Saman ROW Approval

CourtVermont Superior Court
DecidedFebruary 6, 2012
Docket176-10-10 Vtec
StatusPublished

This text of Saman ROW Approval (Saman ROW Approval) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Saman ROW Approval, (Vt. Ct. App. 2012).

Opinion

STATE OF VERMONT SUPERIOR COURT - ENVIRONMENTAL DIVISION

{ In Re: Saman ROW Approval { Docket No. 176-10-10 Vtec {

Decision in On-the-Record Appeal In this on-the-record proceeding, William Basa (“Appellant”) appeals a 2010 decision by the Town of Plainfield Development Review Board (“the DRB”) granting an application for approval of a fifty-foot right-of-way in the Town of Plainfield, Vermont to Peter Saman (“Applicant”). Appellant contends that (1) the application is barred by the successive application doctrine; (2) Applicant is bound by the principles of issue and claim preclusion1; and (3) the approved right-of-way did not comply with Section 3.4 of the Town’s Interim Zoning Regulations (“the Regulations”).2 Appellant is represented by Elizabeth H. MaGill, Esq.; Applicant is represented by Thomas Hayes, Esq.; and the Town of Plainfield is represented by Robert Halpert, Esq. Background Applicant owns a 66± acre parcel of land in the Town of Plainfield, Vermont. In 2002, Applicant filed an application seeking subdivision approval before the Zoning Administrator (“the ZA”). At the same time, he also sought the Planning Commission’s approval of a fifty- foot right-of-way which crossed an adjoining lot and provided access to the 66± acre parcel. The Planning Commission denied the right-of-way, and, subsequently, the ZA denied the subdivision application as nonconforming based on insufficient road frontage and the lack of an approved right-of-way. Applicant appealed only the Planning Commission’s decision to this Court. See In re Appeal of Peter Saman, No. 83-4-02 Vtec, slip. op. at 2 (Vt. Envtl. Ct. Apr. 2, 2003) (Teachout, J.).

1 In their briefs, the parties use the terms “res judicata” and “collateral estoppel.” The Vermont Supreme Court, however, frequently refers to those terms as claim and issue preclusion, and thus we adopt its wording here. 2 Appellant also contends that approving the right-of-way requires construing Section 3.4 of the Regulations so as to undermine the frontage requirements of Section 4.2. Because this is an on-the-record appeal, however, we are limited to a review of the DRB’s Findings of Fact and Conclusions of Law. As Applicant submitted the 2010 application solely for the purpose of obtaining approval of a right-of-way but did not include a request for subdivision approval, the DRB considered only the right-of-way issue. Our review is similarly limited, and we do not consider Appellant’s arguments relating to the frontage requirements.

1 However, we reviewed both the ZA’s decision as well as that of the Planning Commission because both decisions were “issued in an interrelated manner.” Id. On appeal, we affirmed the ZA’s denial of subdivision approval based on the violation of the minimum frontage requirements. Id. at 5. However, we did not reach the merits of the request for right-of-way approval because our decision on the frontage issue rendered it moot. On April 29, 2010, Applicant filed another application (“the 2010 application”) seeking only approval of a right-of-way. This application presumably addressed the same right-of-way for which approval was sought in 2002. The application did not include a request for subdivision approval. In June and August, 2010, the DRB held two hearings to determine whether the right-of-way complied with Section 3.4 of the Regulations. During those hearings, the DRB received evidence concerning the width of the right-of-way; emergency access via the right-of-way; the right-of-way’s negative impact on wetlands, waterways, and adjacent residences; and the slope of the right-of-way. After considering the evidence, the DRB issued Findings of Facts and Conclusions of Law in which it concluded that the right-of-way complied with Section 3.4. See In re Saman Request for Right of Way Use Approval, Findings of Fact and Conclusions of Law (Town of Plainfield Dev. Review Bd. Nov. 5, 2010). The DRB unanimously approved the right-of-way but made clear that its decision was limited solely to an approval of the right-of-way and was not an approval of any proposed subdivision. Appellant then timely appealed the DRB’s decision to this Court. Standard of Review In an on-the-record appeal, our role as a tribunal reviewing the decisions of municipal panels is similar to that of the Vermont Supreme Court when reviewing appeals from administrative bodies. That is, we do not take new evidence or complete our own determination of the facts. Instead, we will uphold the DRB’s factual findings if they are supported by substantial evidence in the record. See In re Stowe Highlands Resort PUD to PRD Application, 2009 VT 76, ¶ 7, 186 Vt. 568. We will review the DRB’s legal conclusions without deference unless such conclusions are within the DRB’s area of expertise. Id. Discussion Appellant contends that (1) the application is barred by the successive application doctrine; (2) Applicant is bound by the principles of issue and claim preclusion; and (3) the approved right-of-way did not comply with Section 3.4 of the Regulations. The only issue that

2 was before the DRB, and therefore the only issue that is before us in this on-the-record appeal, is the approval of the right-of-way. We do not consider any request for subdivision approval. For the reasons detailed below, we conclude that neither the successive application doctrine nor the doctrines of issue and claim preclusion bar Applicant’s application for right-of- way approval. We also conclude that the DRB’s finding that the proposed right-of-way will not adversely impact adjacent residences is supported by substantial evidence in the record. I. Successive Application Doctrine, Issue Preclusion, and Claim Preclusion Appellant argues that the successive application doctrine as well as the principles of issue and claim preclusion bar Applicant’s 2010 application. Applicant contends that the application is not barred because it is not linked to a subdivision application and because the 2002 right-of-way decision was not decided on the merits. The principles of claim and issue preclusion generally apply to zoning proceedings. In re McGrew, 2009 VT 44, ¶ 10, 186 Vt. 37 (citing In re Carrier, 155 Vt. 152, 157-58 (1990)). However, such principles operate with more flexibility in the municipal zoning context than in the civil context. In re Ferro & Pomeroy Demo/Constr. Permit, No. 197-10-09 Vtec, slip. op. at 5 (Vt. Super. Ct. Envtl. Div. Nov. 22, 2011) (Durkin, J.) (citing In re Dunkin Donuts Site Plan Approval, 2008 VT 139, ¶¶ 7, 10–13, 185 Vt. 583 (mem.)). This flexibility is embodied in the successive application doctrine, a subset of the claim and issue preclusion doctrines that applies specifically to zoning proceedings. See Dunkin Donuts, 2008 VT 139, ¶ 7 (“[T]he ‘successive- application doctrine’ is a distinct set of preclusive rules developed specifically for zoning proceedings.” (quoting In re Armitage, 2006 VT 113, ¶ 4, 181 Vt. 241)); In re JLD Props. – Wal- Mart St. Albans, No. 116-6-08 Vtec, slip. op. at 11 (Vt. Envtl. Ct. Mar. 16, 2009) (Durkin, J.) (“This general rule, known as the ‘successive-application doctrine,’ embodies the principles of claim and issue preclusion applicable to zoning applications.”); In re Choquette Zoning Permit Amendment, No. 199-9-08 Vtec, slip. op. at 2 (Vt. Envtl. Ct. Jan. 7, 2009) (Durkin, J.) (noting that claim preclusion should not be strictly applied to zoning decisions and applying the successive application doctrine instead). The successive application doctrine prohibits a municipal panel from entertaining a second application for the same project concerning the same property after a previous application has been denied, unless there has been a substantial change of conditions. Dunkin Donuts, 2008 VT 139, ¶ 8 (quoting Carrier, 155 Vt. at 158). As in claim and issue preclusion, a

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Armitage
2006 VT 113 (Supreme Court of Vermont, 2006)
In Re Appeal of McGrew
2009 VT 44 (Supreme Court of Vermont, 2009)
State v. CNA Ins. Companies
779 A.2d 662 (Supreme Court of Vermont, 2001)
In Re Application of Carrier
582 A.2d 110 (Supreme Court of Vermont, 1990)
Department of Taxes v. Murphy
2005 VT 84 (Supreme Court of Vermont, 2005)
In Re Dunkin Donuts S.P. Approval
2008 VT 139 (Supreme Court of Vermont, 2008)
In Re Stowe Highlands Resort PUD to PRD Application
2009 VT 76 (Supreme Court of Vermont, 2009)
In re Stormwater NPDES Petition
2006 VT 91 (Supreme Court of Vermont, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Saman ROW Approval, Counsel Stack Legal Research, https://law.counselstack.com/opinion/saman-row-approval-vtsuperct-2012.