Samuel Braen's Sons v. Fondo

145 A.2d 145, 52 N.J. Super. 188, 1958 N.J. Super. LEXIS 395
CourtNew Jersey Superior Court Appellate Division
DecidedOctober 9, 1958
StatusPublished
Cited by7 cases

This text of 145 A.2d 145 (Samuel Braen's Sons v. Fondo) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Samuel Braen's Sons v. Fondo, 145 A.2d 145, 52 N.J. Super. 188, 1958 N.J. Super. LEXIS 395 (N.J. Ct. App. 1958).

Opinion

The opinion of the court was delivered by

Conford, J. A. D.

This action was instituted June 1, 1955 to recover upon a statutory bond (N. J. S. 3A:44—143 et seq.) given July 33, 1954, covering performance by a contractor on a contract for certain municipal improvements in the Borough of Fair Lawn. The contractor was Magnifico Construction Company, which, after commencing performance of the work, defaulted and was adjudicated bankrupt March 15, 1955. Plaintiff and its assignors were suppliers of labor and materials to the contractor in connection with the project. It was stipulated at the trial that there was a balance of $1,531.97 owing to the plaintiff on the job.

Paragraph 7 of the complaint states that the action “is instituted within one year from the date of acceptance.” The defendant Standard Accident Insurance Company (Standard) filed its answer June 33, 1955 denying liability in general terms and not setting up the defense of prema[191]*191tui'ity of the action. It is undisputed that the Borough of Pair Lawn did not accept the improvement until July 10, 1956. On October 4, 1956 the case was pretried, and the pretrial order expressly states as a defense that the action was prematurely instituted in that it was filed prior to acceptance of the work, contrary to the statute governing bonds on public contracts. Moreover) included in the specification of issues in the order is the question: “14. Has the action against Standard Accident Insurance Co. been prematurely brought?”

After tiie submission of proofs at the trial the court granted a motion by Standard to dismiss the action as against it on the ground of prematurity of the action under the statute, N. J. S. 2A:44-145, which provides as to actions on surety bonds given on public contracts:

“No action shall be brought against any of the sureties on the bond required by this article until the expiration of 80 days after the acceptance of the building, work or improvement by the duly authorized board or officer.”

Under N. J. S. 2A:44-146 an action on such a bond may lie brought by any of the persons for whose benefit it is required to bo filed within one year from the date of acceptance of the work. The bond is required primarily for the benefit of the public agency or body for wldch the work is being done and secondarily for the benefit of material-men and subconi factors and others whose labor or materials go into the performance of the contract. N. J. S. 2A:44-143; Williamsport Planing Mill Co. v. Board of Education of City of Paterson, 130 N. J. L. 321, 322 (Sup. Ct. 1943); Franklin Lumber Co. v. Globe Indemnity Co., 102 N. J. L. 9, 12 (Sup. Ct. 1925); affirmed 102 N. J. L. 715 (E. & A. 1926). Tt is therefore clear that although plaintiff was in the class of parties entitled to sue upon the bond it was bonnd by the statutory stipulation forbidding institution of an action on the bond until 80 days after acceptance of the work by the borough. Williamsport Pinning Mill Co. v. Maryland Casualty Co., 129 N. J. L. 333 (Sup. Ct. 1943).

[192]*192Although plaintiff concededly was in contravention of the statutory stipulation in filing its action well prior to the acceptance of the work, it contends its action was nevertheless “timely” since, at the time of the pretrial conference on October 4, 1956, and when the motion for dismissal was made, on December 12, 1957, more than 80 days had elapsed from the date of the borough’s acceptance of the work. In other words, so goes the argument, the defect of prematurity existing when the action was first instituted was cured by the occurrence of acceptance and the passage of 80 days thereafter pendente lite. But a proper appreciation of the public policy underlying the statutory proscription brings in its train a rejection of the position thus urged.

The purpose of the statutory prohibition of institution of any action on the bond by materialmen and suppliers of labor until after acceptance of the project is to protect the security of the public body in the bond from depletion or impairment by prior actions against the surety “before it is known whether the contractor has faithfully performed his contract with the public board or body,” and, if not, what loss has consequently been sustained by the public body. Franklin Lumber Co. v. Globe Indemnity Co., supra (102 N. J. L., at page 12); Graybar Flectric Co. v. Manufacturers Cas. Co., 37 N. J. Super. 284, 289 (Law Div. 1955), affirmed (other grounds) 21 N. J. 517 (1956). It is thus seen that the statutory policy involved is offended by the fact that the action has been prematurely instituted and that the policy is necessarily weakened if it is to be held that the illegality of a premature action becomes spent once there is acceptance of the work and a lapse of 80 days thereafter in advance of trial. Moreover, the fact, stressed by plaintiff, that these circumstances antedated the raising of the defense of prematurity by the defendant bonding company in the action is immaterial, not only for the reason just stated, but for the additional reason that the statutory policy is not legislated for the benefit of the surety on the bond but for the protection of the public body. This also serves to answer the contention that Standard was in no way prejudiced by [193]*193the prematurity of the action. The fact that in the particular case before us the public body may suffer no injury by allowing the action to go forward against the surety is of no consequence. The statute must be interpreted and enforced in the light of its policy and of the effect of the construction contended for upon the general effectuation and vindication of that policy.

Plaintiff next argues that the defense of prematurity should have been asserted by affirmative defense in the answer or by motion addressed to the complaint; that defendant having failed to do so until the trial plaintiff was deprived of an opportunity to take a voluntary dismissal and reinstitute its action at a proper time. The speciousness of this contention lies in its overlooking the fact that the pretrial order unequivocally raised the defense of prematurity and that this was at a time when the plaintiff could indeed have discontinued the action and filed a new one free of the vice of prematurity and well within the one-year period of limitations fixed by the statute. While the defendant should, as a matter of orderly pleading, have amended its answer to include the defense of prematurity as incorporated in the pretrial order, Schlossberg v. Jersey City Sewerage Authority, 15 N. J. 360, 370 (1954) (assuming, but not deciding that the affirmative defense was required to be pleaded in the answer notwithstanding the above mentioned recital in paragraph 7 of the complaint), nevertheless the pretrial order controlled the subsequent conduct of the litigation. R. R. 4:29-1. By its contents plaintiff was fully apprised of the defect in its action well in time to take a saving course if it chose to do so.

Finally, it is urged on plaintiff’s behalf that the trial court erred in denying plaintiff’s motion at the trial to amend the pretrial order so as to include as an issue plaintiff’s contention that the defendant was estopped from setting up the defense of statutory prematurity.

The case was tried December 11 and 12, 1957.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seaboard Sur. Co. v. Bd. of Chosen Freeholders
537 A.2d 310 (New Jersey Superior Court App Division, 1988)
Miltz v. Borroughs-Shelving, a Div. of Lear Siegler, Inc.
497 A.2d 516 (New Jersey Superior Court App Division, 1985)
Hartford Fire Ins. Co. v. Riefolo Constr. Co.
390 A.2d 1210 (New Jersey Superior Court App Division, 1978)
Maurice E. Keating, Inc. v. TP. OF SOUTHAMPTON
373 A.2d 421 (New Jersey Superior Court App Division, 1977)
Myers v. Cave
150 A.2d 269 (New Jersey Superior Court App Division, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
145 A.2d 145, 52 N.J. Super. 188, 1958 N.J. Super. LEXIS 395, Counsel Stack Legal Research, https://law.counselstack.com/opinion/samuel-braens-sons-v-fondo-njsuperctappdiv-1958.