Salt Pond Associates v. United States Army Corps of Engineers

815 F. Supp. 766, 23 Envtl. L. Rep. (Envtl. Law Inst.) 21026, 36 ERC (BNA) 1922, 1993 U.S. Dist. LEXIS 3093, 1993 WL 68107
CourtDistrict Court, D. Delaware
DecidedFebruary 19, 1993
DocketCiv. A. 92-597-LON
StatusPublished
Cited by7 cases

This text of 815 F. Supp. 766 (Salt Pond Associates v. United States Army Corps of Engineers) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Salt Pond Associates v. United States Army Corps of Engineers, 815 F. Supp. 766, 23 Envtl. L. Rep. (Envtl. Law Inst.) 21026, 36 ERC (BNA) 1922, 1993 U.S. Dist. LEXIS 3093, 1993 WL 68107 (D. Del. 1993).

Opinion

OPINION

LONGOBARDI, Chief Judge.

I. BACKGROUND

This dispute stems from Plaintiffs efforts to develop a piece of land for resale as waterfront lots. On November 29,1988, the Plaintiff paid 5.5 million dollars for property located along the Town of Bethany Beach known as the Salt Pond property. Docket Item (“D.I.”) 3 at 4. In an effort to ensure that any and all federal, environmental wetlands requirements were being satisfied under the Clean Water Act (hereinafter “CWA”) and other environmental protection laws, 1 the Plaintiff (“Salt Pond”) apparently engaged in extensive consultation with the United States Army Corp of Engineers (“the Government”), 2 as well as their own environmental experts. 3 Id at 6-8. However, despite efforts by both sides to protect the “developing” interests of Salt Pond and the “environmental” interests that the Government is le-' gaily required to protect, irreconcilable disputes have arisen between the parties. These disputes, leading to Plaintiffs request *769 to. this Court for relief, center around the breadth of the Government’s regulatory jurisdiction under the circumstances presented by this case as well as the allegedly adverse impact this land development will have on the environment.

■On January 25, 1989, the Plaintiff submitted to the Government a wetlands delineation report requesting verification by the Government of its proposed section 404 wetlands delineation. Id. at 5. 4 On April 4, 1991, after Plaintiff had spent over two years towards the development of the property, the Government informed the Plaintiff that a twelve acre area of the total land was in fact under the jurisdictional control of the Government. Id,. On August 12, 1991, during an on-site inspection by the Government’s investigators, the Government determined that ten ponds (hereinafter “the ponds”) had been excavated in wetlands by the Plaintiff and that the Plaintiff had engaged in regulated land clearing in wetlands. D.I. 10 at 9.

■On October 5,1991, the Government issued a Cease and Desist letter which required the Plaintiff to discontinue any and all development of the land because of numerous environmental violations discovered during the latest on-site investigation by the Government. Id. 5 As a follow-up to that order, the Government directed the Plaintiff to apply for an “after-the-fact” permit 6 for work already undertaken and work still to be undertaken in connection with the development of the Salt Pond property. Id. at 10. 7

After significant correspondence regarding the appropriate procedural mechanisms, Salt Pond submitted to this after-the-fact permit process under full reservation of its rights in the hope that any and all environmental violations could be remedied so that the development of the land could proceed to completion. D.I. 3 at 11. Plaintiff further implored the Government to sever from the permit application consideration of Plaintiffs application for a water and sewer utility crossing permit (hereinafter “the Loop Canal permit”) pleading that the issuance of this permit under Section 10 of the Rivers and Harbors Act (hereinafter “RHA”) 8 was completely unrelated to matters pertaining to section 404 wetlands jurisdiction and the excavation of the ponds. Id. at 12. 9 The Government *770 responded by informing the Plaintiff that its request for the Loop Canal permit would only be processed in conjunction with the required “after-the-fact” permit. Id. at 13-14. 10

After giving public notice of Salt Pond’s permit application on March 25, 1992, and receiving extensive commentary on the project from environmental agencies and individual environmentalists, 11 the Government ultimately denied Salt Pond’s application on September 24, 1992, finding the project in its entirety “contrary to the general public interest.” D.I. 11, Attachment D at 19. 12 The Government offered the Plaintiff an opportunity to receive an alternative permit which would include the Loop Canal permit if Salt Pond satisfied 31 “special conditions.” Id. at 19-24. 13 The Government indicated that if this alternative permit was not accepted by the Plaintiff, then Plaintiff would have 60 days in which to initiate action for environmental restoration including the complete restoration of the excavated ponds. Id., Attachment B at 1-2. Additionally, subsequent efforts by Salt Pond to have the Loop Canal permit determination severed from the denial of the after-the-fact permit decision were once again rejected by the Government. D.I. 3 at 14 (citing the record). 14

It is the Government’s “conditional” grant of the Loop Canal permit which is at the heart of the present dispute. Particularly significant are those special conditions associated with the Plaintiffs filling in or otherwise restoring the ponds and the fact that the Loop Canal permit decision was linked to and dependent upon the pond restoration conditions. Specifically, the Plaintiff posits that the Government’s environmental findings fail to establish a “sufficient causal connection between the alleged violations and *771 the mandated corrective action.’ 12. 15 D.I. 3 at

Plaintiff contends that the Government has no section 404 jurisdiction over the excavation of these ponds because excavation is an unregulated activity for' which no Government permit is required and, that by conditioning the grant of the after-the-fact permit, including the Loop Canal permit request, upon these pond restoration conditions, the Government is attempting to improperly regulate the excavation of these ponds through some sort of “back-door” approach to the permit application process. D.I. 3 at 16-25. It is the Plaintiff’s ultimate position that any and all conditions relating to the restoration or filling of the excavated ponds are improper and that the withholding of the Loop Canal permit pending the restoration of the ponds is an improper use of the Government’s authority.

II. NATURE AND STAGE OF THE PROCEEDING

The Plaintiff has filed a motion for a preliminary injunction setting forth various demands for relief (hereinafter “Plaintiffs Motion”). D.I. 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boll v. United States Army Corps of Engineers
255 F. Supp. 2d 520 (W.D. Pennsylvania, 2003)
United States v. Mango
997 F. Supp. 264 (N.D. New York, 1998)
American Mining Congress v. United States Army Corps of Engineers
951 F. Supp. 267 (District of Columbia, 1997)
Curtis 1000, Inc. v. Youngblade
878 F. Supp. 1224 (N.D. Iowa, 1995)
MCG ASSOCIATES v. Department of Environmental Protection
650 A.2d 797 (New Jersey Superior Court App Division, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
815 F. Supp. 766, 23 Envtl. L. Rep. (Envtl. Law Inst.) 21026, 36 ERC (BNA) 1922, 1993 U.S. Dist. LEXIS 3093, 1993 WL 68107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/salt-pond-associates-v-united-states-army-corps-of-engineers-ded-1993.