Salmon v. Flacke

113 Misc. 2d 640, 449 N.Y.S.2d 610, 1982 N.Y. Misc. LEXIS 3354
CourtNew York Supreme Court
DecidedApril 13, 1982
StatusPublished
Cited by2 cases

This text of 113 Misc. 2d 640 (Salmon v. Flacke) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Salmon v. Flacke, 113 Misc. 2d 640, 449 N.Y.S.2d 610, 1982 N.Y. Misc. LEXIS 3354 (N.Y. Super. Ct. 1982).

Opinion

OPINION OF THE COURT

Vincent E. Doyle, J.

This matter came before this court by an order to show cause signed by the Honorable Norman J. Wolf and granted on January 8,1982. The petitioner seeks an order: (1) voiding the grant by the New York State Department of Environmental Conservation (DEC) of a permit to respondent, Chaffee Landfill, Inc. (Chaffee), to operate a solid waste management facility in the Town of Sardinia which was issued on November 5, 1981; (2) voiding DEC’s grant of a variance to that permit issued on November 31, 1981; and (3) enjoining the disposal of any Buffalo Sewer Authority (BSA) sewer sludge cake at the landfill until such time as a proper permit and variance is issued.

Turning first to the first affirmative defense raised by Chaffee in its answer, this court must consider whether the petitioner is the real party in interest and whether he has standing to commence this proceeding. Generally, a party pleading a defense has the burden of proving it (Moncel [642]*642Realty Corp. v Whitestone Farms, 188 Misc 431, 433, affd 272 App Div 899; see, also, 3 Weinstein-Korn-Miller, NY Civ Prac, par 3018.14). Chaffee, while citing the Town Law (§ 65) as authority to support its first affirmative defense, has failed to submit any proof showing that the petitioner brings this proceeding without a direction from the Town Board of the Town of Sardinia. Nor Has Chaffee shown that the petitioner individually lacks standing to bring this proceeding. This court therefore holds the petitioner is a proper party and has standing".

Chaffee’s third affirmative defense is that this proceeding is barred by CPLR 217. CPLR 217 requires a proceeding against a body or officer to be commenced within four months after the determination to be reviewed becomes final. Since the instant proceeding was commenced well within four months after the issuance of both the permit and variance, this court finds Chaffee’s third affirmative defense to be without merit.

Chaffee also raises the defense of loches in its answer. A permit to construct a solid waste management facility in the Town of Sardinia was issued to Chaffee on July 28, 1981. Chaffee claims that the then Supervisor of the Town of Sardinia and the Town of Sardinia’s Town Board had notice of the issuance of the construction permit and were aware that upon compliance with the conditions of the construction permit, an operation permit would be granted. Hence, it argues that because the petitioner’s predecessor in office and the town board failed to begin this proceeding shortly after the issuance of the construction permit on July 28, 1981, and prior to the expenditure of large sums of money necessary to comply with the conditions of the construction permit, the petitioner should be barred from maintaining this proceeding.

Generally, the defense of loches is available to a defendant if the plaintiff has unreasonably delayed in bringing the proceeding and the delay has caused prejudice to the defendant. In this case, the petitioner’s predecessor in office and the town board apparently did register on July 22, 1981, through their attorney, at least one complaint with DEC about Chaffee’s application for a permit to construct and to operate. The respondents therefore have [643]*643been aware of the town’s disapproval of the operation permit since July, 1981. The petitioner does not now urge that the solid waste management facility be permanently closed or that the landfill should be forever prohibited from accepting BSA sewer sludge cake, but instead urges that Chaffee was required to follow certain procedures when it sought an operation permit and variance, and should be made to follow those procedures in the future.

Moreover, in light of the serious question concerning the protection of the environment that this case presents, and in light of DEC’s continuing obligation to obey statutory directives, regardless of whether it is faced with a lawsuit, this court is compelled to dismiss Chaffee’s defense of laches (accord City of Davis v Coleman, 521 F2d 661, 673; Steubing v Brinegar, 511 F2d 489).

This court will next examine the petitioner’s contentions. His first claim is that DEC lacked authority to grant the operation permit dated November 5, 1981 because Chaffee had not submitted a complete application (see 6 NYCRR 360.3 [b] [1]). Section 360.3 (b) (2) mandates that every application include a “contingency plan setting forth in detail the applicant’s proposal for corrective or remedial action to be taken in the event of equipment breakdowns, ground or surface water or air contamination attributable to the facility’s operation, fires, explosions and spills or releases of hazardous or toxic materials.” Petitioner claims that such a contingency plan is missing from the permit application file of Chaffee Landfill at the DEC. Respondents Flacke and Spagnoli assert that the necessary contingency plans are set forth in the engineering report submitted by Chaffee as part of its permit application.

The incorporation of contingency plans within the engineering report, however, does not fulfill the regulation’s clear requirement nor does it promote the policy reasons behind the regulation. By scattering the so-called plans throughout the engineering report, under various titles, Chaffee has made them less than accessible for consultation by persons in charge during an emergency and less than accessible for review and possible constructive criticism by DEC and the public.

[644]*644Accordingly, this court holds that the DEC acted without authority when it issued the operation permit to Chaffee before Chaffee had submitted an application complete with a contingency plan.

Petitioner also takes issue with DEC’s failure to consider the environmental impact of permitting Chaffee to operate the landfill as required under ECL article 8 (commonly known as the State Environmental Quality Review Act or SEQRA) and as required under 6 NYCRR Part 617. Respondents Flacke and Spagnoli urge that Chaffee’s operation permit was excluded from SEQRA’s application because of the approval of the landfill in 1958 by the Erie County Department of Health.

ECL 8-0111 (subd 5) excludes actions undertaken or approved prior to the effective date of article 8 from the required preparation of an environmental impact statement (ECL 8-0109, subd 2). “Actions” are defined to include, inter alia: “(i) * * * projects or activities involving the issuance to a person of a leáse, permit, license, certificate or other entitlement for use or permission to act by one or more agencies.” (ECL 8-0105, subd 4.) SEQRA or ECL article 8 was made effective September 1, 1976.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Salmon v. Flacke
91 A.D.2d 867 (Appellate Division of the Supreme Court of New York, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
113 Misc. 2d 640, 449 N.Y.S.2d 610, 1982 N.Y. Misc. LEXIS 3354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/salmon-v-flacke-nysupct-1982.