Sage Street Associates v. Northdale Construction Co.

889 S.W.2d 400, 1994 WL 457291
CourtCourt of Appeals of Texas
DecidedOctober 6, 1994
DocketB14-90-00311-CV
StatusPublished
Cited by4 cases

This text of 889 S.W.2d 400 (Sage Street Associates v. Northdale Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sage Street Associates v. Northdale Construction Co., 889 S.W.2d 400, 1994 WL 457291 (Tex. Ct. App. 1994).

Opinion

OPINION ON REMAND FROM THE SUPREME COURT OF TEXAS

MURPHY, Justice.

This case comes before us on remand to determine the sufficiency of the evidence to support the jury’s finding of damages in favor of appellee Northdale Construction Company. We find the evidence is sufficient, and affirm.

The Supreme Court of Texas has extensively reviewed the facts of this case in its opinion reported at 863 S.W.2d 438. In short, a construction contract was entered into between Northdale, through its president Robert B. Evans, and Sage Street Associates, through its general partner Marvin B. Myers. Federal Insurance Co. was the bonding company involved in the construction project. The contract called for North-dale to build a high-rise apartment building for Sage Street. During the construction, disputes arose between the parties, which culminated in Sage Street terminating Northdale from the project. The parties filed separate suits which were consolidated for trial. The jury found that Northdale was entitled to damages of $2,491,110 due to Sage Street’s wrongful termination of the contract.

This Court affirmed the jury’s award, holding that testimony supported a damage figure greater than the jury’s finding. Sage St. Assoc. v. Northdale Constr. Co., 809 S.W.2d 775, 778 (Tex.App.—Houston [14th Dist.] 1991). The Texas Supreme Court remanded the case, finding that this Court erred in failing to apply the appropriate review standard to the issue of whether the evidence was sufficient to support the jury’s award. Sage St. Assoc. v. Northdale Constr. Co., 863 S.W.2d 438, 447 (Tex.1993). According to the supreme court’s opinion, our task is to determine whether the evidence is sufficient to support the damage award “under the theory submitted to the jury.” Id.

In reviewing a factual insufficiency challenge, the appellate court must consider all of the evidence in the record, both supporting and contrary to the judgment. Plas-Tex, Inc. v. U.S. Steel Corp., 772 S.W.2d 442, 445 (Tex.1989). After considering and weighing all the evidence, the court should set aside the verdict only if it is so contrary to the overwhelming weight of the evidence as to be clearly wrong and unjust. Cain v. Bain, 709 S.W.2d 175, 176 (Tex.1986). It is up to the jury, as trier of fact, to judge the credibility of witnesses, and resolve conflicts and inconsistencies in testimony. Lee-Wright, Inc. v. Hall, 840 S.W.2d 572, 579 (Tex.App.—Houston [1st Dist.] 1992, no writ). This court is not a factfinder, and we may not substitute our judgment for that of the jury, even if a different answer could be reached on the evidence. St. Paul Medical Ctr. v. Cecil, 842 S.W.2d 808,813 (Tex.App.—Dallas 1992, no writ); Barras v. Monsanto Co., 831 S.W.2d 859, 866 (Tex.App.—Houston [14th Dist.] 1992, writ denied).

Because we are to determine the sufficiency of the evidence under the theory submitted to the jury, we examine the court’s charge to establish what the jury was asked to take into consideration in making its decision. The charge submitted to the jury on the damages issue stated:

What sum of money, if any, do you find from a preponderance of the evidence is due to Northdale from Sage Street pursuant to the contract for the work it performed, its overhead, and its profit, if any.

The jury answered: $2,491,110.00. We find there is ample evidence in the record to support this damage award.

The jury was first asked to calculate the amount of money owed Northdale for the work it performed. There is some disagreement in the record as to what this value was. Robert Evans, president of Northdale, testified that Northdale spent approximately $13.1 million before it was terminated. This number is supported by Northdale’s cost report for 1985, which shows expenditures on the project of $13,113,553. 1 On the other hand, Northdale’s last pay application shows expenditures totalling $12,625,770, to which is added unpaid change orders in the amount of *402 $328,099 and unpaid utilities and testing of $59,314, for a total of $13,013,183.

There is also a disagreement about how much Northdale had been paid by Sage Street before the termination. Northdale’s last pay application supports a figure of $11,-014,165, while Sage Street’s check disbursements show a total of $11,103,204, including a payment of $89,039 at the closing of the contract. These figures result in four possible calculations of amounts for what North-dale was owed pursuant to the work it performed on the project prior to termination: (1) $13,113,553 - 11,014,165 = $2,099,388; (2) $13,113,553 - 11,103,204 = $2,010,349; (3) $13,013,183 - 11,014,165 = $1,999,018; or (4) $13,013,183 - 11,103,204 = $1,909,979.

The jury was also asked to consider Northdale’s overhead and profit, if any. The above values for work performed are all below the damages awarded by the jury; therefore, the next issue for us to decide is whether the evidence was sufficient to support a finding that the parties intended for North-dale to receive a $760,000 profit in addition to what it was owed for the work performed.

Robert Evans testified that he specifically discussed the $760,000 profit with Marvin Myers, Sage Street’s general partner and representative. Myers told Evans that the profit was “sacred,” and Northdale would receive the costs of the project plus $760,000, no matter what the project ultimately cost. This testimony was corroborated by Michael Roszyk of Skyline Construction Management, and by George Willock, Northdale’s former manager of marketing, both of whom were present for the meeting at which Myers made the “sacred” remark. Myers testified that he only guaranteed that profit up to the contract price of $13,535,000, but if the costs of the project went over the contract price, Northdale’s profit would be reduced accordingly. No witnesses or documentary evidence corroborated Myers’s interpretation of the parties’ agreement.

The two contracts on which the dispute is based were contradictory and ambiguous as to the $760,000 profit. The first contract was signed on March 7, 1984, and within itself contained inconsistent clauses. One clause in the contract stated that Sage Street was to pay Northdale $13,535,000, or the cost of the work certified to HUD, whichever was smaller. However, another clause stated that Northdale was to receive $760,000 without regard to costs, through an overhead allowance of $261,159.00, and $498,841.00 in profit and overhead through a subcontract with a Northdale affiliate. 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sage Street Associates v. Federal Insurance Co.
43 S.W.3d 100 (Court of Appeals of Texas, 2001)
Sage Street Associates v. Northdale Construction Co.
956 S.W.2d 583 (Court of Appeals of Texas, 1997)
Sage Street Associates v. Northdale Construction Co.
937 S.W.2d 425 (Texas Supreme Court, 1997)
Peter v. Ogden Ground Services Inc.
915 S.W.2d 648 (Court of Appeals of Texas, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
889 S.W.2d 400, 1994 WL 457291, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sage-street-associates-v-northdale-construction-co-texapp-1994.