Sampson v. DCI of Alexandria

970 So. 2d 55, 2007 WL 3171250
CourtLouisiana Court of Appeal
DecidedOctober 31, 2007
Docket07-671
StatusPublished
Cited by9 cases

This text of 970 So. 2d 55 (Sampson v. DCI of Alexandria) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sampson v. DCI of Alexandria, 970 So. 2d 55, 2007 WL 3171250 (La. Ct. App. 2007).

Opinion

970 So.2d 55 (2007)

Mark SAMPSON and Alfreda Coleman Sampson
v.
DCI OF ALEXANDRIA, et al.

No. 07-671.

Court of Appeal of Louisiana, Third Circuit.

October 31, 2007.

*57 William F. Henderson, Attorney at Law, Alexandria, LA, for Defendant-Appellant, DCI of Alexandria, Inc.

Mark L. Roberts, McCoy, Roberts & Begnaud, Ltd., Natchitoches, LA, for Plaintiff-Appellee, Mark and Alfreda Sampson.

Court composed of OSWALD A. DECUIR, ELIZABETH A. PICKETT, and J. DAVID PAINTER, Judges.

PAINTER, Judge.

Defendant, DCI of Alexandria (DCI), appeals the trial court's judgment in favor of the plaintiffs, Mark and Alfreda Sampson, in the amount of $45,495.95 and the court's denial of its reconventional demand for $20,906.28, representing the balance allegedly due under a building contract.

FACTS AND PROCEDURAL HISTORY

On May 11, 2004, the parties entered a fixed-sum contract to build a house for the Sampsons. Under the term of the contract DCI agreed, in exchange for $90,000.00, to:

"furnish all LABOR, AND TOOLS necessary to construct proposed building according to plans and specifications, provided by owner as specified below:

FOR FOUNDATIONS, FRAMING AND TRIM OUT OF DWELLING

ALL MATERIAL AND EQUIPMENT ARE TO BE FURNISHED BY OWNER. All work to be completed in a workmanlike manner according to standard practices. ANY ALTERATION OR DEVIATION FROM ABOVE SPECIFICATIONS INVOLVING EXTRA COSTS WILL BE EXECUTED ONLY UPON WRITTEN CHANGE ORDERS, AND WILL BECOME AN EXTRA CHARGE OVER AND ABOVE THIS CONTRACT AMOUNT TO BE PAID 50% UPON ACCEPTANCE AND 50% UPON COMPLETION OF EACH CHANGE ORDER. The contractor shall guarantee his work for a period of (1) year from date of final acceptance by the owner. This condition does not invalidate longer periods of warranty for equipment furnished by the manufacturer with longer periods of warranty. It is agreed NO OCCUPANCY OF DWELLING SHALL BE PERMITTED UNTIL FINAL PAYMENT OF CONTRACT & ALL CHANGE ORDERS HAVE BEEN PAID IN FULL. All agreements are contingent upon strikes, accidents, or delays beyond our control. The Contractor will carry General Liability Insurance. Owner to carry fire, tornado, and other necessary insurances. Our workers are fully covered by Workmen's Compensation Insurance."

The following is undisputed: Alfreda Sampson tried to buy builder's risk insurance as required by the contract but found the prices to be prohibitively high. When she discussed this with Mike Dunn, sole shareholder and operator of DCI, he offered to obtain the insurance for a better price. He obtained the policy, and the Sampsons paid the premium. However, when Dunn obtained the policy he named DCI as the beneficiary.

Construction began with building materials supplied by the Sampsons. On September 28, 2004, DCI sent an invoice to the Sampsons showing charges as follows: *58

  Foundation in Place   $22,500.00
  Builders Risk Policy  $   910.00
  Termite Company       $ 1,153.77
  Dirt Work             $ 5,500.00
  Concrete Finishers    $ 4,391.00

The Sampsons made a payment of $30,063.77 on October 1, 2004, which did not include payment of the amount for the concrete finishers, because the Sampsons felt that the contract made DCI responsible for providing that service.

On November 23, 2004, a storm damaged or destroyed the partially constructed house. DCI made a claim against the builder's risk policy for damages in the amount of $23,221.11. Dunn testified that the claim included amounts as follows:

Materials                                     $5,709.00
Labor to remove and sort damaged materials    $3,024.00
Labor to reframe roof                         $6,430.00
Overhead and supervision                      $3,350.00
Workers' compensation and general liability
insurance and taxes                           $3,456.00
Profit                                        $2,201.92

These amounts were reduced by the policy deductible of $1,000.00. The insurance company deducted the amount claimed as profit and sent a check for $21,019.19 to DCI. DCI kept the proceeds of the insurance check.

DCI began rebuilding the house, but, on January 12, 2005, another storm destroyed the house, which was eighty-seven percent complete according to DCI's claim. DCI again made a claim against the builders's risk insurance for the following amounts:

Materials                      $45,021.77
Labor                          $35,697.52
Insurances                     $10,341.57
Matching Funds                 $ 1,341.57
Supervision                    $ 9,000.00
Insurances on Supervision      $   619.26
Matching Funds on Supervision  $   688.00
Overhead (10%)                 $10,275.40
Profit                         $10,275.40
Demolition                     $ 5,756.00

DCI began rebuilding the house, and on May 23, 2005 sent the Sampsons an invoice showing the following charges:

Framing labor                               $58,500.00
Concrete Finishers (not included in layout
and forming labor)                          $ 4,391.00
Concrete Finishers for Patio                $   882.00
Lowes for windows                           $ 2,039.80
Stine Lumber wood for windows               $   310.46
Coburn Supply Stove Top & Chimney Hood      $ 2,454.37
Payment Received                            $68,000.00
Final 10% Due Upon Completion               $ 9,000.00

On May 31, 2005, the Sampsons paid $60,000.00 but, according to the testimony of Mrs. Sampson, deliberately left out the amounts for the concrete finishers. On July 20, 2005, they made another payment of $8,000.00.

The Sampsons were billed $29,800.00 in connection with the heating and air conditioning installation. The parties do not dispute that this item was not covered by the contract between the Sampsons and DCI. However, DCI hired the subcontractor, paid them, and billed the Sampsons for the work. DCI admits that it added a $6,000.00 mark-up to the bill for the subcontractor's work.

After the second storm, while attempting to settle the insurance claim, DCI filed a lien against the Sampsons for $150,557.71. The insurance company sent Dunn a check in the amount of $117,528.74 made payable to Dunn and the mortgage holder, Hancock Bank. The Sampsons filed a petition seeking cancellation of the lien, damages and attorney's fees for the wrongful filing of the lien, damages for defective workmanship, reimbursement of the value of the salvage materials, and reimbursement of an overpayment made to DCI by the builder's risk insurer. DCI filed a reconventional demand seeking to recover amounts allegedly still owed to it under the building contract, as well as attorney's fees.

*59 After a trial on the merits, the court rendered judgment in favor of the Sampsons in the amount of $45,495.95 plus costs and attorney's fees. It further denied DCI's reconventional demands. The court gave extensive written reasons for its decision. DCI appeals.

DISCUSSION

Insurance

We first consider the question of the ownership of the insurance policy and its proceeds as this will determine whether DCI has received full payment. DCI asserts that the trial court erred in finding that the builder's risk policy covered the Sampsons and that the Sampsons still owed money on the original contract. It argues that the trial court improperly reformed the policy to make it payable to the Sampsons where DCI was the named beneficiary.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baxter v. Lewis
247 So. 3d 873 (Louisiana Court of Appeal, 2018)
Succession of McKinley
206 So. 3d 959 (Louisiana Court of Appeal, 2016)
Succession of Joe Andy McKinley
Louisiana Court of Appeal, 2016
Titus v. Wilson
186 So. 3d 255 (Louisiana Court of Appeal, 2016)
Kaylin Renee Celestine, Etc. v. Brenda Dugas
Louisiana Court of Appeal, 2013
TTV, L.L.C. v. Simmons
58 So. 3d 684 (Louisiana Court of Appeal, 2011)
Ttv, LLC v. David B. Simmons
Louisiana Court of Appeal, 2011
D & J Tire, Inc. v. Hercules Tire & Rubber Co.
598 F.3d 200 (Fifth Circuit, 2010)
Bryan D. Scofield, Inc. v. Susan A. Daigle, Ltd.
999 So. 2d 311 (Louisiana Court of Appeal, 2008)
Novelaire Technologies, LLC v. Harrison
994 So. 2d 57 (Louisiana Court of Appeal, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
970 So. 2d 55, 2007 WL 3171250, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sampson-v-dci-of-alexandria-lactapp-2007.