San Antonio River Authority v. Austin Bridge & Road, L.P. and Hayward Baker, Inc.

CourtTexas Supreme Court
DecidedMay 1, 2020
Docket17-0905
StatusPublished

This text of San Antonio River Authority v. Austin Bridge & Road, L.P. and Hayward Baker, Inc. (San Antonio River Authority v. Austin Bridge & Road, L.P. and Hayward Baker, Inc.) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
San Antonio River Authority v. Austin Bridge & Road, L.P. and Hayward Baker, Inc., (Tex. 2020).

Opinion

IN THE SUPREME COURT OF TEXAS ══════════ No. 17-0905 ══════════

SAN ANTONIO RIVER AUTHORITY, PETITIONER,

v.

AUSTIN BRIDGE & ROAD, L.P. AND HAYWARD BAKER, INC., RESPONDENTS ══════════════════════════════════════════ ON PETITION FOR REVIEW FROM THE COURT OF APPEALS FOR THE FOURTH DISTRICT OF TEXAS ══════════════════════════════════════════

Argued September 18, 2019

JUSTICE BLAND delivered the opinion of the Court, in which JUSTICE GREEN, JUSTICE LEHRMANN, JUSTICE BLACKLOCK, and JUSTICE BUSBY joined.

JUSTICE BOYD filed a dissenting opinion, in which CHIEF JUSTICE HECHT, JUSTICE GUZMAN, and JUSTICE DEVINE joined.

This construction contract dispute involves repairs to the Medina Lake Dam that went over

budget. The San Antonio River Authority hired Austin Bridge and Road L.P. as its general

contractor for the project. The parties agreed—in bid documents proffered by the River

Authority—to submit any disputes about the contract to arbitration. When disagreements about the

scope of work and payment arose, Austin Bridge invoked the contract’s arbitration provisions.

Arbitration proceedings commenced. But after the arbitrator denied the River Authority’s plea of

governmental immunity, the River Authority objected to continuing the arbitration. The River Authority then sued its contractors in state district court, contending that it had lacked any authority

to agree to the contract’s arbitration provisions.

We conclude that Local Government Code Chapter 271 provided that authority. Chapter

271 authorizes local governments, like the River Authority, to agree to arbitrate claims brought

under the chapter. Chapter 271 further provides that the final resolution of an arbitration

proceeding is “enforceable” insofar as immunity is waived. What is enforceable is authorized.

Because the River Authority possessed the authority to agree to arbitrate claims under

chapter 271, and exercised that authority in this contract, we must determine whether an arbitrator

may decide matters of governmental immunity. Immunity implicates subject-matter jurisdiction;

it may be waived only by the legislature’s consent. And enforcement of a judgment against a local

government requires the exercise of state judicial power. Courts are empowered to enforce such

judgments only to the extent that immunity is waived. Accordingly, the judiciary retains the duty

to decide whether a local government has waived its immunity, and the extent to which any

arbitration award is recoverable against a local government—the parties’ agreement to arbitrate

notwithstanding. Finally, we conclude that the River Authority’s immunity has been waived in this

case. Because the court of appeals reached similar conclusions, we affirm its judgment.

I

The Bexar–Medina–Atascosa Counties Water Control and Improvement District No. 1

owns and operates the Medina Lake Dam, built more than a hundred years ago. 1 About twenty

1 For a brief description of the Medina Lake Dam and its storied history, see Lance v. Robinson, 543 S.W.3d 723, 726–27 (Tex. 2018).

2 years ago, the District discovered that the dam was falling apart. The Texas Legislature authorized

$4 million in state funds for needed repairs. 2

The District and four other local governments—Bexar County, the Bexar Metropolitan

Water District, the San Antonio River Authority, and the Edwards Aquifer Authority—agreed to

undertake the repair project through a “Cooperative Agreement.” In that agreement, the District

and Bexar County each promised to provide $3 million for the project. For its part, the San Antonio

River Authority agreed to serve as the “project manager and contract administrator.” In exchange

for a fee for its services, the River Authority promised to “ensure quality construction and

execution of the project” and to “manage and deliver the [project] within authorized funding

levels.”

After soliciting bids for the work, the River Authority awarded the construction contract to

Austin Bridge. The construction contract required Austin Bridge to repair the dam within a year.

In return, the River Authority agreed to pay Austin Bridge under a project-management schedule.

The contract includes an arbitration provision requiring that disputes arising under the

contract “be decided by arbitration in accordance with the Construction Industry Arbitration Rules

of the American Arbitration Association.” The contract further provides that an “award rendered

by the arbitrators will be final, judgment may be entered upon it in any court having jurisdiction

thereof, and will not be subject to modification or appeal except to the extent permitted by Sections

10 and 11 of the Federal Arbitration Act.”

2 See Act of May 27, 2009, 81st Leg., R.S., ch. 1409, § 17, 2009 Tex. Gen. Laws 4416, 4420. The legislature appropriated the funds to the Texas Water Development Board for the Board to then grant to the District to assist with the repairs.

3 Austin Bridge subcontracted part of the repair work to Hayward Baker, Inc. Hayward

Baker expended more in labor and materials than projected, increasing the cost of the project. Both

Austin Bridge and Hayward Baker attribute these costs to faulty specifications in the River

Authority’s bid documents, which resulted in change orders to the scope of their work; the River

Authority disagrees. When the River Authority refused to pay these additional costs, Hayward

Baker demanded arbitration against Austin Bridge, which in turn demanded arbitration against the

River Authority. In its demand, Austin Bridge alleged that the River Authority breached the

construction contract by failing to pay additional amounts owed under the agreement.

The River Authority appeared before the arbitrator and moved to dismiss the arbitration

proceeding on the ground that governmental immunity bars the claim against it. The arbitrator

denied the motion. Having lost that ruling before the arbitrator, the River Authority sued Austin

Bridge and Hayward Baker in state district court. The River Authority requested that the court

enjoin the arbitration proceeding and declare that governmental immunity bars the claim against

the Authority. The parties moved for summary judgment on the immunity question. The trial court

denied the River Authority’s motion and granted Austin Bridge and Hayward Baker’s, ruling that

the arbitration provisions in the construction contract are enforceable.

The court of appeals reversed in part. 3 It agreed with the trial court that the River Authority

had the authority to agree to arbitrate but concluded that a court, not an arbitrator, must decide

whether the River Authority is immune from the claims against it and from enforcement of any

resulting award. 4 The court of appeals then addressed the immunity issue, ruling in accord with

3 581 S.W.3d 245, 259 (Tex. App.—San Antonio 2017). 4 Id. at 252, 258.

4 the arbitrator and the trial court that Local Government Code Chapter 271 waives the River

Authority’s immunity from suit. 5 The court of appeals remanded the case to the trial court with

instructions to enter an order compelling arbitration and staying all other court proceedings

pending the arbitrator’s award. 6

We granted the River Authority’s petition for review. In this Court, the parties present three

issues: (1) whether their agreement to arbitrate is enforceable, (2) if so, whether the courts must

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Options of Chicago, Inc. v. Kaplan
514 U.S. 938 (Supreme Court, 1995)
Howsam v. Dean Witter Reynolds, Inc.
537 U.S. 79 (Supreme Court, 2002)
Texas Department of Parks & Wildlife v. Miranda
133 S.W.3d 217 (Texas Supreme Court, 2004)
City of Galveston v. State
217 S.W.3d 466 (Texas Supreme Court, 2007)
In Re Merrill Lynch Trust Co. FSB
235 S.W.3d 185 (Texas Supreme Court, 2007)
Forest Oil Corp. v. McAllen
268 S.W.3d 51 (Texas Supreme Court, 2008)
Kirby Lake Development, Ltd. v. Clear Lake City Water Authority
320 S.W.3d 829 (Texas Supreme Court, 2010)
The City of Houston v. Steve Williams
353 S.W.3d 128 (Texas Supreme Court, 2011)
Texas Natural Resource Conservation Commission v. IT-Davy
74 S.W.3d 849 (Texas Supreme Court, 2002)
Burlington Resources Oil & Gas Co. v. San Juan Basin Royalty Trust
249 S.W.3d 34 (Court of Appeals of Texas, 2007)
Quincy Lee Co. v. Lodal and Bain Engineers Inc.
602 S.W.2d 262 (Texas Supreme Court, 1980)
Haddock v. Quinn
287 S.W.3d 158 (Court of Appeals of Texas, 2009)
Clear Lake City Water Authority v. Clear Lake Utilities Co.
549 S.W.2d 385 (Texas Supreme Court, 1977)
Dubai Petroleum Co. v. Kazi
12 S.W.3d 71 (Texas Supreme Court, 2000)
City of Sherman v. Public Utility Com'n of Texas
643 S.W.2d 681 (Texas Supreme Court, 1983)
General Services Commission v. Little-Tex Insulation Co.
39 S.W.3d 591 (Texas Supreme Court, 2001)
Berkman v. City of Keene
311 S.W.3d 523 (Court of Appeals of Texas, 2009)
Kansas City Southern v. Port of Corpus Christi Authority
305 S.W.3d 296 (Court of Appeals of Texas, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
San Antonio River Authority v. Austin Bridge & Road, L.P. and Hayward Baker, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/san-antonio-river-authority-v-austin-bridge-road-lp-and-hayward-tex-2020.