. Resources Code, §27000 et seq.; 1 hereinafter “act”), commenced this action to impose civil fines 2 and to halt further development on the ground defendant lacked a coastal permit. A temporary restraining order issued by the trial court was subsequently dissolved and a preliminary injunction denied. The court found that prior to 1, February 1973 defendant had obtained a vested right to complete the development because it had relied in good faith on the city’s building permit, and that a coastal permit therefore was not required. Plaintiff appeals.

We have concluded the act requires a coastal permit for construction commenced after 1 February 1973, but does not require one for builders performing substantial lawful construction of their projects prior thereto.

The act, adopted as an initiative measure (Proposition 20) at the 7 November 1972 general election, has the stated purposes of permanently protecting and restoring the natural and scenic resources of the coastal zone. (§27001.)

The act provides that a permit from a regional commission shall be required for developments on land within 1,000 yards of the mean high tide line (called the “permit area”) (§§27001, subd. (c), 27104, 27400) to assure coastal development consistent with certain environmental objectives (§§27402, 27403, 27001, 27302).

Section 27400 provides: “On or after February 1, 1973, any person wishing to perform any development within the permit area shall obtain a permit authorizing such development from the regional commission and, if required by law, from any city, county, state, regional or local agency.” (Italics added.)

*891 Section 27404 provided at the time the act was passed: “If, prior to the effective date of this division, any city or county has issued a building permit, no person who has obtained a vested right thereunder shall be required to secure a permit from the regional commission; . . . Any such person shall be deemed to have such vested rights if, prior to April 1, 1972, he has in good faith and in reliance upon the building permit diligently commenced construction and performed substantial work on the development and incurred substantial liabilities for work and materials necessary therefor.” 3 (Italics added.)

The ballot pamphlet furnished voters respecting Proposition 20 contained the Detailed Analysis by the Legislative Counsel stating: “4. Beginning February 1, 1973, [the act would] require a permit from a regional commission for any proposed development (with specified exemptions) within the ‘permit area,’ . . . .” (Italics added.) The ballot pamphlet also contained the Argument in Favor of Proposition 20, jointly authored by a United States Senator, a State Senator, and the Speaker of the Assembly, which stated: “The Safeguards: (1) This act will not impose a moratorium or prohibit any particular kind of building, but ensures that authorized construction will have no substantial adverse environmental effect[.]” (Italics added in part.)

In imposing the permit requirement on “any person wishing to perform any development” on or after 1 February 1973, the language of section 27400 is directed at persons who have not commenced construction on the operative date, and it is conceded by plaintiff that construction could lawfully commence prior to that date without a coastal permit. Nowhere does the act expressly provide for a moratorium on construction commenced prior to 1 February 1973. Reference having been omitted to a moratorium and to work commenced but uncompleted on 1 February, the plain implication of the prospective language used is that the coastal permit requirement would be inapplicable to such projects.

Legislative Counsel’s analysis set forth in the voters’ pamphlet reinforces this conclusion by having stated a coastal permit would be required for “proposed” developments beginning 1 February. Further, the ballot argument of the act’s proponents expressly stated the act would not impose a moratorium.

*892 Had the act been intended to require a permit for completion of construction commenced before 1 February, the requirement would as a practical matter have resulted in a moratorium on all construction in the permit area. The built-in delays incident to the issuance of permits, which could exceed seven months (§§ 27420, 27423), would have necessitated work stoppages for all development along the California coastline after 1 February 1973 for a significant period 4 (except the rare uncompleted projects commenced prior to 1 April 1972). Such interference with construction in progress, tantamount to a moratorium, would result in serious economic dislocations not contemplated by the act, its authors, or the voters.

Therefore, in the absence of language in the act imposing a moratorium, it is reasonable to conclude the voters intended none.

It should here be added that the Legislative Counsel, by opinion rendered nearly two months prior to passage of the act, concluded that a person who, prior to 1 February 1973, in good faith lawfully commenced construction, performed substantial work, and incurred substantial liabilities would be allowed to complete the development without a coastal permit.

Relying on provisions of section 27404 set forth above that no permit is required of certain persons who have commenced construction, plaintiff urges the section thus means all others must obtain permits. It is only by negative implication from this section that such a class can be defined. While providing for exemption, the section does not expressly impose a permit requirement on anyone. The prospective language used in section 27400 and in the Detailed Analysis of the Legislative Counsel, the proponents’ express denial of intent to impose a moratorium, and the absence of express statutory provision for a moratorium again lead us to conclude the permit requirement should not be expanded by negative implication to construction commenced before 1 February 1973.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. Bates
127 F.3d 839 (Ninth Circuit, 1997)
Citizens for Covenant Compliance v. Anderson
906 P.2d 1314 (California Supreme Court, 1995)
City of West Hollywood v. Beverly Towers, Inc.
805 P.2d 329 (California Supreme Court, 1991)
Halaco Engineering Co. v. South Central Coast Regional Commission
720 P.2d 15 (California Supreme Court, 1986)
Pardee Construction Co. v. California Coastal Commission
95 Cal. App. 3d 471 (California Court of Appeal, 1979)
Los Alamitos General Hospital, Inc. v. Lackner
86 Cal. App. 3d 417 (California Court of Appeal, 1978)
Frisco Land & Mining Co. v. State of California
74 Cal. App. 3d 736 (California Court of Appeal, 1977)
South Coast Regional Commission v. Higgins
68 Cal. App. 3d 636 (California Court of Appeal, 1977)
South Coast Regional Commission v. Gordon
558 P.2d 867 (California Supreme Court, 1977)
Oceanic California, Inc. v. North Central Coast Regional Commission
63 Cal. App. 3d 57 (California Court of Appeal, 1976)
Avco Community Developers, Inc. v. South Coast Regional Commission
553 P.2d 546 (California Supreme Court, 1976)
Sierra Club v. California Coastal Zone Conservation Commission
58 Cal. App. 3d 149 (California Court of Appeal, 1976)
Davis v. California Coastal Zone Conservation Commission
57 Cal. App. 3d 700 (California Court of Appeal, 1976)
Sanders v. Pacific Gas & Electric Co.
53 Cal. App. 3d 661 (California Court of Appeal, 1975)
REA Enterprises v. California Coastal Zone Conservation Commission
52 Cal. App. 3d 596 (California Court of Appeal, 1975)
No Oil, Inc. v. Occidental Petroleum Corp.
50 Cal. App. 3d 8 (California Court of Appeal, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
513 P.2d 129, 9 Cal. 3d 888, 109 Cal. Rptr. 377, 3 Envtl. L. Rep. (Envtl. Law Inst.) 20760, 5 ERC (BNA) 1761, 1973 Cal. LEXIS 235, Counsel Stack Legal Research, https://law.counselstack.com/opinion/san-diego-coast-regional-commission-v-see-the-sea-limited-cal-1973.