Saint Francis Hospital v. B T Contractors, No. Cv96 0564910 (Jan. 3, 1997)
This text of 1997 Conn. Super. Ct. 92 (Saint Francis Hospital v. B T Contractors, No. Cv96 0564910 (Jan. 3, 1997)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Saint Francis Hospital is the owner of real estate located in Hartford, Connecticut. Gilbane was the Hospital's construction manager for its construction project. The defendants B T Contractors on August 13, 1996 and Nobel Insurance Company on August 14, 1996 each filed mechanic's liens on the property involved in the construction project. On August 22, 1996, Gilbane requested in writing, and by certified mail, return receipt requested, that the liens be discharged. When the defendants failed to release the liens the instant application was filed.
The defendants cite Roundhouse Construction Corp. v. TelesecoMasons Supplies Co.,
This court does not read Sections
Legislation passed in 1975 put in place Sections
Accordingly, this court holds that there is subject matter jurisdiction to proceed with a hearing and denies the motion to dismiss.
Mary Hennessey, J. CT Page 94
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
1997 Conn. Super. Ct. 92, Counsel Stack Legal Research, https://law.counselstack.com/opinion/saint-francis-hospital-v-b-t-contractors-no-cv96-0564910-jan-3-1997-connsuperct-1997.