Salt Meadows Homeowners Association, Inc. v. Zonko Builders, Inc.

Superior Court of Delaware·Decided January 31, 2023·No. S17C-05-018 RHR·Published

Opinion

IN THE SUPERIOR COURT OF THE STATE OF DELAWARE

SALT MEADOWS HOMEOWNERS ) ASSOCIATION, INC., et al., )

)

Plaintiffs, )

)

v. ) C.A. No. S17C-05-018 RHR )

ZONKO BUILDERS, INC., )

)

Defendant/Third-Party )

Plaintiff. )

Submitted: October 27, 2022 Decided: January 31, 2023

DECISION ON POST-TRIAL MOTIONS

Upon Defendant’s Motion for New Trial or Remittitur, GRANTED in part and DENIED in part.

Upon Defendant’s Renewed Motion for Judgment as a Matter of Law Pursuant to Delaware Superior Court Civil Rule 50(b), GRANTED.

Upon Plaintiffs’ Motion for Costs and Interest, GRANTED in part and DENIED in part.

Shannon D. Humiston, Esquire, Daniel M. Silver, Esquire, Matthew J. Rifino, Esquire, McCarter & English, LLP, Wilmington, Delaware, Attorneys for Plaintiffs Salt Meadows Homeowners Association, Inc., et al.

Colin M. Shalk, Esquire, Kenneth M. Doss, Esquire, Casarino Christman Shalk Ransom & Doss, P.A., Wilmington, Delaware, Attorneys for Defendant Zonko Builders, Inc.

ROBINSON, J.

Trial in this matter took place in May 2022 and the parties have filed several post-trial motions. Defendant Zonko Builders, Inc. filed a Motion for a New Trial or Remittitur and a Renewed Motion for Judgment as a Matter of Law. Plaintiffs filed a Motion for Costs and Interest. I. BACKGROUND AND PROCEDURAL POSTURE Salt Meadows is a twenty-unit condominium complex consisting of five separate buildings, each containing four townhome units, located in Fenwick Island, Delaware. Plaintiffs are the individual unit owners and the homeowners’ association (collectively, “Plaintiffs”). Defendant, Zonko Builders, Inc. (“Zonko”), is the contractor that oversaw construction of the project.

Construction of Salt Meadows began in September 2004 and the final certificate of occupancy was issued in April 2007. In February 2016, a homeowner discovered extensive water damage in her unit. After consulting with several engineers and contractors, Plaintiffs began the long—and still ongoing—process of repairing the buildings.

Plaintiffs filed suit in May 2017 alleging four counts: negligent construction, breach of contract, breach of express warranty, and breach of implied warranty. Among many pretrial motions, Plaintiffs filed a motion for partial summary judgment. At oral argument on this motion, this court found that Plaintiffs had

established negligence,1 but ordered further briefing as to the question of damages. This court eventually denied the partial motion for summary judgment as to damages.2 This case is unusual because the repair work is ongoing. Even with the pandemic-related delays in getting this matter to trial, Plaintiffs claimed that only a small percentage of the damage has been repaired and they sought past and future damages. As of the date of trial, Plaintiffs had paid approximately $2.4M for repairs that were made between June 2016 and April 2021.3 The parties largely agreed that amount was appropriate, and it was not seriously challenged by Zonko. The main issue for the jury, then, was the amount of future damages. Plaintiffs argued that only a small amount of the necessary repairs had been completed and that a significant amount of future damages was needed. Zonko’s position at trial was that all the necessary repairs were largely finished and that no further expenses were due beyond the $2.4M that was already incurred.

The trial began on May 2, 2022. Plaintiffs called three witnesses: Kathy Lambrow (“Lambrow”), a unit owner and president of the homeowners association; Mike Lewis (“Lewis”) of Custom Carpentry, LLC who was the contractor

1 Transcript of Oral Argument Dec. 11, 2020 at 2, 5-6, 14-15, Salt Meadows Homeowners Assoc., Inc. v. Zonko Builders, Inc., (C.A. No. S17C-05-018) (D.I. 191). 2 Salt Meadows Homeowners Assoc., Inc. v. Zonko Builders, Inc., 2021 WL 2181426 (Del. Super. May 27, 2021). The finding was clarified by a stipulated order dated September 20, 2021. 3 The exact figure was $2,458,071.00.

performing the repairs on the buildings; and Jeremy Walbert, P.E., (“Walbert”) a civil engineer from the Becker Morgan Group who consulted with the homeowners association and Lewis. Zonko called one witness, its expert, Jason Boyd, P.E. (“Boyd”).4 On May 12, the jury found in favor of Plaintiffs. The jury verdict form provided two lines for damages: one for general damages, where the jury awarded Plaintiffs $11.3M, and one line for future repairs to various columns, where the jury awarded Plaintiffs $1.6M. II. DISCUSSION A. ZONKO’S MOTION FOR NEW TRIAL AND REMITTITUR Zonko has filed a Motion for a New Trial or Remittitur for the general damages awarded. Zonko argues that the jury improperly considered testimony about inflation to award Plaintiffs more than what they were asking for. Lewis prepared an estimate dated March 15, 2019 that reflected it would cost $8.3M to complete all of the work. At the time of trial, Plaintiffs had spent approximately $2.4M to repair the most pressing damage. Lewis testified repeatedly that the March 15, 2019 estimate was imprecise, and that many of the future expenses were likely to be higher because of inflation and pandemic-era supply problems. Likewise, Walbert also testified that costs of materials were much higher than they were in March 2019 when the estimate was prepared. Zonko objected to the testimony about

4 Boyd testified out of order because of a scheduling conflict.

inflation, arguing that neither Lewis nor Walbert were qualified to testify about inflation and that neither had previously offered an opinion about the impact of inflation on the March 2019 estimate.

1. Remittitur I agree with Zonko that remittitur is warranted in this case. In considering remittitur, “the trial court must evaluate the evidence and decide whether the jury award falls within a supportable range.”5 Remittitur should be granted only when the damages are so excessive that the jury must have based its award on “passion, prejudice or misconduct, rather than on objective consideration of evidence presented at trial.”6 A jury’s verdict with respect to damages is presumed to be correct, “unless it is so grossly disproportionate to the injuries suffered so as to shock the Court’s conscience and sense of justice.”7 There are two reasons to grant remittitur in this case. First, I agree with Zonko’s speculation that the jury improperly added amounts for inflation in awarding $11.3M, which was $3M over Lewis’s estimate. Testimony about inflation and added costs related to the pandemic were improperly put before the jury, albeit incrementally. Lambrow initiated this problematic line of testimony by testifying generally about the uncertainty of how much it would cost to complete

5 Reid v. Hindi, 976 A.2d 125, 131 (Del. 2009) (citation omitted). 6 Barba v. Boston Sci. Corp., 2015 WL 6336151, at *9 (Del. Super. Oct. 9, 2015). 7 Maier v. Santucci, 697 A.2d 747, 749 (Del. 1997).

Free access — add to your briefcase to read the full text and ask questions with AI

Salt Meadows Homeowners Association, Inc. v. Zonko Builders, Inc., (Del. Ct. App. 2023).

Salt Meadows Homeowners Association, Inc. v. Zonko Builders, Inc. (Salt Meadows Homeowners Association, Inc. v. Zonko Builders, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Burgos Ex Rel. Burgos v. Hickok
695 A.2d 1141 (Supreme Court of Delaware, 1997)
Reid v. Hindt
976 A.2d 125 (Supreme Court of Delaware, 2009)
Storey v. Camper
401 A.2d 458 (Supreme Court of Delaware, 1979)
Perry v. Berkley
996 A.2d 1262 (Supreme Court of Delaware, 2010)
Maier v. Santucci
697 A.2d 747 (Supreme Court of Delaware, 1997)
Young v. Frase
702 A.2d 1234 (Supreme Court of Delaware, 1997)