Salemi v. Duffy Construction Corp.

197 N.E.2d 397, 94 Ohio Law. Abs. 196, 31 Ohio Op. 2d 482, 1964 Ohio App. LEXIS 619
CourtOhio Court of Appeals
DecidedMarch 26, 1964
DocketNo. 26635
StatusPublished
Cited by2 cases

This text of 197 N.E.2d 397 (Salemi v. Duffy Construction Corp.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Salemi v. Duffy Construction Corp., 197 N.E.2d 397, 94 Ohio Law. Abs. 196, 31 Ohio Op. 2d 482, 1964 Ohio App. LEXIS 619 (Ohio Ct. App. 1964).

Opinions

Wasserman, J.

This case is before this court on an appeal on questions of law from a jury verdict of $185,000.00 and judgment entered thereon in the Court of Common Pleas of Cuyahoga County against defendant, Duffy Construction Corporation, in favor of the plaintiff, Peter L. Salemi. For the purpose of brevity, Peter L. Salemi, plaintiff-appellee, will hereafter be referred to as plaintiff and Duffy Construction Corporation, defendant-appellant, will be referred to as defendant.

Plaintiff was an individual engaged in the business of grading and excavating contract work under the name of the Central Excavating Company. Defendant had entered into a general contract with the G-eneral Electric Corporation for the construction of a plant on premises bordering on Highland Road in the Village of Richmond Heights in Cuyahoga County. [200]*200Plaintiff obtained a subcontract from tbe defendant to perform tbe excavating and grading work on tbe project. Tbe property in question was located to the south of Highland Road. These premises contained a driveway leading from Highland Road. The driveway was approximately 12 to 15 feet wide and approximately 400 feet long. The terrain on each side of the driveway was level for an estimated 20 feet. Throughout the proceedings in the trial court this driveway was referred to as “the existing driveway” and was used by all persons engaged in the work on the construction project.

The plan for construction called for a new driveway to the east of the existing one and parallel to the one in use. It was intended to replace the existing driveway when the new driveway had reached a point in construction when the sub-base was laid down. The existing driveway would then be excavated for the purpose of placing a storm sewer within the excavation and would then be recovered.

The testimony indicates that on October 7, 1956, at 6:00 P. M., the sub-base had not been laid down on the new driveway and the existing driveway was still in full use.

At the time of the accident, there were three contractors concerned with the undertaking. These were the defendants as the general contractor, the plaintiff as the grading and excavating contractor, and the Norton Construction Company as the sewer sub-contractor.

Prior to the time of the accident, the Norton Construction Company was occupied with a trench excavation near Highland Road approximately 450 feet west of the existing driveway. On this job it was using a device called a backhoe. The plaintiff had placed grading and excavating equipment on the premises.

The defendant was to erect a field office and was to provide temporary toilet facilities under its General Electric contract. The location of these facilities was not shown on any plans with which the plaintiff was familiar. The location of the field office, and the septic tank to be used by the toilet facilities, was left to the discretion of the defendant subject only to the approval of the General Electric Company.

The contract between the defendant and the General Electric Company was a guaranteed maximum contract with a com[201]*201pletion clause. Tbe completion clause provided: “Time is of the essence of the contract.” It further provided that if the cost of the work, plus fixed fees, be less than the guaranteed maximum, the difference representing the saving was to be apportioned to a specific percentage between the defendant and the G-eneral Electric Company.

Plaintiff, through his subcontract, had a unit price agreement under which he was to be paid in accordance with the amount of earth moved rather than on a time basis. There was a schedule prepared by the defendant in the plaintiff’s contract which contained a “time is of the essence clause.”

There was testimony that the plaintiff was under pressure from the defendant. He, therefore, kept his crew working six days a week with overtime everyday of the week. Francis F. Duffy, President of the defendant corporation, testified that his construction supervisor kept a separate sheet of plaintiff’s progress and the amount of equipment plaintiff had on the job “due to the fact that winter was not far away and we wanted to have the work progress so that we could get our foundation in and our steel erected before the very bad weather set.”

The evidence shows that the plaintiff would personally visit the scene of his various projects to check with his works’ foreman, that on Saturday, October 6, 1956, plaintiff visited the scene of this project, arriving at approximately 1:30 P. M., and that his purpose in going to the premises was to make the necessary field changes on the job and to discuss these with his on-the-job foreman and to discover if the defendant construction superintendent wanted anything particularly done. It also shows that at the time of the plaintiff’s visitation, the weather was dry as it had been during the course of the work on this project and that he noticed that the backhoe of Norton was still working near Highland Road approximately 450 feet from the existing driveway.

The evidence establishes that late in the afternoon of October 6th, defendant’s construction superintendent decided to have constructed an excavation for the septic tank system, that the temporary field office had already been substantially erected at a distance of 26 feet west of the existing driveway, that Mr. Kenneth C. Olsen, the defendant’s superintendent, arranged with Norton to lease his backhoe and crew for the time neces[202]*202sary to make the excavation, that Norton proceeded to make the excavation in accordance with instructions and location designated by Mr. Olsen. It is undisputed in the record that the crew making the excavations was at all times under the direction and control of defendant and was acting as its agents and employees. The evidence further indicates that the septic tank excavation was dug along the westerly side of the existing driveway approximately 200 to 300 feet south of Highland Road, that this hole was approximately 6 to 8 feet wide, 10 to 12 feet long and about 7 feet deep, that to the north of the septic tank excavation and forming a part of it was a filter bed trench which was approximately the same width but not so deep, and that this trench ran parallel to the existing highway for a distance of 30 feet. According to Mr. Duffy’s testimony, the easterly border of the hole was within inches of the driveway. The evidence also indicates that the plaintiff was completely ignorant of these arrangements, that the continued use of the existing driveway resulted in the driveway being packed down together with the adjacent terrain so that there was no well-defined border to the driveway, that after the Norton Crew finished the work for the defendant, the backhoe was returned to its former position as hereinbefore described, that Norton was paid by the defendant for the time used to make these excavations, that at the close of the construction day, Saturday, October 6, 1956, the septic tank hole and adjacent filter bed trench had been completely constructed and was left without any form of barricade or warning lights, and that the fill from the excavation was placed on the westerly side of the trench in the form of a windrow of earth.

The evidence also establishes that Saturday night, October 6, 1956, it rained hard and that mud caused by heavy rain materially affects work of an excavating contractor, necessitating change in the plan and procedure of his work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doloughty v. Blanchard Const. Co.
352 A.2d 613 (New Jersey Superior Court App Division, 1976)
Otts v. Brough
409 P.2d 95 (Idaho Supreme Court, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
197 N.E.2d 397, 94 Ohio Law. Abs. 196, 31 Ohio Op. 2d 482, 1964 Ohio App. LEXIS 619, Counsel Stack Legal Research, https://law.counselstack.com/opinion/salemi-v-duffy-construction-corp-ohioctapp-1964.