Sagl v. Hirt

52 N.W.2d 721, 236 Minn. 281, 1952 Minn. LEXIS 653
CourtSupreme Court of Minnesota
DecidedApril 4, 1952
Docket35,620
StatusPublished
Cited by4 cases

This text of 52 N.W.2d 721 (Sagl v. Hirt) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sagl v. Hirt, 52 N.W.2d 721, 236 Minn. 281, 1952 Minn. LEXIS 653 (Mich. 1952).

Opinion

Thomas Gallagher, Justice.

Action by William Sagl, doing business as Electric Motor Service, as plaintiff, against Edward G. Hirt, defendant, upon an implied contract for the reasonable value of work and labor furnished by plaintiff to defendant in connection with the construction of a laundry building at the Veterans Hospital in St. Cloud. Defendant was contractor for the general construction thereof under an agreement with the United States of America and had sublet the electrical work thereon to plaintiff.

The principal dispute between the parties, both here and at the trial, is whether plaintiff under his subcontract was bound to refill certain trenches which he had excavated for installation of the *283 required electrical ducts. He insists that, while his contract did not cover this phase of the work, upon defendant’s demand he had refilled the trenches with the expectancy that he would be compensated for the reasonable value of the labor furnished in connection therewith.

The trial court, after hearing the evidence, determined that this work was not within the terms of plaintiff’s subcontract and that he was entitled to an award against defendant in the sum of $2,'759.83, the reasonable value thereof, plus costs and interest from the date of completion of the work. This is an appeal from the judgment subsequently entered for the amounts thus awarded.

Defendant’s general contract with the United States was entered into in June 1947. On June 23, 1947, plaintiff submitted to him a proposal in writing under which plaintiff proposed to “do the electrical work for the laundry building as per plans and specifications” for a specified sum. This proposal was accepted by defendant June 26, 1947.

In agreements of this kind the United States does not recognize subcontractors, but looks to the general contractor exclusively for responsibility for performance of the entire project. Sections 1(b) and 1(c) of the specifications, made a part of the general contract, respectively provide:

“(b) All work required in connection with the utility services for work of the project shall be as specifically required under applicable sections of the specifications, such as ‘Plumbing’, ‘Heating’, ‘Ventilation’, ‘Electrical Work’, ‘Laundry Equipment’, Etc.
“(c) Except as otherwise specifically noted, all filling, backfilling and grading required by any existing conditions or new construction work shall be performed by the Contractor for general construction.”

With reference to the electrical work, the specifications further provide:

“801-3. Underground Ducts: * * *
“(a) Method of Application: Laid in neatly cut trench uniformly graded 3 inches per 100 feet, minimum, toward manholes. *284 Top of ducts shall be 24 inches below finished grade (30 inches under roads). Ducts shall be encased in 1:3:6 mix concrete envelope (Type B’ concrete) with 3 inches (minimum) wall thickness and with pre-cast concrete separator blocks at each joint.”

Plaintiff entered upon the performance of his contract and excavated certain trenches so that the electrical ducts might be laid therein in accordance with the specifications. After this work was completed and at a time when the excavated dirt was still alongside the trenches, a conversation between plaintiff and defendant took place as follows:

“Q. And there was a talk with Mr. Hirt then about backfill?
"A. Yes.
“Q. What was that talk?
“A. Mr. Hirt said I should do the backfill.
“Q. What did you say?
“A. I told him I did not have anything to do with the backfill or his job. He says he was going to find out.
“Q. When did you next talk with him about the backfilling?
"A. That happened in the summer of 1948, about May or June, something like that.
“Q. What was said at that time?
“A. He asked me why I did not proceed with the backfill.
"Q. And what did you say?
"A. I told him I am not doing the backfill according to my contract and break-down and specifications.
“Q. And you refused to do it?
“A. Yes.
"Q. And he insisted you do it?
*285 “A. He told me lie was going to take it up with Mr. Nichols and see what could he done.
“Q. * * * When did you talk with him again?
“A. Probably a couple of [or] three weeks later, he told me then—
“Q. What did he say then?
“A. That I had the laborers that were not doing much and I should proceed with the backfilling.
“Q. He said you had labor?
“A. Laborers.
“Q. That wasn’t doing very much and you to go ahead and do the backfill?
“A. Yes.
“A. And so I proceeded to backfill.
“Q. And you say you did go ahead with it?
“A. I decided to go ahead with it and charge him for it.”

On appeal, defendant asserts (1) that under the terms of the written contract and specifications plaintiff was required to refill the trenches; (2) that, if not,-then plaintiff’s actions in refilling them were those of a volunteer and, as such, could not form the basis for an implied contract; and (3) that the court improperly .awarded interest on plaintiff’s claim prior to its determination at the trial.

We believe that under the specific terms of the general contract and specifications under which plaintiff performed his subcontract no obligation rested upon him to refill the trenches on the project. While under ordinary circumstances a. contractor making excavations in the performance of work required under his agreement might be expected to be required to refill them, such is not the case where the written instruments otherwise provide. Here, plaintiff’s bid was based upon specific provisions of the general contract and specifications with reference to the labor and material *286 required to be furnished in connection with the electrical work. As indicated, these provided:

“Except as otherwise specifically noted, all filling, backfilling and grading required by any existing conditions or new construction wurk shall be performed by the Contractor for general construc tion(Italics supplied.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
52 N.W.2d 721, 236 Minn. 281, 1952 Minn. LEXIS 653, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sagl-v-hirt-minn-1952.